eng8 2-3-2 bloc 1c (sa).rtf f1b.pdf
Стр. 1–2
Translation from Romanian into English
2026-408
Reconstruction of the terminal building
of “Eugen Doga” International Airport
- Chisinau (cadastral no.
0100120.236.01), including partial
replanning of internal spaces and
building extension
Form No. 1B
(name of the facility) WinEstimate
Cost Estimate-Offer No. 2-3-2
BLOCK 1C Phase 4
Architectural (A section)
(name of works)
Coefficient for basic wages = 1,150
Coefficient for cost of machine operation = 1,150
No. Norm
symbol and
resource
code
Description of works
Unit of
measure
(U.M.)
Quantity
according to the
design data
1 2 3 4 5
1. Demolition Works
1 RCsO56A
Dismantling: timber joinery (windows)
m² 34,50
7422010060100 Carpenter (joiner) man-
hours
12,696
9310060019920 Worker servicing ST man-
hours
12,696
2 RCsO56A
Demolitions: timber joinery (exterior
doors)
m² 15,20
7422010060100 Carpenter (joiner) man-
hours
5,594
9310060019920 Worker servicing ST man-
hours
5,594
3 RCsO56A
Demolitions: timber joinery (exterior
doors)
m² 44,60
7422010060100 Carpenter (joiner) man-
hours
16,413
9310060019920 Worker servicing ST man-
hours
16,413
4 RCsG32C
Dismantling of masonry walls made of
solid bricks, Autoclaved Aerated
Concrete (AAC), ceramic or lightweight
m³ 155,83
1 2 3 4 5
concrete blocks, Gypsum Fiber Panels
(GVP), excluding scaffolding and
cleaning of bricks / brick walls 250 mm
thick
7122050013400 Bricklayer man-
hours
98,562
9310060019920 Worker servicing ST man-
hours
815,38
4100126202818 Water m³ 18,70
2922140006702 Window crane machine-
hours
14,336
5 CL55A
applicative
DISMANTLING of ventilated façade
system with cladding of 600 × 600 mm
ceramic granite tiles with visible fixing (k
= 0.5)
Coefficient for labour input = 0,500
Coefficient for materials = 0,500
Coefficient for machines = 0,500
m² 373,00
9310060019930 Worker man-
hours
1 108,836
2952160007200 Lifting equipment for finishing works machine-
hours
79,206
3410520001102 Truck crane 10 ton-force (tf) machine-
hours
10,23
2952270007609 Electric drilling machine machine-
hours
144,342
2940520004058 Disc cutting machine machine-
hours
1,651
2940520007688 Grinding machine machine-
hours
11,367
6 RpIzC43A
Removal of insulation executed with
mineral wool boards or similar.
m² 598,80
7134050013240 Thermal insulator man-
hours
103,293
9310060019920 Worker servicing ST man-
hours
220,358
2320146200700 Kerosene l 5,988
1711317309326 Cleaning rags kg 17,964
2922140006705 Window crane, capacity 0.0018 meganewtons
(MN) (0.18 ton-force (tf))
machine-
hours
13,772
7 RCsK41C
Removal of rigid floor finishes made of
concrete slabs, marble, stone, porcelain
stoneware, ceramic tiles, etc. / PVC tiles
Gerflor, t = 5 mm
m² 225,20
7132040012700 Parquet layer man-
hours
101,00
Стр. 2–4
of rigid floor finishes made of concrete slabs, marble, stone, porcelain stoneware, ceramic tiles, etc. / PVC tiles Gerflor, t = 5 mm m² 225,20 7132040012700 Parquet layer man- hours 101,002 9310060019920 Worker servicing ST man- hours 101,002 4100126202818 Water m³ 11,26 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 12,949 1 2 3 4 5 8 RCsK41A Removal of rigid floors made of concrete or cement mortar / cement-sand screed laid to slope, 45–105 mm m² 255,20 7132040012700 Parquet layer man- hours 44,022 9310060019920 Worker servicing ST man- hours 44,022 4100126202818 Water m³ 12,76 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 11,739 9 RpIzC40A Removal of waterproofing executed cold or hot, on horizontal, inclined or vertical surfaces, in 1–3 layers of bituminous felt, fabric or felt, including the thermal insulation layer (polystyrene, 20 mm) Small materials (rags, brooms, etc.) as a percentage of material value = 1,200 m² 255,20 7134030012200 Waterproofing installer man- hours 73,37 9310060019920 Worker servicing ST man- hours 528,264 4100116202818 Water for mortars and concrete m³ 15,312 2320146200700 Kerosene l 30,624 2922140006705 Window crane, capacity 0.0018 meganewtons (MN) (0.18 ton-force (tf)) machine- hours 44,022 10 RCsO56B Dismantling: wall and ceiling panelling made of wood, plywood, hardboard (PFL), particleboard (PAS), etc. / dismantling of gypsum plasterboard partition walls m² 528,00 7422010060100 Carpenter (joiner) man- hours 431,112 9310060019920 Worker servicing ST man- hours 285,384 11 RCsG32A Demolition of masonry walls made of brick or Autoclaved Aerated Concrete (AAC), 6–8 cm thick / brick partition walls 120 mm m² 36,30 9310060019920 Worker servicing ST man- hours 77,228 4100126202818 Water m³ 0,363 2922140006702 Window crane machine- hours 2,505 12 RCsO56A Demolitions: timber joinery (interior doors) m² 34,70 7422010060100 Carpenter (joiner) man- hours 12,77 9310060019920 Worker servicing ST man- hours 12,77 1 2 3 4 5 13 RCsK41C Removal of rigid floor finishes made of concrete slabs, marble, stone, porcelain stoneware, ceramic tiles, etc. / ceramic granite flooring m² 22,00 7132040012700 Parquet layer man- hours 9,867 9310060019920 Worker servicing ST man- hours 9,867 4100126202818 Water m³ 1,10 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 1,265 14 RpCO56C Demolitions: cladding made of wood, asbestos cement, hardboard, particleboard, etc., on walls or suspended ceilings, doors, etc. / suspended ceiling m² 243,50 7422010060100 Carpenter (joiner) man- hours 36,403 9310060019922 Service worker man- hours 33,603 15 RCsI41B Dismantling of roof elements – profiled sheet metal roofing m² 591,40 7213
Стр. 4–5
7422010060100 Carpenter (joiner) man-
hours
36,403
9310060019922 Service worker man-
hours
33,603
15 RCsI41B
Dismantling of roof elements – profiled
sheet metal roofing
m² 591,40
7213050013100 Tinsmith man-
hours
380,862
9310060019920 Worker servicing ST man-
hours
244,84
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
13,602
16 RCsI41F
Dismantling of roof elements –
bituminous membranes in one or two
layers
m² 591,40
7213050013100 Tinsmith man-
hours
455,674
9310060019920 Worker servicing ST man-
hours
204,033
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
40,807
17 RCsG32C
Dismantling of masonry walls made of
solid bricks, Autoclaved Aerated
Concrete (AAC), ceramic or lightweight
concrete blocks, Gypsum Fiber Panels
(GVP), excluding scaffolding and
cleaning of bricks /brick parapet 250 mm
m³ 3,70
7122050013400 Bricklayer man-
hours
2,34
9310060019920 Worker servicing ST man-
hours
19,36
4100126202818 Water m³ 0,444
2922140006702 Window crane machine-
hours
0,34
1 2 3 4 5
18 TrB01A1-
5
Transportation of materials from Group
1–3 (loading, stacking, unloading,
stacking), with pneumatic wheelbarrows,
over a distance of 50 m
tonne 453,00
9310060019900 Unskilled worker man-
hours
562,626
19 TrI1AA02
C2
Loading of materials from Group A –
heavy, in lumps by throwing – from ramp
or ground, into truck category 2
tonne 453,00
9310060019900 Unskilled worker man-
hours
234,427
20 TsI51A10
Transportation of construction debris by
10 tonne dump truck over a distance of
10 kilometres
tonne 453,00
3410540000007 Dump truck, 10 tonnes machine-
hours
29,746
Total Demolition Works
2. Walls
21 CK22B
Aluminium profile glazed partitions in
constructions with heights up to 35 m,
made of fixed panels installed at floor
level (system of prefabricated partitions
made of aluminium profiles with infill of
insulated glazing units and sandwich
panels)
m² 865,00
7214210026800 Metal structure installer man-
hours
905,222
9310060019920 Worker servicing ST man-
hours
49,737
203011295101
System of prefabricated partitions made of
aluminium profiles with infill of insulated glazing
units and sandwich panels
m² 865,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 3 460,00
2416566101572 Polyurethane foam kg 138,40
2430226101600 Silicone sealant kg 48,44
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 346,00
4011106202741 Electrical energy kw 519,00
2952160007200 Lifting equipment for finishing works machine-
hours
19,895
22 CK22B
Aluminium profile glazed partitions in
constructions with heights up to 35 m,
made of fixed panels installed at floor
level (System of prefabricated partitions
made of aluminium profiles with infill of
insulated glazing units and sandwich
Стр. 5–7
ructions with heights up to 35 m,
made of fixed panels installed at floor
level (System of prefabricated partitions
made of aluminium profiles with infill of
insulated glazing units and sandwich
panels, fire resistance rating EI45, and
m² 865,00
1 2 3 4 5
doors EI30)
7214210026800 Metal structure installer man-
hours
905,222
9310060019920 Worker servicing ST man-
hours
49,737
2030112951012
System of prefabricated partitions made of
aluminium profiles with infill of insulated glazing
units and sandwich panels, fire resistance rating
EI45, and doors EI30
m² 865,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 3 460,00
2416566101572 Polyurethane foam kg 138,40
2430226101600 Silicone sealant kg 48,44
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 346,00
4011106202741 Electrical energy kw 519,00
2952160007200 Lifting equipment for finishing works machine-
hours
19,895
23 CD73A
Walls made of lightweight panels from
profiled sheet metal with thermal
insulation, “Sandwich” type, mounted on
metal or reinforced concrete purlins at
heights under 12 m: arranged in front of
the purlins. Note: * the brand and type of
panel sealing shall be determined in
accordance with the project
documentation. (Sandwich panel EI 90
K0)
Small materials (silicone, self-tapping screws,
spacer dowels) = 1,030
m² 61,00
7214240021810 Construction locksmith (metal fitter) man-
hours
87,688
9310060019922 Service worker man-
hours
8,418
2811236304903
1
Sandwich panels *EI 90 K0 m² 64,087
2523156720005 Finishing profile kg 201,056
2874115836895 Screws dimensions in mm 6.3/5.5 × 180 pieces 188,49
2874115836896 Sealing washer with EPDM rubber gasket pieces 188,49
2416566101572 Polyurethane foam kg 10,995
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
7,015
Total Walls
3. Enclosing structures of stairwells
24 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (BB-1,
11450*3000)
m² 34,35
7214210026800 Metal structure installer man- 27,652
1 2 3 4 5
hours
9310060019920 Worker servicing ST man-
hours
1,975
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 36,068
2681126001472
1
Oil for metal accessories kg 0,344
2430226102111 ROMALCHIT putty kg 4,122
2416566101572 Polyurethane foam kg 12,022
2410520006700 Truck crane machine-
hours
0,198
25 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (BB-2,
10300*3000)
m² 30,90
7214210026800 Metal structure installer man-
hours
24,874
9310060019920 Worker servicing ST man-
hours
1,777
2523146720200 Prefabricated shopfront glazing units made of
alum
Стр. 7–8
00)
m² 30,90
7214210026800 Metal structure installer man-
hours
24,874
9310060019920 Worker servicing ST man-
hours
1,777
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 32,445
2681126001472
1
Oil for metal accessories kg 0,309
2430226102111 ROMALCHIT putty kg 3,708
2416566101572 Polyurethane foam kg 10,815
2410520006700 Truck crane machine-
hours
0,178
Total Enclosing
structures of stairwells
4. Roof
26 CE06A
Roof coverings made of profiled sheet
metal protected against corrosion,
corrugated or ribbed, mounted on metal
purlins, executed on surfaces larger than
40 m² with profiled sheets fixed with
special clamps and mechanical screws at
the upper flange, including execution of
valleys, flashings, connections to
chimneys, etc. / profiled sheet Rannila
RAN 70
Small materials (material for bonding sheet metal)
= 1,050
m² 1 070,60
7213050013100 Tinsmith man-
hours
1 354,309
9310060019920 Worker servicing ST man-
hours
123,119
2710403642000
2
Galvanized corrugated or ribbed sheet / profiled
sheet Rannila RAN 70
m² 1 292,749
2710403643220 Flat galvanized sheet 0.75 mm kg 674,478
1 2 3 4 5
2874125886734 POP (blind) rivets pieces 5 620,65
2874115837746 Mechanical screws pieces 5 620,65
2710703434927 Flat steel 30 × 6 mm kg 365,342
2430226103064 Profiled mastic cord kg 112,413
2952160007200 Lifting equipment for finishing works machine-
hours
27,086
27 CE17A
Additional polymer layer type Ondutiss
mounted under the roofing layer of tiles,
corrugated or embossed sheets /
Membrane Tehnonicol Parobarrier C
Small materials = 1,030
m² 1 070,60
7134030012200 Waterproofing installer man-
hours
246,238
9310060019920 Worker servicing ST man-
hours
61,559
2682132600465 Additional polymer foil m² 1 268,126
2875276312000
1
Studs (pins) pieces 13 232,616
2952160007200 Lifting equipment for finishing works machine-
hours
12,312
28 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for
general insulation, supported with
galvanized soft steel wire / mineral wool
Tehnoruf H35 thickness 100 mm (105–
135 kg/m³)
m² 1 070,60
7134050013240 Thermal insulator man-
hours
652,531
2682162611371
100
Mineral wool boards Tehnoruf H35 thickness 100
mm (105–135 kg/m³)
m² 1 092,012
2734113805786 Galvanized soft steel wire d = 1 mm kg 240,885
29 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for
general insulation, supported with
galvanized soft steel wire / Mineral wool
Tehnoruf B60 thickness 50 mm (165–195
kg/m³)
m² 1 070,60
7134050013240 Thermal insulator man-
hours
652,531
2682162611371
50
Mineral wool boards Tehnoruf B60 thickness 50
mm (105-135 kg/m³)
m² 1 092,012
2734113805786 Galvanized soft steel wire d = 1 mm kg 240,885
30 CE13A2
Roof coverings with modified bituminous
membranes torch-applied i
Стр. 8–9
oruf B60 thickness 50
mm (105-135 kg/m³)
m² 1 092,012
2734113805786 Galvanized soft steel wire d = 1 mm kg 240,885
30 CE13A2
Roof coverings with modified bituminous
membranes torch-applied in a two-layer
system, on horizontal surfaces mounted
on a continuous substrate (I layer –
Tehnoelast FIX, II layer – Tehnoelast
EKP)
Small materials = 1,050
m² 1 070,60
7134030012200 Waterproofing installer man- 554,035
1 2 3 4 5
hours
9310060019920 Worker servicing ST man-
hours
283,174
2682132600470
13
Bituminous membrane Tehnoelast FIX m² 1 292,749
2682132600470
12
Bituminous membrane Tehnoelast EKP m² 1 292,749
2320216201058 Butane gas (cylinders) kg 674,478
2921140007681 Flame burner machine-
hours
246,238
2952160007200 Lifting equipment for finishing works machine-
hours
73,871
Total Roof
5. Doors
31 CK21A
Doors made of aluminium profiles,
including the fittings and accessories
necessary for doors installed in masonry
of any type, in constructions with height
up to 35 m inclusive, single-leaf, with
frame area up to 7 m² inclusive (U1,2
blind interior doors, 900 × 2100 mm)
m² 5,67
7214210026800 Metal structure installer man-
hours
5,542
9310060019920 Worker servicing ST man-
hours
0,652
2812106306050
1
Aluminium profile doors (blind) m² 5,67
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 22,68
2416566101572 Polyurethane foam kg 2,835
2430226101600 Silicone sealant kg 0,992
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 3,402
4011106202741 Electrical energy kw 5,67
2952160007200 Lifting equipment for finishing works machine-
hours
0,13
32 CK56A
Blind interior fire-resistant door EI 45
(U3/1, 3/2, 900 × 2100 mm)
Small materials (rags, grease) = 1,003
m² 3,78
9310060019930 Worker man-
hours
19,127
2030112931103
1
Blind interior fire-resistant door EI 30 m² 3,791
2811236309291 Anchorage details supplied separately kg 1,137
2873155900311 Electrodes E-42A, diameter 4 mm kg 0,19
2462106110356 Rubber-based adhesive No. 88-H kg 0,045
2416202602671 Mineral wool boards with increased rigidity based
on synthetic mortar M-200
m³ 0,027
2112227324784 Fire-retardant material with thermo-expanding
properties
kg 2,078
2112227324785 Cold smoke rubber gasket, weight 0.25 kg per 1
m
kg 2,597
2430116104162 Fire-protective enamel kg 0,417
2416586105304 Fire-protective primer kg 0,227
2112227324786 Cutting discs pieces 0,265
Стр. 9–11
5 Cold smoke rubber gasket, weight 0.25 kg per 1 m kg 2,597 2430116104162 Fire-protective enamel kg 0,417 2416586105304 Fire-protective primer kg 0,227 2112227324786 Cutting discs pieces 0,265 1 2 3 4 5 2112227324787 Decorative plastic plugs pieces 9,099 2940520007688 Grinding machine machine- hours 0,956 2940520007610 Electric hammer drill machine- hours 0,652 2952270007609 Electric drilling machine machine- hours 2,869 2940600002994 Welding machine machine- hours 0,261 2922140006702 Window crane machine- hours 0,043 33 CK21A Doors made of aluminium profiles, including the fittings and accessories necessary for doors installed in masonry of any type, in constructions with height up to 35 m inclusive, single-leaf, with frame area up to 7 m² inclusive (U 3/2, 4/1 blind exterior doors, 900 × 2100 mm) m² 6,51 7214210026800 Metal structure installer man- hours 6,364 9310060019920 Worker servicing ST man- hours 0,749 2812106306050 1 Aluminium profile doors (blind) m² 6,51 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 26,04 2416566101572 Polyurethane foam kg 3,255 2430226101600 Silicone sealant kg 1,139 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 3,906 4011106202741 Electrical energy kw 6,51 2952160007200 Lifting equipment for finishing works machine- hours 0,15 34 CK21D Doors made of aluminium profiles, including the fittings and accessories necessary for doors installed in masonry of any type, in constructions with height up to 35 m inclusive, double-leaf, with frame area up to 7 m² inclusive (U9–10 blind interior doors, 1000 × 2100 mm) m² 8,40 7214210026800 Metal structure installer man- hours 9,177 9310060019920 Worker servicing ST man- hours 1,063 2812106306050 1 Aluminium profile doors (blind) m² 8,40 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 33,60 2416566101572 Polyurethane foam kg 4,62 2430226101600 Silicone sealant kg 1,621 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 5,04 4011106202741 Electrical energy kw 8,40 2952160007200 Lifting equipment for finishing works machine- hours 0,193 35 CK21D Doors made of aluminium profiles, including the fittings and accessories m² 18,48 1 2 3 4 5 necessary for doors installed in masonry of any type, in constructions with height up to 35 m inclusive, double-leaf, with frame area up to 7 m² inclusive (U11–12 blind interior doors, 800 × 2100 mm) 7214210026800 Metal structure installer man- hours 20,189 9310060019920 Worker servicing ST man- hours 2,338 2812106306050 1 Aluminium profile doors (blind) m² 18,48 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 73,92 2416566101572 Polyurethane foam kg 10,164 2430226101600 Silicone sealant kg 3,567 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 11,088 4011106202741 Electrical energy kw 18,48 2952160007200 Lifting equipment for finishing works machine- hours 0,425 36 CK56
Стр. 11–12
kg 3,567 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 11,088 4011106202741 Electrical energy kw 18,48 2952160007200 Lifting equipment for finishing works machine- hours 0,425 36 CK56A blind interior fire-resistant door EIs 60 (U6/1, 6/2, 1300 × 2100 mm) Small materials (rags, grease) = 1,003 m² 8,19 9310060019930 Worker man- hours 41,441 2030112931106 0 Blind interior fire-resistant door EIs 60 m² 8,215 2811236309291 Anchorage details supplied separately kg 2,464 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,411 2462106110356 Rubber-based adhesive No. 88-H kg 0,099 2416202602671 Mineral wool boards with increased rigidity based on synthetic mortar M-200 m³ 0,058 2112227324784 Fire-retardant material with thermo-expanding properties kg 4,502 2112227324785 Cold smoke rubber gasket, weight 0.25 kg per 1 m kg 5,627 2430116104162 Fire-protective enamel kg 0,904 2416586105304 Fire-protective primer kg 0,493 2112227324786 Cutting discs pieces 0,575 2112227324787 Decorative plastic plugs pieces 19,715 2940520007688 Grinding machine machine- hours 2,072 2940520007610 Electric hammer drill machine- hours 1,413 2952270007609 Electric drilling machine machine- hours 6,216 2940600002994 Welding machine machine- hours 0,565 2922140006702 Window crane machine- hours 0,094 37 CK56A Blind interior fire-resistant door EIs 60 (U7, 1450 × 2100 mm) Small materials (rags, grease) = 1,003 m² 12,18 9310060019930 Worker man- hours 61,631 2030112931106 Blind interior fire-resistant door EIs 60 m² 12,217 1 2 3 4 5 0 2811236309291 Anchorage details supplied separately kg 3,665 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,611 2462106110356 Rubber-based adhesive No. 88-H kg 0,147 2416202602671 Mineral wool boards with increased rigidity based on synthetic mortar M-200 m³ 0,086 2112227324784 Fire-retardant material with thermo-expanding properties kg 6,695 2112227324785 Cold smoke rubber gasket, weight 0.25 kg per 1 m kg 8,368 2430116104162 Fire-protective enamel kg 1,344 2416586105304 Fire-protective primer kg 0,733 2112227324786 Cutting discs pieces 0,855 2112227324787 Decorative plastic plugs pieces 29,32 2940520007688 Grinding machine machine- hours 3,082 2940520007610 Electric hammer drill machine- hours 2,101 2952270007609 Electric drilling machine machine- hours 9,245 2940600002994 Welding machine machine- hours 0,84 2922140006702 Window crane machine- hours 0,14 38 CK56A Blind interior fire-resistant door EIs 60 (U8, 1000 × 2100 mm) Small materials (rags, grease) = 1,003 m² 2,10 9310060019930 Worker man- hours 10,626 2030112931106 0 Blind interior fire-resistant door EIs 60 m² 2,106 2811236309291 Anchorage details supplied separately kg 0,632 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,105 2462106110356 Rubber-based adhesive No. 88-H kg 0,025 2416202602671 Mineral wool boards with increased rigidity
Стр. 12–13
upplied separately kg 0,632 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,105 2462106110356 Rubber-based adhesive No. 88-H kg 0,025 2416202602671 Mineral wool boards with increased rigidity based on synthetic mortar M-200 m³ 0,015 2112227324784 Fire-retardant material with thermo-expanding properties kg 1,154 2112227324785 Cold smoke rubber gasket, weight 0.25 kg per 1 m kg 1,443 2430116104162 Fire-protective enamel kg 0,232 2416586105304 Fire-protective primer kg 0,126 2112227324786 Cutting discs pieces 0,147 2112227324787 Decorative plastic plugs pieces 5,055 2940520007688 Grinding machine machine- hours 0,531 2940520007610 Electric hammer drill machine- hours 0,362 2952270007609 Electric drilling machine machine- hours 1,594 2940600002994 Welding machine machine- hours 0,145 2922140006702 Window crane machine- hours 0,024 39 CK19A Aluminium windows with one or more sashes in constructions with heights up to 35 m inclusive, with frame area up to m² 15,75 1 2 3 4 5 3.00 m² inclusive (O-1, 900 × 2500 (h) mm) 7214210026800 Metal structure installer man- hours 18,112 9310060019920 Worker servicing ST man- hours 1,811 2030112938100 Aluminium windows m² 15,75 2416566101572 Polyurethane foam kg 11,104 2430226101600 Silicone sealant kg 3,89 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 94,50 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 9,45 4011106202741 Electrical energy kw 15,75 2952160007200 Lifting equipment for finishing works machine- hours 0,362 40 CK19A Aluminium windows with one or more sashes in constructions with heights up to 35 m inclusive, with frame area up to 3.00 m² inclusive (Ф-1, 900 × 700 (h) mm) m² 1,26 7214210026800 Metal structure installer man- hours 1,449 9310060019920 Worker servicing ST man- hours 0,145 2030112938100 Aluminium windows m² 1,26 2416566101572 Polyurethane foam kg 0,888 2430226101600 Silicone sealant kg 0,311 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 7,56 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 0,756 4011106202741 Electrical energy kw 1,26 2952160007200 Lifting equipment for finishing works machine- hours 0,029 41 CK19A Aluminium windows with one or more sashes in constructions with heights up to 35 m inclusive, with frame area up to 3.00 m² inclusive (Ф-2, 1300 × 700 (h) mm) m² 0,91 7214210026800 Metal structure installer man- hours 1,046 9310060019920 Worker servicing ST man- hours 0,105 2030112938100 Aluminium windows m² 0,91 2416566101572 Polyurethane foam kg 0,642 2430226101600 Silicone sealant kg 0,225 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 5,46 2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 0,546 4011106202741 Electrical energy kw 0,91 2952160007200 Lifting equipment for finishing works machine- hours 0,021 42 CK19A Aluminium windows with one or more sashes in constructions with hei
Стр. 13–15
4011106202741 Electrical energy kw 0,91
2952160007200 Lifting equipment for finishing works machine-
hours
0,021
42 CK19A
Aluminium windows with one or more
sashes in constructions with heights up to
35 m inclusive, with frame area up to
m² 4,06
1 2 3 4 5
3.00 m² inclusive (Ф-3, 1450 × 700 (h)
mm)
7214210026800 Metal structure installer man-
hours
4,669
9310060019920 Worker servicing ST man-
hours
0,467
2030112938100 Aluminium windows m² 4,06
2416566101572 Polyurethane foam kg 2,862
2430226101600 Silicone sealant kg 1,003
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 24,36
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 2,436
4011106202741 Electrical energy kw 4,06
2952160007200 Lifting equipment for finishing works machine-
hours
0,093
43 CK26B
External aluminium window sills
installed at windows
m 16,00
7422010060100 Carpenter (joiner) man-
hours
5,888
9310060019920 Worker servicing ST man-
hours
1,472
2743123549026
5230
External aluminium window sills m 16,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 64,00
2952160007200 Lifting equipment for finishing works machine-
hours
0,184
44 CK26A
Internal PVC window sills installed at
windows (250 mm)
Small materials (plugs) = 1,020
m 16,00
7422010060100 Carpenter (joiner) man-
hours
5,152
9310060019920 Worker servicing ST man-
hours
1,472
2521106718392
250
Internal PVC window sills (b = 250 mm) m 16,32
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 65,28
2952160007200 Lifting equipment for finishing works machine-
hours
0,184
45 CK13A1
Sliding or folding double-leaf metal gates
installed in masonry of any type,
including the necessary accessories, with
area up to 7 m² inclusive (P1, 4000 ×
2850 (h) mm)
m² 57,00
7212030022700 Welder man-
hours
12,454
7214210026800 Metal structure installer man-
hours
226,148
9310060019920 Worker servicing ST man-
hours
78,66
7141020013300 Painter (plasterer-painter) man-
hours
9,832
2812106306000
1
Prefabricated metal doors made of steel profiles m² 57,00
1 2 3 4 5
1421102200496 Sorted unwashed river and lake sand 0.0–1.0 mm m³ 0,285
2651122100402 Metallurgical cement with additives M 30, bags
S1500
kg 76,95
4011106202741 Electrical energy kw 15,39
2873155900800 Welding electrodes kg 7,695
2430226100034 Anticorrosive red lead primer G.351-4 S 3097-80 kg 37,05
4100116202818 Water for mortars and concrete m³ 0,057
2410520006700 Truck crane machine-
hours
3,277
Total Doors
6. Glazing
6.1. Exterior glazing (Aluminium glazing
units with sound-insulating mirror glass
“Planibel Dark Blue”, inner glass
“Triplex”)
46 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (ВН-19,
106700 × 2550 mm, + automatic sli
Стр. 15–16
lazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (ВН-19,
106700 × 2550 mm, + automatic sliding
doors)
m² 272,085
7214210026800 Metal structure installer man-
hours
219,028
9310060019920 Worker servicing ST man-
hours
15,645
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 285,689
2681126001472
1
Oil for metal accessories kg 2,721
2430226102111 ROMALCHIT putty kg 32,65
2416566101572 Polyurethane foam kg 95,23
2410520006700 Truck crane machine-
hours
1,564
47 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (ВН-20,
8250 × 2550 mm, + automatic sliding
doors of the “break-out” type, +
automatic opening transoms in case of
fire)
m² 21,04
7214210026800 Metal structure installer man-
hours
16,937
9310060019920 Worker servicing ST man-
hours
1,21
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 22,092
1 2 3 4 5
2681126001472
1
Oil for metal accessories kg 0,21
2430226102111 ROMALCHIT putty kg 2,525
2416566101572 Polyurethane foam kg 7,364
2410520006700 Truck crane machine-
hours
0,121
48 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (ВН-21,
70150 × 2550 mm, + automatic sliding
doors of the “break-out” type, +
automatic opening transoms in case of
fire)
m² 178,88
7214210026800 Metal structure installer man-
hours
143,998
9310060019920 Worker servicing ST man-
hours
10,286
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 187,824
2681126001472
1
Oil for metal accessories kg 1,789
2430226102111 ROMALCHIT putty kg 21,466
2416566101572 Polyurethane foam kg 62,608
2410520006700 Truck crane machine-
hours
1,029
49 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (ВН-22,
6100 × 8100 mm, + automatic sliding
doors of the “break-out” type, +
automatic opening transoms in case of
fire)
m² 49,41
7214210026800 Metal structure installer man-
hours
39,775
9310060019920 Worker servicing ST man-
hours
2,841
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 51,88
2681126001472
1
Oil for metal accessories kg 0,494
2430226102111 ROMALCHIT putty kg 5,929
2416566101572 Polyurethane foam kg 17,293
2410520006700 Truck crane machine-
hours
0,284
Total Exterior glazing
(Aluminium glazing units
with sound-insulating
mirror glass “Planibel
Стр. 16–18
66101572 Polyurethane foam kg 17,293
2410520006700 Truck crane machine-
hours
0,284
Total Exterior glazing
(Aluminium glazing units
with sound-insulating
mirror glass “Planibel
1 2 3 4 5
Dark Blue”, inner glass
“Triplex”)
6.2. Skylight
50 CK10A
Simple metal skylights, fixed or with
movable sashes, installed in constructions
of any type, including the necessary
accessories such as: gutters for collecting
water resulting from condensation,
protective devices against water
penetration from precipitation at changes
of slopes and at glazing edges, etc.
(Installation of skylights, dimensions
1250 × 1250 mm, 6 pieces)
m² 9,38
7214210026800 Metal structure installer man-
hours
17,799
7141020013300 Painter (plasterer-painter) man-
hours
4,315
9310060019920 Worker servicing ST man-
hours
1,618
2523146720400 Metal skylight, including accessories m² 9,38
2873155900800 Welding electrodes kg 0,188
4011106202741 Electrical energy kw 0,469
2430226100034 Anticorrosive red lead primer G.351-4 S 3097-80 kg 0,75
2651122100402 Metallurgical cement with additives M 30, bags
S1500
kg 11,256
1421102200496 Sorted unwashed river and lake sand 0.0–1.0 mm m³ 0,038
4100116202818 Water for mortars and concrete m³ 0,009
2410520006700 Truck crane machine-
hours
0,216
Total Skylight
Total Glazing
7. Floor finishes
7.1. Level 1
7.1.1. Type Б-1
51 CG54A
Cast epoxy floor finishes. “FUXRAD”
system “FX 47”, antistatic coating in 4
layers, layer thickness 2.5–3.0 mm on
existing substrate
Small materials (rags, levelling screeds, tool
cleaner) = 1,009
m² 946,67
7129200011200 Finisher MP man-
hours
2 863,203
9310060019922 Service worker man-
hours
1 219,311
2653102100845 Primer Fuxit-3000* kg 262,677
1421102200803 Quartz sand “Fuxit-9420”* kg 1 910,38
1 2 3 4 5
2653102100846 Levelling layer “Fuxit-3300”* kg 1 146,228
2653102100848 Conductive layer “Fuxit-3310”* kg 76,415
2653102100847 Top coat, two-component “Fuxit-3110” – current
collector*
kg 1 910,38
2653102100849 Copper tape* m 668,633
2653102100850 Silicon carbide “Fuxit-9471” kg 286,557
2881116002700 Abrasive disc pieces 19,104
2940520007688 Grinding machine machine-
hours
217,734
2952240005106 Industrial vacuum cleaner machine-
hours
72,941
2952270007607 Electric drilling machine with auger attachment machine-
hours
217,734
2952160007200 Lifting equipment for finishing works machine-
hours
21,773
2922140006702 Window crane machine-
hours
10,887
Total Type Б-1
7.1.2. Type П-1
52 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (160 -180 mm)
m² 174,79
7132030012600 Mosaic worker man-
hours
120,605
9310060019920 Worker servicing ST man-
hours
20,101
2664102102010
150
Cement mortar M150 m
Стр. 18–19
finely trowelled surface (160 -180 mm)
m² 174,79
7132030012600 Mosaic worker man-
hours
120,605
9310060019920 Worker servicing ST man-
hours
20,101
2664102102010
150
Cement mortar M150 m³ 5,768
4100116202818 Water for mortars and concrete m³ 1,748
2952160007200 Lifting equipment for finishing works machine-
hours
6,03
2952270003817 Electric mortar mixer, 200 L machine-
hours
2,412
53 CG01A1
k=28
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 28,000
Coefficient for materials = 28,000
Coefficient for machines = 28,000
m² 174,79
7132030012600 Mosaic worker man-
hours
562,824
9310060019920 Worker servicing ST man-
hours
112,565
2664102102010
150
Cement mortar M150 m³ 26,918
4100116202818 Water for mortars and concrete m³ 9,788
2952160007200 Lifting equipment for finishing works machine-
hours
16,885
2952270003817 Electric mortar mixer, 200 L machine- 8,442
1 2 3 4 5
hours
54 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 174,79
9310060019930 Worker man-
hours
481,214
2670112202052 Ceramic granite tiles m² 177,412
2462106110554 Adhesive based on acrylic resins or latex kg 751,597
2430226100000
1
Grout kg 34,958
2881116002700 Abrasive disc pieces 3,496
4100126202818 Water m³ 0,699
2952270003205 Universal stone cutting machine machine-
hours
14,674
2922140006702 Window crane machine-
hours
2,332
2952270007607 Electric drilling machine with auger attachment machine-
hours
1,065
Total Type П-1
7.1.3. Type П-2
55 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (50 mm)
m² 62,69
7132030012600 Mosaic worker man-
hours
43,256
9310060019920 Worker servicing ST man-
hours
7,209
2664102102010
150
Cement mortar M150 m³ 2,069
4100116202818 Water for mortars and concrete m³ 0,627
2952160007200 Lifting equipment for finishing works machine-
hours
2,163
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,865
56 CG01A1
k=4
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 4,000
Coefficient for materials = 4,000
Coefficient for machines = 4,000
m² 62,69
7132030012600 Mosaic worker man-
hours
28,837
9310060019920 Worker servicing ST man-
hours
5,767
2664102102010
150
Cement mortar M150 m³ 1,379
4100116202818 Water for mortars and concrete m³ 0,502
2952160007200 Lifting equipment for finishing works machine- 0,865
Стр. 19–21
cing ST man-
hours
5,767
2664102102010
150
Cement mortar M150 m³ 1,379
4100116202818 Water for mortars and concrete m³ 0,502
2952160007200 Lifting equipment for finishing works machine- 0,865
1 2 3 4 5
hours
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,433
57 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 62,69
9310060019930 Worker man-
hours
172,592
2670112202052 Ceramic granite tiles m² 63,63
2462106110554 Adhesive based on acrylic resins or latex kg 269,567
2430226100000
1
Grout kg 12,538
2881116002700 Abrasive disc pieces 1,254
4100126202818 Water m³ 0,251
2952270003205 Universal stone cutting machine machine-
hours
5,263
2922140006702 Window crane machine-
hours
0,836
2952270007607 Electric drilling machine with auger attachment machine-
hours
0,382
Total Type П-2
7.1.4. Type П-3
58 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (20-40 mm)
m² 37,67
7132030012600 Mosaic worker man-
hours
25,992
9310060019920 Worker servicing ST man-
hours
4,332
2664102102010
150
Cement mortar M150 m³ 1,243
4100116202818 Water for mortars and concrete m³ 0,377
2952160007200 Lifting equipment for finishing works machine-
hours
1,30
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,52
59 IzF01D2
k=2
Priming of surfaces for application of the
diffusion layer, vapour barrier, thermal
insulation or waterproofing on pitched
roofs, horizontal or vertical roofs, or on
floors of wet rooms, tanks or cold rooms,
with anionic bituminous emulsion, in one
layer
Coefficient for labour input = 2,000
Coefficient for materials = 2,000
Coefficient for machines = 2,000
m² 37,67
7134030012200 Waterproofing installer man-
hours
4,332
2413317001000 Anionic bitumen emulsion for waterproofing kg 22,602
2922140006703 Window crane, capacity 0.0015 meganewtons machine- 0,026
1 2 3 4 5
(MN) (0.15 ton-force (tf)) hours
60 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (35 mm)
m² 37,67
7132030012600 Mosaic worker man-
hours
25,992
9310060019920 Worker servicing ST man-
hours
4,332
2664102102010
150
Cement mortar M150 m³ 1,243
4100116202818 Water for mortars and concrete m³ 0,377
2952160007200 Lifting equipment for finishing works machine-
hours
1,30
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,52
61 CG01A1
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
m² 37,67
7132030012600 Mosaic worker man-
hours
4,332
9310060019920 Worker servicing ST man-
hours
0,866
2664102102010
150
Cement mortar M150 m³ 0,207
4100116202818 Wat
Стр. 21–22
shall
be added
m² 37,67
7132030012600 Mosaic worker man-
hours
4,332
9310060019920 Worker servicing ST man-
hours
0,866
2664102102010
150
Cement mortar M150 m³ 0,207
4100116202818 Water for mortars and concrete m³ 0,075
2952160007200 Lifting equipment for finishing works machine-
hours
0,13
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,065
62 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 37,67
9310060019930 Worker man-
hours
103,709
2670112202052 Ceramic granite tiles m² 38,235
2462106110554 Adhesive based on acrylic resins or latex kg 161,981
2430226100000
1
Grout kg 7,534
2881116002700 Abrasive disc pieces 0,753
4100126202818 Water m³ 0,151
2952270003205 Universal stone cutting machine machine-
hours
3,162
2922140006702 Window crane machine-
hours
0,503
2952270007607 Electric drilling machine with auger attachment machine-
hours
0,23
Total Type П-3
7.1.5. Type K-1
1 2 3 4 5
63 CI24A
Cladding of steps with bonded ceramic
granite tiles, thickness under 30 mm
m² 34,30
9310060019930 Worker man-
hours
152,06
2670112202052 Ceramic granite tiles m² 34,986
2462106110554 Adhesive based on acrylic resins or latex kg 198,94
2653102100853 Primer (undercoat) kg 5,145
2430226100000
1
Grout kg 6,86
2881116002700 Abrasive disc pieces 0,686
4100126202818 Water m³ 0,171
2952270003205 Universal stone cutting machine machine-
hours
13,53
2922140006702 Window crane machine-
hours
1,42
2952270007607 Electric drilling machine with auger attachment machine-
hours
0,284
Total Type K-1
Total Level 1
7.2. Level 2
7.2.1. Type П-4
64 IzF53A
Manual execution of floor substrate with
thermal insulation layer made of extruded
polystyrene boards XPS – 20 mm (ρ = 35
kg/m³, λ = 0.032 W/mK)
Small materials (metal bars D = 6–8 mm, length
400 mm) = 1,015
m² 650,56
7134050013250 Insulator man-
hours
52,37
9310060019922 Service worker man-
hours
37,407
2670112204002
20
Extruded polystyrene boards XPS – 20 mm (ρ =
35 kg/m³, λ = 0.032 W/mK)
m² 673,525
2922140006702 Window crane machine-
hours
2,993
65 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (60 mm)
m² 650,56
7132030012600 Mosaic worker man-
hours
448,886
9310060019920 Worker servicing ST man-
hours
74,814
2664102102010
150
Cement mortar M150 m³ 21,468
4100116202818 Water for mortars and concrete m³ 6,506
2952160007200 Lifting equipment for finishing works machine-
hours
22,444
2952270003817 Electric mortar mixer, 200 L machine-
hours
8,978
Стр. 22–24
4100116202818 Water for mortars and concrete m³ 6,506
2952160007200 Lifting equipment for finishing works machine-
hours
22,444
2952270003817 Electric mortar mixer, 200 L machine-
hours
8,978
1 2 3 4 5
66 CG01A1
k=6
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 6,000
Coefficient for materials = 6,000
Coefficient for machines = 6,000
m² 650,56
7132030012600 Mosaic worker man-
hours
448,886
9310060019920 Worker servicing ST man-
hours
89,777
2664102102010
150
Cement mortar M150 m³ 21,468
4100116202818 Water for mortars and concrete m³ 7,807
2952160007200 Lifting equipment for finishing works machine-
hours
13,467
2952270003817 Electric mortar mixer, 200 L machine-
hours
6,733
67 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 650,56
9310060019930 Worker man-
hours
1 791,057
2670112202052 Ceramic granite tiles m² 660,318
2462106110554 Adhesive based on acrylic resins or latex kg 2 797,408
2430226100000
1
Grout kg 130,112
2881116002700 Abrasive disc pieces 13,011
4100126202818 Water m³ 2,602
2952270003205 Universal stone cutting machine machine-
hours
54,615
2922140006702 Window crane machine-
hours
8,678
2952270007607 Electric drilling machine with auger attachment machine-
hours
3,965
Total Type П-4
7.2.2. Type П-5
68 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (20...70 mm)
m² 194,80
7132030012600 Mosaic worker man-
hours
134,412
9310060019920 Worker servicing ST man-
hours
22,402
2664102102010
150
Cement mortar M150 m³ 6,428
4100116202818 Water for mortars and concrete m³ 1,948
2952160007200 Lifting equipment for finishing works machine-
hours
6,721
1 2 3 4 5
2952270003817 Electric mortar mixer, 200 L machine-
hours
2,688
69 CG01A1
k=3
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² 194,80
7132030012600 Mosaic worker man-
hours
67,206
9310060019920 Worker servicing ST man-
hours
13,441
2664102102010
150
Cement mortar M150 m³ 3,214
4100116202818 Water for mortars and concrete m³ 1,169
2952160007200 Lifting equipment for finishing works machine-
hours
2,016
2952270003817 Electric mortar mixer, 200 L machine-
hours
1,008
70 IzF04J1
applicative
Waterproofing membrane Parobarrier B
m² 194,80
7134030012200 Waterproofing installer man-
hours
4,48
2682132601626
01
membrane Parobarrie
Стр. 24–25
0 L machine-
hours
1,008
70 IzF04J1
applicative
Waterproofing membrane Parobarrier B
m² 194,80
7134030012200 Waterproofing installer man-
hours
4,48
2682132601626
01
membrane Parobarrier B m² 210,384
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
0,112
71 IzF53A
Manual execution of floor substrate with
thermal insulation layer made of extruded
polystyrene boards Tehnonicol Carbon
EPS PROF 300 – 100 mm (γ = 35 kg/m³,
λ = 0.032 W/mK)
Small materials (metal bars D = 6–8 mm, length
400 mm) = 1,015
m² 194,80
7134050013250 Insulator man-
hours
15,681
9310060019922 Service worker man-
hours
11,201
2670112204002
10
Extruded polystyrene boards XPS Carbon PROF
300 – 100 mm (ρ = 35 kg/m³, λ = 0.032 W/mK)
m² 201,676
2922140006702 Window crane machine-
hours
0,896
72 IzF04J1
applicative
Glass fiber mat TECHNONICOL 100
g/m²
m² 194,80
7134030012200 Waterproofing installer man-
hours
4,48
2682132601626
02
Glass fiber mat TECHNONICOL 100 g/m² m² 210,384
2922140006703 Window crane, capacity 0.0015 meganewtons machine- 0,112
1 2 3 4 5
(MN) (0.15 ton-force (tf)) hours
73 IzF04J1
applicative
Polymer membrane ECOPLAST V-GR
m² 194,80
7134030012200 Waterproofing installer man-
hours
4,48
2682132601626
03
Polymer membrane ECOPLAST V-GR m² 210,384
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
0,112
74 IzF04J1
applicative
Geotextile TECHNONICOL 300 g/m²
m² 194,80
7134030012200 Waterproofing installer man-
hours
4,48
2682132601626
04
Geotextile TECHNONICOL 300 g/m² m² 210,384
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
0,112
75 CG45A
Demountable raised floor finishes with
600 × 600 mm module and height 30–80
mm: with standardized construction
pedestals / ceramic granite slabs 600 ×
600 mm on supporting polymer structure
m² 194,80
9310060019930 Worker man-
hours
71,91
2661126417161
1
Ceramic granite slabs 600 × 600 × 20 mm m² 198,696
2811106302011 Metal pedestals for raised floors with connecting
elements
pieces 541,154
2430126108727 Epoxy enamel kg 38,96
2682162608364 Braided polyamide cord, diameter 2 mm kg 0,39
2466477300806 Polyurethane adhesive for floor pedestals kg 2,435
2430226100011 Putty EP-00-10 kg 33,116
2952160007200 Lifting equipment for finishing works machine-
hours
5,018
Total Type П-5
7.2.3. Type П-6
76 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (20-40 mm)
m² 23,81
7132030012600 Mosaic worker man-
hours
16,429
9310060019920 Worker servicing ST man-
hours
2,738
2664102102010
150
Cement mortar M150 m³ 0,786
4100116202818 Water for mortars and concrete m³ 0,238
2952160007200 Lifting equipment for finishing works machine-
hours
0,821
29
Стр. 25–27
hours
2,738
2664102102010
150
Cement mortar M150 m³ 0,786
4100116202818 Water for mortars and concrete m³ 0,238
2952160007200 Lifting equipment for finishing works machine-
hours
0,821
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,329
1 2 3 4 5
77 IzF01D2
k=2
Priming of surfaces for application of the
diffusion layer, vapour barrier, thermal
insulation or waterproofing on pitched
roofs, horizontal or vertical roofs, or on
floors of wet rooms, tanks or cold rooms,
with anionic bituminous emulsion, in one
layer
Coefficient for labour input = 2,000
Coefficient for materials = 2,000
Coefficient for machines = 2,000
m² 23,81
7134030012200 Waterproofing installer man-
hours
2,738
2413317001000 Anionic bitumen emulsion for waterproofing kg 14,286
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
0,016
78 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (35 mm)
m² 23,81
7132030012600 Mosaic worker man-
hours
16,429
9310060019920 Worker servicing ST man-
hours
2,738
2664102102010
150
Cement mortar M150 m³ 0,786
4100116202818 Water for mortars and concrete m³ 0,238
2952160007200 Lifting equipment for finishing works machine-
hours
0,821
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,329
79 CG01A1
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
m² 23,81
7132030012600 Mosaic worker man-
hours
2,738
9310060019920 Worker servicing ST man-
hours
0,548
2664102102010
150
Cement mortar M150 m³ 0,131
4100116202818 Water for mortars and concrete m³ 0,048
2952160007200 Lifting equipment for finishing works machine-
hours
0,082
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,041
80 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 23,81
9310060019930 Worker man-
hours
65,551
1 2 3 4 5
2670112202052 Ceramic granite tiles m² 24,167
2462106110554 Adhesive based on acrylic resins or latex kg 102,383
2430226100000
1
Grout kg 4,762
2881116002700 Abrasive disc pieces 0,476
4100126202818 Water m³ 0,095
2952270003205 Universal stone cutting machine machine-
hours
1,999
2922140006702 Window crane machine-
hours
0,318
2952270007607 Electric drilling machine with auger attachment machine-
hours
0,145
Total Type П-6
Total Level 2
Total Floor finishes
8. Interior finishing (Ceiling)
8.1. Type 1
81 CN53A
Priming of interior ceiling surfaces
m² 946,50
7141020013300 Painter (plasterer-painter) man-
hours
32,654
2416586105303
2
Primer kg 141,975
810741 Dry sanding
Стр. 27–28
. Type 1
81 CN53A
Priming of interior ceiling surfaces
m² 946,50
7141020013300 Painter (plasterer-painter) man-
hours
32,654
2416586105303
2
Primer kg 141,975
810741 Dry sanding paper pieces 47,325
82 CF52B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar
m² 946,50
7122050013442 Plasterer man-
hours
1 665,367
2653102100831 Dry mix kg 6 758,01
4100116202818 Water for mortars and concrete m³ 3,786
2952160007200 Lifting equipment for finishing works machine-
hours
85,99
2952240004021 Electric mixer machine-
hours
21,225
83 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 946,50
7122050013401 Mason, grade 4 man-
hours
489,814
9310060019920 Worker servicing ST man-
hours
108,847
2653102100833 Gypsum-based putty “Eurofin” kg 998,463
4100126202818 Water m³ 0,947
2952160007200 Lifting equipment for finishing works machine-
hours
1,088
84 CN53A
Priming of interior wall surfaces
m² 946,50
1 2 3 4 5
7141020013300 Painter (plasterer-painter) man-
hours
32,654
2416586105303
2
Primer kg 141,975
810741 Dry sanding paper pieces 47,325
85 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 946,50
7141020013300 Painter (plasterer-painter) man-
hours
598,661
2430116103800 Vinyl copolymer-based paint kg 378,60
2653102100830 Construction gypsum type A kg 56,79
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 473,25
1711317306661 Cleaning cotton kg 47,325
4100116202818 Water for mortars and concrete m³ 1,893
Total Type 1
8.2. Type 2
86 CN53A
Priming of interior ceiling surfaces
m² 105,40
7141020013300 Painter (plasterer-painter) man-
hours
3,636
2416586105303
2
Primer kg 15,81
810741 Dry sanding paper pieces 5,27
87 CF52B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar (2
mm)
m² 105,40
7122050013442 Plasterer man-
hours
185,451
2653102100831 Dry mix kg 752,556
4100116202818 Water for mortars and concrete m³ 0,422
2952160007200 Lifting equipment for finishing works machine-
hours
9,576
2952240004021 Electric mixer machine-
hours
2,364
88 CF53B
k=3
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar.
Difference in addition or deduction for
each 1.0 mm (to be added to or deducted
from item CF52)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² -105,40
7122050013442 Plasterer man-
hours
-112,725
2653102100831 Dry mix kg -452,166
4100116202818 Water for mortars and concrete m³ -0,316
Стр. 28–30
als = 3,000
Coefficient for machines = 3,000
m² -105,40
7122050013442 Plasterer man-
hours
-112,725
2653102100831 Dry mix kg -452,166
4100116202818 Water for mortars and concrete m³ -0,316
1 2 3 4 5
2952160007200 Lifting equipment for finishing works machine-
hours
-1,455
2952240004021 Electric mixer machine-
hours
-5,818
89 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 105,40
7122050013401 Mason, grade 4 man-
hours
54,544
9310060019920 Worker servicing ST man-
hours
12,121
2653102100833 Gypsum-based putty “Eurofin” kg 111,186
4100126202818 Water m³ 0,105
2952160007200 Lifting equipment for finishing works machine-
hours
0,121
90 CN53A
Priming of interior wall surfaces
m² 105,40
7141020013300 Painter (plasterer-painter) man-
hours
3,636
2416586105303
2
Primer kg 15,81
810741 Dry sanding paper pieces 5,27
91 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 105,40
7141020013300 Painter (plasterer-painter) man-
hours
66,666
2430116103800 Vinyl copolymer-based paint kg 42,16
2653102100830 Construction gypsum type A kg 6,324
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 52,70
1711317306661 Cleaning cotton kg 5,27
4100116202818 Water for mortars and concrete m³ 0,211
92 CK52B
Suspended ceilings from “Griliato” strip
panels on metal frame with suspension
using strap and rod, in rooms with height
up to 4 m / suspended metal cassette
ceiling Griliato
Small materials (profile selector, rags) = 1,003
m² 105,40
9310060019930 Worker man-
hours
107,877
2662102701010 “Griliato” ceiling panels m² 107,831
2812106305912 Suspension with clamp and rod pieces 84,573
2812106305914 White 24 mm corner profiles m 118,402
2812106305915 Trapezoidal lamella profiles 35/30 m 88,802
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 22,835
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pieces 85,63
2952160007200 Lifting equipment for finishing works machine-
hours
0,436
2952270007609 Electric drilling machine machine-
hours
2,933
1 2 3 4 5
Total Type 2
8.3. Type 3
93 CK52B
applicative
Suspended ceilings made of “Griliato”
slat panels on metal frame using
suspension with clamp and rod, in rooms
with height up to 4 m / suspended metal
slatted ceiling
Small materials (profile selector, rags) = 1,003
m² 493,00
9310060019930 Worker man-
hours
504,585
2662102701010
1
Suspended metal slatted ceiling m² 504,369
2812106305912 Suspension with clamp and rod pieces 395,583
2812106305914 White 24 mm corner profiles m 553,816
2812106305915 Trapezoidal lamella profiles 35/30 m 415,362
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 106,807
2051142950712 Dowels for fixing ceiling suspensions
Стр. 30–31
m 553,816
2812106305915 Trapezoidal lamella profiles 35/30 m 415,362
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 106,807
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pieces 400,528
2952160007200 Lifting equipment for finishing works machine-
hours
2,041
2952270007609 Electric drilling machine machine-
hours
13,72
Total Type 3
8.4. Type 4
94 CE44A
Roof coverings made of lightweight
profiled sheet metal panels with thermal
insulation, type “Sandwich” EI90,
mounted on metal purlins. Note: * the
brand and type of panel sealing shall be
determined in accordance with the project
documentation.
Small materials (silicone, self-tapping screws) =
1,020
m² 275,50
7214210026800 Metal structure installer man-
hours
380,19
9310060019920 Worker servicing ST man-
hours
95,047
2811236304903 “Sandwich” panels * m² 286,63
2523156720006 Finishing profile (including ridge joint) kg 725,006
2874115836897 Screws, dimensions in mm 6.3/5.5 × 235 pieces 843,03
2874115836896 Sealing washer with EPDM rubber gasket pieces 843,03
2416566101572 Polyurethane foam kg 50,863
2952160007200 Lifting equipment for finishing works machine-
hours
15,841
Total Type 4
Total Interior finishing
1 2 3 4 5
(Ceiling)
9. Interior finishing (Walls)
9.1. Type 1 (external walls)
95 CF02B
Interior plastering 2 cm thick, trowelled,
manually executed, on walls or columns,
on plane surfaces with cement-lime
mortar grade M100-T for splash coat,
base coat and finishing coat, on brick
masonry or small concrete blocks / 25
mm
m² 761,00
7122050013400 Bricklayer man-
hours
875,15
9310060019920 Worker servicing ST man-
hours
175,03
2664102103001 Cement-lime mortar m³ 15,981
4100116202818 Water for mortars and concrete m³ 4,946
2952270003817 Electric mortar mixer, 200 L machine-
hours
4,376
2952160007200 Lifting equipment for finishing works machine-
hours
1,75
96 CF17B
Various works – thickness difference, ±5
mm to base coat layer applied on walls,
executed with mortar
m² 761,00
7122050013400 Bricklayer man-
hours
87,515
9310060019920 Worker servicing ST man-
hours
26,254
2664102100000 Mortar m³ 4,566
2952160007200 Lifting equipment for finishing works machine-
hours
0,875
97 CN53A
Priming of interior wall surfaces
m² 761,00
7141020013300 Painter (plasterer-painter) man-
hours
26,254
2416586105303
2
Primer kg 114,15
810741 Dry sanding paper pieces 38,05
98 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar / 2 mm
m² 761,00
7122050013442 Plasterer man-
hours
1 067,683
2653102100831 Dry mix kg 5 433,54
4100116202818 Water for mortars and concrete m³ 3,044
2952160007200 Lifting equipment for finishing works machine-
hours
69,137
Стр. 31–33
lasterer man-
hours
1 067,683
2653102100831 Dry mix kg 5 433,54
4100116202818 Water for mortars and concrete m³ 3,044
2952160007200 Lifting equipment for finishing works machine-
hours
69,137
2952240004021 Electric mixer machine-
hours
14,002
1 2 3 4 5
99 CF51B
k=3
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar. Difference in
addition or deduction for each 1.0 mm (to
be added to or deducted from item CF50)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² -761,00
7122050013442 Plasterer man-
hours
-630,108
2653102100831 Dry mix kg -3 264,69
4100116202818 Water for mortars and concrete m³ -2,283
2952160007200 Lifting equipment for finishing works machine-
hours
-42,007
2952240004021 Electric mixer machine-
hours
-7,876
100 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 761,00
7122050013401 Mason, grade 4 man-
hours
393,817
9310060019920 Worker servicing ST man-
hours
87,515
2653102100833 Gypsum-based putty “Eurofin” kg 802,779
4100126202818 Water m³ 0,761
2952160007200 Lifting equipment for finishing works machine-
hours
0,875
101 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 761,00
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
122,521
2430226101010 Quartz primer “Gleta” kg 315,815
810741 Dry sanding paper pieces 38,05
102 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 761,00
7141020013300 Painter (plasterer-painter) man-
hours
481,332
2430116103800 Vinyl copolymer-based paint kg 304,40
2653102100830 Construction gypsum type A kg 45,66
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 380,50
1711317306661 Cleaning cotton kg 38,05
4100116202818 Water for mortars and concrete m³ 1,522
Total Type 1 (external
walls)
9.2. Type 2 (partition walls, columns)
1 2 3 4 5
103 CN53A
Priming of interior wall surfaces
m² 458,40
7141020013300 Painter (plasterer-painter) man-
hours
15,815
2416586105303
2
Primer kg 68,76
810741 Dry sanding paper pieces 22,92
104 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar
m² 458,40
7122050013442 Plasterer man-
hours
643,135
2653102100831 Dry mix kg 3 272,976
4100116202818 Water for mortars and concrete m³ 1,834
2952160007200 Lifting equipment for finishing works machine-
hours
41,646
2952240004021 Electric mixer machine-
hours
8,435
105 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m²
Стр. 33–34
rs
41,646
2952240004021 Electric mixer machine-
hours
8,435
105 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 458,40
7122050013401 Mason, grade 4 man-
hours
237,222
9310060019920 Worker servicing ST man-
hours
52,716
2653102100833 Gypsum-based putty “Eurofin” kg 483,566
4100126202818 Water m³ 0,458
2952160007200 Lifting equipment for finishing works machine-
hours
0,527
106 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 458,40
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
73,802
2430226101010 Quartz primer “Gleta” kg 190,236
810741 Dry sanding paper pieces 22,92
107 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 458,40
7141020013300 Painter (plasterer-painter) man-
hours
289,938
2430116103800 Vinyl copolymer-based paint kg 183,36
2653102100830 Construction gypsum type A kg 27,504
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 229,20
1711317306661 Cleaning cotton kg 22,92
4100116202818 Water for mortars and concrete m³ 0,917
1 2 3 4 5
Total Type 2 (partition
walls, columns)
9.3. Type 3 (window sill section)
108 CF02B
Interior plastering 2 cm thick, trowelled,
manually executed, on walls or columns,
on plane surfaces with cement-lime
mortar grade M100-T for splash coat,
base coat and finishing coat, on brick
masonry or small concrete blocks / 25
mm
m² 146,30
7122050013400 Bricklayer man-
hours
168,245
9310060019920 Worker servicing ST man-
hours
33,649
2664102103001 Cement-lime mortar m³ 3,072
4100116202818 Water for mortars and concrete m³ 0,951
2952160007200 Lifting equipment for finishing works machine-
hours
0,336
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,841
109 CF17B
Various works – thickness difference, ±5
mm to base coat layer applied on walls,
executed with mortar
m² 146,30
7122050013400 Bricklayer man-
hours
16,825
9310060019920 Worker servicing ST man-
hours
5,047
2664102100000 Mortar m³ 0,878
2952160007200 Lifting equipment for finishing works machine-
hours
0,168
110 CN53A
Priming of interior wall surfaces
m² 146,30
7141020013300 Painter (plasterer-painter) man-
hours
5,047
2416586105303
2
Primer kg 21,945
810741 Dry sanding paper pieces 7,315
111 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar / 2 mm
m² 146,30
7122050013442 Plasterer man-
hours
205,259
2653102100831 Dry mix kg 1 044,582
4100116202818 Water for mortars and concrete m³ 0,585
2952160007200 Lifting equipment for finishing works machine-
hours
13,291
2952240004021 Electric mixer machine-
hours
2,692
112 CF51B Interior plastering 5
Стр. 34–36
r for mortars and concrete m³ 0,585
2952160007200 Lifting equipment for finishing works machine-
hours
13,291
2952240004021 Electric mixer machine-
hours
2,692
112 CF51B Interior plastering 5 mm thick, manually m² -146,30
1 2 3 4 5
k=3
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar. Difference in
addition or deduction for each 1.0 mm (to
be added to or deducted from item CF50)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
7122050013442 Plasterer man-
hours
-121,136
2653102100831 Dry mix kg -627,627
4100116202818 Water for mortars and concrete m³ -0,439
2952160007200 Lifting equipment for finishing works machine-
hours
-8,076
2952240004021 Electric mixer machine-
hours
-1,514
113 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 146,30
7122050013401 Mason, grade 4 man-
hours
75,71
9310060019920 Worker servicing ST man-
hours
16,825
2653102100833 Gypsum-based putty “Eurofin” kg 154,332
4100126202818 Water m³ 0,146
2952160007200 Lifting equipment for finishing works machine-
hours
0,168
114 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 146,30
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
23,554
2430226101010 Quartz primer “Gleta” kg 60,715
810741 Dry sanding paper pieces 7,315
115 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 146,30
7141020013300 Painter (plasterer-painter) man-
hours
92,535
2430116103800 Vinyl copolymer-based paint kg 58,52
2653102100830 Construction gypsum type A kg 8,778
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 73,15
1711317306661 Cleaning cotton kg 7,315
4100116202818 Water for mortars and concrete m³ 0,293
Total Type 3 (window sill
section)
9.4. Type 4 (partition walls, columns)
1 2 3 4 5
116 CN53A
Priming of interior wall surfaces
m² 560,00
7141020013300 Painter (plasterer-painter) man-
hours
19,32
2416586105303
2
Primer kg 84,00
810741 Dry sanding paper pieces 28,00
117 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar
m² 560,00
7122050013442 Plasterer man-
hours
785,68
2653102100831 Dry mix kg 3 998,40
4100116202818 Water for mortars and concrete m³ 2,24
2952160007200 Lifting equipment for finishing works machine-
hours
50,876
2952240004021 Electric mixer machine-
hours
10,304
118 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 560,00
7122050013401 Mason, grade 4 man-
hours
289,80
9310060019920 Worker servicing ST man-
Стр. 36–37
f gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 560,00
7122050013401 Mason, grade 4 man-
hours
289,80
9310060019920 Worker servicing ST man-
hours
64,40
2653102100833 Gypsum-based putty “Eurofin” kg 590,744
4100126202818 Water m³ 0,56
2952160007200 Lifting equipment for finishing works machine-
hours
0,644
119 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 560,00
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
90,16
2430226101010 Quartz primer “Gleta” kg 232,40
810741 Dry sanding paper pieces 28,00
120 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 560,00
7141020013300 Painter (plasterer-painter) man-
hours
354,20
2430116103800 Vinyl copolymer-based paint kg 224,00
2653102100830 Construction gypsum type A kg 33,60
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 280,00
1711317306661 Cleaning cotton kg 28,00
4100116202818 Water for mortars and concrete m³ 1,12
Total Type 4 (partition
1 2 3 4 5
walls, columns)
9.5. Finishing of the wall and partition
walls in the lower part
121 CD07B
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height up to 6 m
inclusive (cladding with HPL panels –
High Pressure Laminate)
m² 99,30
7214240021810 Construction locksmith (metal fitter) man-
hours
114,195
2732103646070
2
HPL panels (High Pressure Laminate) m² 110,223
2874125886734 POP (blind) rivets pieces 347,55
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 278,04
2922140007000 Crane machine-
hours
4,568
122 CD07B
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height up to 6 m
inclusive / stainless steel
m² 4,90
7214240021810 Construction locksmith (metal fitter) man-
hours
5,635
2732103646070
21
Stainless steel m² 5,439
2874125886734 POP (blind) rivets pieces 17,15
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 13,72
2922140007000 Crane machine-
hours
0,225
123 RCsP38F
Aluminium frame
tonne 0,13
7214210026800 Metal structure installer man-
hours
6,055
9310060019922 Service worker man-
hours
0,598
2811106301200
1
Aluminium frame kg 130,00
2735725901235 Covered electrode E 51 2R 2 × 350 mm S 1125/2 kg 0,065
2874115802501 Bolt M20 pieces 1,30
2874115840601 Hexagonal nut M20 pieces 1,30
2874115883700 Washer M20 pieces 1,30
2413547308164 Technical calcium carbide (carbide) S102 kg 0,016
2411115904512 Technical gaseous oxygen S2031 m³ 0,023
2811236309900 Metal fabrications kg 0,13
2410520006751 Truck crane, 4.5–9.9 ton-force (TF); machine-
hours
0,149
3110500003004 Welding inverter, 14 kW machine-
hours
0,075
Total Finishing of the
wall and partition walls in
Стр. 37–39
20006751 Truck crane, 4.5–9.9 ton-force (TF); machine-
hours
0,149
3110500003004 Welding inverter, 14 kW machine-
hours
0,075
Total Finishing of the
wall and partition walls in
the lower part
1 2 3 4 5
Total Interior finishing
(Walls)
10. Exterior finishing
10.1. Ventilated façade from ceramic
granite panels
124 CL53A
Installation of ventilated façade system
with cladding of building walls and
structures with linear metal panels
arranged horizontally with concealed
fixing, with architectural details surface
up to 30% of the total wall surface. Note:
the resource with norm 0.00 (zero) shall
be taken in accordance with the project
(Aluminium composite panel made of
ACP)
Small materials (self-tapping screws) = 1,005
m² 335,80
9310060019930 Worker man-
hours
647,607
2811236304899
1
Linear metal façade panels with complete set of
substructure elements and fixing components for
ventilated façade cladding (brackets, bearing
profiles, anchors, clamps, etc.) (Aluminium
composite panel made of AK-AR)
m² 371,227
2521302602900 Thermal insulation boards m² 347,603
2614122601913 Glass fiber mat type 160 g/m² m² 371,227
2523156719204 Plastic dowels with screws 8 × 100 reinforced
with glass fibers
pieces 2 531,092
3410520001102 Truck crane 10 ton-force (tf) machine-
hours
7,723
2952160007200 Lifting equipment for finishing works machine-
hours
88,433
2940520007609 Electric drill with carbide (widia) bit machine-
hours
15,447
2952270007609 Electric drilling machine machine-
hours
106,197
2940520004058 Disc cutting machine machine-
hours
1,699
Total Ventilated façade
from ceramic granite
panels
10.2. Node 1 (Parapet cladding along axis
“RAZ”)
125 CD08A1
Fiber cement boards FC thickness 12 mm
(walls made of cement-bonded particle
boards CBPB – 12 mm)
Small materials (galvanized metal accessories for
walls, sealing compound for gaskets) = 1,050
m² 123,00
7214240021810 Construction locksmith (metal fitter) man- 114,575
1 2 3 4 5
hours
2521306717875
12
Fiber cement boards FC thickness 12 mm (walls
made of cement-bonded particle boards CBPB –
12 mm)
m² 180,81
2874125886734 POP (blind) rivets pieces 516,60
2922140007000 Crane machine-
hours
7,072
126 CD73A
Walls made of lightweight panels from
profiled sheet metal with thermal
insulation, “Sandwich” type, mounted on
metal or reinforced concrete purlins at
heights under 12 m: arranged in front of
the purlins. Note: (Sandwich panels type
IZOTHERM SCw thickness 100 mm,
with mineral wool board core)
Small materials (silicone, self-tapping screws,
spacer dowels) = 1,030
m² 243,20
7214240021810 Construction locksmith (metal fitter) man-
hours
349,60
9310060019922 Service worker man-
hours
33,562
2811236304903
100
Sandwich panels – 100 mm (walls) m² 255,506
2523156720005 Finishing profile kg 801,587
2874115
Стр. 39–40
l fitter) man- hours 349,60 9310060019922 Service worker man- hours 33,562 2811236304903 100 Sandwich panels – 100 mm (walls) m² 255,506 2523156720005 Finishing profile kg 801,587 2874115836895 Screws dimensions in mm 6.3/5.5 × 180 pieces 751,488 2874115836896 Sealing washer with EPDM rubber gasket pieces 751,488 2416566101572 Polyurethane foam kg 43,837 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 27,968 127 CD73A Walls made of lightweight panels from profiled sheet metal with thermal insulation, “Sandwich” type, mounted on metal or reinforced concrete purlins at heights under 12 m: arranged in front of the purlins. Note: (Sandwich panels type IZOTHERM SCw thickness 50 mm, with mineral wool board core) Small materials (silicone, self-tapping screws, spacer dowels) = 1,030 m² 226,90 7214240021810 Construction locksmith (metal fitter) man- hours 326,169 9310060019922 Service worker man- hours 31,312 2811236304903 50 Sandwich panels – 50 mm (roof) m² 238,381 2523156720005 Finishing profile kg 747,862 2874115836895 Screws dimensions in mm 6.3/5.5 × 180 pieces 701,121 2874115836896 Sealing washer with EPDM rubber gasket pieces 701,121 2416566101572 Polyurethane foam kg 40,899 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 26,093 128 IzF14B Sound insulation layer executed with mineral wool boards TEHNOVENT m² 229,50 1 2 3 4 5 thickness 30 mm 7134050013240 Thermal insulator man- hours 42,228 2682162611373 0 Mineral wool boards TEHNOVENT thickness 30 mm m² 234,09 129 CD07A1 Walls made of corrugated galvanized sheet panels fixed by shooting onto metal framework, installed at a height greater than 6 m / aluminium composite panel (ACP) m² 505,80 7214240021810 Construction locksmith (metal fitter) man- hours 552,586 2732103646070 1 Corrugated sheet aluminium composite panel (ACP) m² 561,438 2874125886734 POP (blind) rivets pieces 1 770,30 2874115893397 Tornado bolt K 6/20 OL50 pieces 1 416,24 2461117308504 Cartridges for TORNADO bolt gun pieces 1 416,24 2922140007000 Crane machine- hours 29,084 130 CL54B Façade system made of extruded aluminium lamellas. m² 196,20 9310060019930 Worker man- hours 328,179 2811236304901 1 Façade system LINIUS (made of extruded aluminium lamellas) m² 231,516 2614122601913 Glass fiber mat type 160 g/m² m² 202,086 2952160007200 Lifting equipment for finishing works machine- hours 23,42 2952270007609 Electric drilling machine machine- hours 47,834 2940520004058 Disc cutting machine machine- hours 2,708 2940520007609 Electric drill with carbide (widia) bit machine- hours 6,995 131 IzF14B Sound insulation layer executed with mineral wool boards Tehnoruf H35 thickness 100 mm m² 14,60 7134050013240 Thermal insulator man- hours 2,686 2682162611371 00 Mineral wool boards Tehnoruf H35 thickness 100 mm m² 14,892 132 CK26B Flashing strip Rannila 120 mm m
Стр. 40–41
0 mm
m² 14,60
7134050013240 Thermal insulator man-
hours
2,686
2682162611371
00
Mineral wool boards Tehnoruf H35 thickness 100
mm
m² 14,892
132 CK26B
Flashing strip Rannila 120 mm
m 418,60
7422010060100 Carpenter (joiner) man-
hours
154,045
9310060019920 Worker servicing ST man-
hours
38,511
2743123549026
52301
Flashing strip Rannila 120 mm m 418,60
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 1 674,40
2952160007200 Lifting equipment for finishing works machine- 4,814
1 2 3 4 5
hours
133 СF59A
Cladding of surfaces with one layer of
gypsum plasterboard (GYP) 12.5 mm
with execution of single flat metal
framework, with height up to 4 m: walls
without insulation
Small materials (water, sanding paper, etc.) =
1,005
m² 215,70
9310060019930 Worker man-
hours
443,274
2662102701000 Gypsum plasterboard panels 12.5 mm m² 227,617
2710703520284 Guide profile m 159,332
2710703520285 Support profile m 476,913
2521302602900 Thermal insulation boards m² 223,282
2523156720072 Sealing tape under profiles “Dihtungsband” m 509,429
2513206621602 Joint tape “Serpeanca” m 164,21
2430226102822 Gypsum-based joint compound “Fugenfüller
Leicht”
kg 58,747
2430226101017 Primer “Tiefengrund” kg 18,968
2051142950711
1
Dowels with screws 8 × 80 mm for fixing metal
profiles
pieces 325,168
2874115833871 Self-tapping screws 3.5 × 25 mm pieces 2 798,61
2952160007200 Lifting equipment for finishing works machine-
hours
1,588
2952270007609 Electric drilling machine machine-
hours
10,468
Total Node 1 (Parapet
cladding along axis
“RAZ”)
10.3. Node 2 (Gutter + hoppers, 7 pieces)
134 CE05B1
Roof coverings made of flat galvanized
sheet metal or flat sheet metal protected
against corrosion, fixed with clamps,
executed with double seams in both
directions, carried out on surfaces smaller
than or equal to 40 m² with sheets of 0.5
mm thickness, including execution of
valleys, flashings, connections to
chimneys, etc.
Small materials (mineral oil, zinc white, tin, alloy,
ready-prepared red lead paint) = 1,050
m² 0,80
7213050013100 Tinsmith man-
hours
0,874
9310060019920 Worker servicing ST man-
hours
0,046
2710403642299 Flat galvanized sheet 0.5 × 1000 × 650 mm kg 4,662
2873145887450 Sheet metal nails kg 0,025
2873147300863 Clamps kg 0,21
2952160007200 Lifting equipment for finishing works machine-
hours
0,009
Стр. 41–43
Flat galvanized sheet 0.5 × 1000 × 650 mm kg 4,662
2873145887450 Sheet metal nails kg 0,025
2873147300863 Clamps kg 0,21
2952160007200 Lifting equipment for finishing works machine-
hours
0,009
1 2 3 4 5
135 IzF53A
Manual execution of floor substrate with
thermal insulation layer made of extruded
polystyrene boards XPS – 40 mm
Small materials (metal bars D = 6–8 mm, length
400 mm) = 1,015
m² 47,90
7134050013250 Insulator man-
hours
3,856
9310060019922 Service worker man-
hours
2,754
2670112204002
40
Extruded polystyrene boards XPS – 40 mm m² 49,591
2922140006702 Window crane machine-
hours
0,22
136 IzF14B
Sound insulation layer executed with
mineral wool boards TEHNOVENT
thickness 30 mm
m² 69,70
7134050013240 Thermal insulator man-
hours
12,825
2682162611373
0
Mineral wool boards TEHNOVENT thickness 30
mm
m² 71,094
137 CE05A
Roof coverings made of flat galvanized
sheet metal or flat sheet metal protected
against corrosion, fixed with clamps,
executed with double seams in both
directions, carried out on surfaces larger
than 40 m² with sheets of 0.4 mm
thickness, including execution of valleys,
flashings, connections to chimneys, etc.
Small materials (mineral oil, zinc white, tin, alloy,
ready-prepared red lead paint) = 1,050
m² 69,70
7213050013100 Tinsmith man-
hours
60,116
9310060019920 Worker servicing ST man-
hours
4,008
2710403641817 Flat galvanized sheet 0.4 × 1000 × 650 mm kg 325,673
2873145887450 Sheet metal nails kg 2,196
2873147300863 Clamps kg 18,296
2952160007200 Lifting equipment for finishing works machine-
hours
0,802
Total Node 2 (Gutter +
hoppers, 7 pieces)
Total Exterior finishing
Total
Social fund
Total
Transportation of materials
Storage expenses
Direct expenses
Overhead expenses
Total
Estimated profit
Total estimate:
Including wages
Subsemnata, Poleaco va Ana, tradu cător
autorizat, (limba Englez ă), certific
exactitatea traducerii cu textul
înscrisului, care a fost vizată de mine şi
port răspundere personală pentru
corectitudinea traducerii actului.
Undersigned, Poleacova Ana, sworn translator,
(English language), certify the authenticity of
the translation which corresponds to the text
of the authentic document, which was
confirmed by me and I do take personal
responsibility for the truthfulness of the
translation.
26.02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,
Authorization AT No. 461 of 10.02.2014, AT No. 500 of 21.07.2014,
English, French, Romanian, Russian, Translator
Стр. 43
02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,