eng5 2-2-2 bloc 1b (sa).rtf f.pdf
Стр. 1–2
Translation from Romanian and Russian into English
2026-404
Reconstruction of the terminal
building of “Eugen Doga”
International Airport - Chisinau
(cadastral no. 0100120.236.01),
including partial replanning of
internal spaces and building
extension
Form No. 1B
(name of the facility) WinEstimate
Cost Estimate-Offer No. 2-2-2
BLOCK 1B Phase 3
Architectural (A section)
(name of works)
Coefficient for basic wages = 1,150
Coefficient for cost of machine operation = 1,150
No. Norm
symbol and
resource
code
Description of works
Unit of
measure
(U.M.)
Quantity
according to the
design data
1 2 3 4 5
1. Demolition Works
1 RCsO56A
Dismantling of exterior stained-glass
glazing (stained-glass units)
m² 650,00
7422010060100 Carpenter (joiner) man-
hours
239,20
9310060019920 Worker servicing ST man-
hours
239,20
Total Demolition Works
2. Roof
2.1. Detail A (S = 602.5 m²)
2 CE17A
Additional polymer layer type Ondutiss
mounted under the roofing layer of tiles,
corrugated or embossed sheets /
Membrane Tehnonicol Parobarrier C
Small materials = 1,030
m² 602,50
7134030012200 Waterproofing installer man-
hours
138,575
9310060019920 Worker servicing ST man- 34,644
1 2 3 4 5
hours
2682132600465 Additional polymer foil m² 713,661
2875276312000
1
Studs (pins) pieces 7 446,90
2952160007200 Lifting equipment for finishing works machine-
hours
6,929
3 IzF11B
Thermal insulation layer on terraces,
roofs and slabs, executed with granulite,
on horizontal or inclined surfaces up to
7% / thickness 50…130 mm
m³ 54,23
7134030012200 Waterproofing installer man-
hours
100,407
2873122005400 Granulite for concrete m³ 56,399
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
17,462
4 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for
general insulation, supported with
galvanized soft steel wire / mineral wool
Tehnoruf H35 thickness 100 mm (105–
135 kg/m³)
m² 602,50
7134050013240 Thermal insulator man-
hours
367,224
2682162611371
100
Mineral wool boards Tehnoruf H35 thickness 100
mm (105–135 kg/m³)
m² 614,55
2734113805786 Galvanized soft steel wire d = 1 mm kg 135,562
5 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for
general insulation, supported with
galvanized soft steel wire / Mineral wool
Tehnoruf B60 thickness 50 mm (165–195
kg/m³)
m² 602,50
7134050013240 Thermal insulator man-
hours
367,224
2682162611371
50
Mineral wool boards Tehnoruf B60 thickness 50
mm (105-135 kg/m³)
m² 614,55
2734113805786 Galvanized soft steel wire d = 1 mm kg 135,562
6 CE13A2
Roof coverings with modified bituminous
membranes torch-applied in a two-layer
system, on horizontal surfaces
Стр. 2–3
)
m² 614,55
2734113805786 Galvanized soft steel wire d = 1 mm kg 135,562
6 CE13A2
Roof coverings with modified bituminous
membranes torch-applied in a two-layer
system, on horizontal surfaces mounted
on a continuous substrate (I layer –
Tehnoelast FIX, II layer – Tehnoelast
EKP)
Small materials = 1,050
m² 602,50
7134030012200 Waterproofing installer man-
hours
311,794
9310060019920 Worker servicing ST man-
hours
159,361
2682132600470
13
Bituminous membrane Tehnoelast FIX m² 727,519
1 2 3 4 5
2682132600470
12
Bituminous membrane Tehnoelast EKP m² 727,519
2320216201058 Butane gas (cylinders) kg 379,575
2921140007681 Flame burner machine-
hours
138,575
2952160007200 Lifting equipment for finishing works machine-
hours
41,572
Total Detail A (S = 602.5
m²)
2.2. Detail B (S = 53 m²)
7 CE06A
Roof coverings made of profiled sheet
metal protected against corrosion,
corrugated or ribbed, mounted on metal
purlins, executed on surfaces larger than
40 m² with profiled sheets fixed with
special clamps and mechanical screws at
the upper flange, including execution of
valleys, flashings, connections to
chimneys, etc. / profiled sheet Rannila
RAN 70
Small materials (material for bonding sheet metal)
= 1,050
m² 53,00
7213050013100 Tinsmith man-
hours
67,045
9310060019920 Worker servicing ST man-
hours
6,095
2710403642000
2
Galvanized corrugated or ribbed sheet / profiled
sheet Rannila RAN 70
m² 63,997
2710403643220 Flat galvanized sheet 0.75 mm kg 33,39
2874125886734 POP (blind) rivets pieces 278,25
2874115837746 Mechanical screws pieces 278,25
2710703434927 Flat steel 30 × 6 mm kg 18,086
2430226103064 Profiled mastic cord kg 5,565
2952160007200 Lifting equipment for finishing works machine-
hours
1,341
8 CE17A
Additional polymer layer type Ondutiss
mounted under the roofing layer of tiles,
corrugated or embossed sheets /
Membrane Tehnonicol Parobarrier C
Small materials = 1,030
m² 53,00
7134030012200 Waterproofing installer man-
hours
12,19
9310060019920 Worker servicing ST man-
hours
3,047
2682132600465 Additional polymer foil m² 62,778
2875276312000
1
Studs (pins) pieces 655,08
2952160007200 Lifting equipment for finishing works machine-
hours
0,609
9 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for m² 53,00
Стр. 3–5
ds (pins) pieces 655,08
2952160007200 Lifting equipment for finishing works machine-
hours
0,609
9 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for m² 53,00
1 2 3 4 5
general insulation, supported with
galvanized soft steel wire / mineral wool
Tehnoruf H35 thickness 100 mm (105–
135 kg/m³)
7134050013240 Thermal insulator man-
hours
32,303
2682162611371
100
Mineral wool boards Tehnoruf H35 thickness 100
mm (105–135 kg/m³)
m² 54,06
2734113805786 Galvanized soft steel wire d = 1 mm kg 11,925
10 IzF14C
Sound insulation layer for suspended
ceilings made of mineral wool boards for
general insulation, supported with
galvanized soft steel wire / Mineral wool
Tehnoruf B60 thickness 50 mm (165–195
kg/m³)
m² 53,00
7134050013240 Thermal insulator man-
hours
32,303
2682162611371
50
Mineral wool boards Tehnoruf B60 thickness 50
mm (105-135 kg/m³)
m² 54,06
2734113805786 Galvanized soft steel wire d = 1 mm kg 11,925
11 CE13A2
Roof coverings with modified bituminous
membranes torch-applied in a two-layer
system, on horizontal surfaces mounted
on a continuous substrate (I layer –
Tehnoelast FIX, II layer – Tehnoelast
EKP)
Small materials = 1,050
m² 53,00
7134030012200 Waterproofing installer man-
hours
27,427
9310060019920 Worker servicing ST man-
hours
14,018
2682132600470
13
Bituminous membrane Tehnoelast FIX m² 63,997
2682132600470
12
Bituminous membrane Tehnoelast EKP m² 63,997
2320216201058 Butane gas (cylinders) kg 33,39
2921140007681 Flame burner machine-
hours
12,19
2952160007200 Lifting equipment for finishing works machine-
hours
3,657
Total Detail B (S = 53 m²)
2.3. On axis 28, A–Y
12 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete
kg 512,50
7214240021810 Construction locksmith (metal fitter) man- 111,981
1 2 3 4 5
hours
9310060019920 Worker servicing ST man-
hours
5,894
7212030022700 Welder man-
hours
5,894
2775276309886 Metal fabrications embedded in concrete kg 512,50
2734113803207 Soft black wire, diameter 2 mm kg 5,125
2873155901200 Welding electrodes kg 2,562
4011106202741 Electrical energy kw 4,10
13 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,513
7141020013400 Industrial painter man-
hours
3,799
2430116100000 Chlorinated rubber enamel kg 4,001
2430226100814 Red lead primer G 355-6 kg 2,001
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,282
2320166200676 White spirit kg 1,00
1711317306661 Cleaning cotton kg 0,50
14 CD73A
Walls made of lightweight panels from
profiled sheet metal with thermal
insulation, “Sandwich” type, mounted on
metal or re
Стр. 5–6
White spirit kg 1,00
1711317306661 Cleaning cotton kg 0,50
14 CD73A
Walls made of lightweight panels from
profiled sheet metal with thermal
insulation, “Sandwich” type, mounted on
metal or reinforced concrete purlins at
heights under 12 m: arranged in front of
the purlins. Note: (Sandwich panels type
IZOTHERM SCw thickness 100 mm,
with mineral wool board core)
Small materials (silicone, self-tapping screws,
spacer dowels) = 1,030
m² 21,30
7214240021810 Construction locksmith (metal fitter) man-
hours
30,619
9310060019922 Service worker man-
hours
2,939
2811236304903
100
Sandwich panels – 100 mm (walls) m² 22,378
2523156720005 Finishing profile kg 70,205
2874115836895 Screws dimensions in mm 6.3/5.5 × 180 pieces 65,817
2874115836896 Sealing washer with EPDM rubber gasket pieces 65,817
2416566101572 Polyurethane foam kg 3,839
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
2,45
15 CE05B
Roof coverings made of flat galvanized
sheet metal or flat sheet metal protected
against corrosion, fixed with clamps,
executed with double seams in both
directions, carried out on surfaces larger
than 40 m² with sheets of 0.5 mm
thickness / apron
Small materials (mineral oil, zinc white, tin, alloy,
m² 18,00
1 2 3 4 5
ready-prepared red lead paint) = 1,050
7213050013100 Tinsmith man-
hours
15,525
9310060019920 Worker servicing ST man-
hours
1,035
2710403642299 Flat galvanized sheet 0.5 × 1000 × 650 mm kg 104,895
2873145887450 Sheet metal nails kg 0,567
2873147300863 Clamps kg 4,725
2952160007200 Lifting equipment for finishing works machine-
hours
0,207
16 CE25B
Additional sealing along the perimeter, at
penetrations or joints with expanded
polymer profiles
Small materials (adhesive, thinner) = 1,050
m 35,50
7134030012200 Waterproofing installer man-
hours
6,124
9310060019920 Worker servicing ST man-
hours
2,041
2812106306005 Expanded polymer profile m 41,003
17 CK35B
Metal dowels fixed in reinforced concrete
walls (chemical anchor)
pieces 60,00
7422010060100 Carpenter (joiner) man-
hours
13,80
2874136313300
1
(chemical anchor pieces 60,00
Total On axis 28, A–Y
Total Roof
3. Doors
18 CK21A
Doors made of aluminium profiles,
including the fittings and accessories
necessary for doors installed in masonry
of any type, in constructions with height
up to 35 m inclusive, single-leaf, with
frame area up to 7 m² inclusive (U29
interior doors 1850 × 2100)
m² 7,77
7214210026800 Metal structure installer man-
hours
7,595
9310060019920 Worker servicing ST man-
hours
0,894
2812106306050
1
Aluminium profile doors (blind) m² 7,77
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 31,08
2416566101572 Polyurethane foam kg 3,885
2430226101600 Silicone sealant kg 1,36
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 4,662
4011106202741 Electrical energ
Стр. 6–8
× 30 mm pieces 31,08
2416566101572 Polyurethane foam kg 3,885
2430226101600 Silicone sealant kg 1,36
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 4,662
4011106202741 Electrical energy kw 7,77
2952160007200 Lifting equipment for finishing works machine-
hours
0,179
1 2 3 4 5
Total Doors
4. Glazing
4.1. Interior glazing (Aluminium glazing
units with sound-insulating mirror glass
“Planibel Dark Blue”, inner glass
“Triplex”)
19 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-1,
18050*3300,)
m² 59,57
7214210026800 Metal structure installer man-
hours
47,954
9310060019920 Worker servicing ST man-
hours
3,425
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 62,549
2681126001472
1
Oil for metal accessories kg 0,596
2430226102111 ROMALCHIT putty kg 7,148
2416566101572 Polyurethane foam kg 20,849
2410520006700 Truck crane machine-
hours
0,343
20 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-
21, 39850*3300,)
m² 131,51
7214210026800 Metal structure installer man-
hours
105,866
9310060019920 Worker servicing ST man-
hours
7,562
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 138,085
2681126001472
1
Oil for metal accessories kg 1,315
2430226102111 ROMALCHIT putty kg 15,781
2416566101572 Polyurethane foam kg 46,028
2410520006700 Truck crane machine-
hours
0,756
21 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-3,
2100*3300,)
m² 34,65
1 2 3 4 5
7214210026800 Metal structure installer man-
hours
27,893
9310060019920 Worker servicing ST man-
hours
1,992
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 36,383
2681126001472
1
Oil for metal accessories kg 0,346
2430226102111 ROMALCHIT putty kg 4,158
2416566101572 Polyurethane foam kg 12,127
2410520006700 Truck crane machine-
hours
0,199
22 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-4,
16000*3300,)
m² 52,80
7214210026800 Metal structure installer man-
hours
42,504
9310060019920 Worker servicing ST man-
hours
3,036
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 55,44
2681126001472
1
Oil for metal accessories kg 0,528
2430226102111 ROMALCHIT putty kg 6,336
2416566101572 Polyurethane foam kg 18,48
2410520006
Стр. 8–9
zing units made of aluminium profiles m² 55,44 2681126001472 1 Oil for metal accessories kg 0,528 2430226102111 ROMALCHIT putty kg 6,336 2416566101572 Polyurethane foam kg 18,48 2410520006700 Truck crane machine- hours 0,304 23 CK11B Prefabricated shopfront glazing units, installed in masonry of any type, with area between 7.5–10.0 m², in constructions mounted at heights up to 5 m inclusive, made of aluminium (VI/B-5, 18250*3300,) m² 60,255 7214210026800 Metal structure installer man- hours 48,505 9310060019920 Worker servicing ST man- hours 3,465 2523146720200 Prefabricated shopfront glazing units made of aluminium profiles m² 63,268 2681126001472 1 Oil for metal accessories kg 0,603 2430226102111 ROMALCHIT putty kg 7,231 2416566101572 Polyurethane foam kg 21,089 2410520006700 Truck crane machine- hours 0,346 24 CK11B Prefabricated shopfront glazing units, installed in masonry of any type, with area between 7.5–10.0 m², in constructions mounted at heights up to 5 m inclusive, made of aluminium (VI/B-6, 2540*3300,) m² 16,764 1 2 3 4 5 7214210026800 Metal structure installer man- hours 13,495 9310060019920 Worker servicing ST man- hours 0,964 2523146720200 Prefabricated shopfront glazing units made of aluminium profiles m² 17,602 2681126001472 1 Oil for metal accessories kg 0,168 2430226102111 ROMALCHIT putty kg 2,012 2416566101572 Polyurethane foam kg 5,867 2410520006700 Truck crane machine- hours 0,096 25 CK11B Prefabricated shopfront glazing units, installed in masonry of any type, with area between 7.5–10.0 m², in constructions mounted at heights up to 5 m inclusive, made of aluminium (VI/B- 7,4500*3300,) m² 14,85 7214210026800 Metal structure installer man- hours 11,954 9310060019920 Worker servicing ST man- hours 0,854 2523146720200 Prefabricated shopfront glazing units made of aluminium profiles m² 15,593 2681126001472 1 Oil for metal accessories kg 0,148 2430226102111 ROMALCHIT putty kg 1,782 2416566101572 Polyurethane foam kg 5,197 2410520006700 Truck crane machine- hours 0,085 26 CK11B Prefabricated shopfront glazing units, installed in masonry of any type, with area between 7.5–10.0 m², in constructions mounted at heights up to 5 m inclusive, made of aluminium (VI/B-8, 20500*3300,) m² 67,65 7214210026800 Metal structure installer man- hours 54,458 9310060019920 Worker servicing ST man- hours 3,89 2523146720200 Prefabricated shopfront glazing units made of aluminium profiles m² 71,033 2681126001472 1 Oil for metal accessories kg 0,677 2430226102111 ROMALCHIT putty kg 8,118 2416566101572 Polyurethane foam kg 23,678 2410520006700 Truck crane machine- hours 0,389 27 CK11B Prefabricated shopfront glazing units, installed in masonry of any type, with area between 7.5–10.0 m², in constructions mounted at heights up to 5 m inclusive, made of aluminium (VI/B-9, m² 52,19
Стр. 9–11
refabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-9,
m² 52,19
1 2 3 4 5
15800*3300,)
7214210026800 Metal structure installer man-
hours
42,013
9310060019920 Worker servicing ST man-
hours
3,001
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 54,80
2681126001472
1
Oil for metal accessories kg 0,522
2430226102111 ROMALCHIT putty kg 6,263
2416566101572 Polyurethane foam kg 18,266
2410520006700 Truck crane machine-
hours
0,30
28 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VI/B-
10, 16850*3300,)
m² 55,605
7214210026800 Metal structure installer man-
hours
44,762
9310060019920 Worker servicing ST man-
hours
3,197
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 58,385
2681126001472
1
Oil for metal accessories kg 0,556
2430226102111 ROMALCHIT putty kg 6,673
2416566101572 Polyurethane foam kg 19,462
2410520006700 Truck crane machine-
hours
0,32
Total Interior glazing
(Aluminium glazing units
with sound-insulating
mirror glass “Planibel
Dark Blue”, inner glass
“Triplex”)
4.2. Exterior glazing
29 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VE-23,
62370*9300)
m² 580,04
7214210026800 Metal structure installer man-
hours
466,932
9310060019920 Worker servicing ST man-
hours
33,352
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 609,042
1 2 3 4 5
2681126001472
1
Oil for metal accessories kg 5,80
2430226102111 ROMALCHIT putty kg 69,605
2416566101572 Polyurethane foam kg 203,014
2410520006700 Truck crane machine-
hours
3,335
30 CK11B
Prefabricated shopfront glazing units,
installed in masonry of any type, with
area between 7.5–10.0 m², in
constructions mounted at heights up to 5
m inclusive, made of aluminium (VE-24,
32700*9300)
m² 304,11
7214210026800 Metal structure installer man-
hours
244,809
9310060019920 Worker servicing ST man-
hours
17,486
2523146720200 Prefabricated shopfront glazing units made of
aluminium profiles
m² 319,316
2681126001472
1
Oil for metal accessories kg 3,041
2430226102111 ROMALCHIT putty kg 36,493
2416566101572 Polyurethane foam kg 106,439
2410520006700 Truck crane machine-
hours
1,749
Total Exterior glazing
4.3. Skylight
31 CK10A
Simple metal skylights, fixed or with
movable sashes, installed in constructions
of any type, including the necessary
accessories such as: gutters for collecting
water
Стр. 11–12
Skylight
31 CK10A
Simple metal skylights, fixed or with
movable sashes, installed in constructions
of any type, including the necessary
accessories such as: gutters for collecting
water resulting from condensation,
protective devices against water
penetration from precipitation at changes
of slopes and at glazing edges, etc.
(Installation of skylights, dimensions
14,800 × 2,250 mm, with remote
opening, 3 pieces)
m² 99,90
7214210026800 Metal structure installer man-
hours
189,56
7141020013300 Painter (plasterer-painter) man-
hours
45,954
9310060019920 Worker servicing ST man-
hours
17,233
2523146720400 Metal skylight, including accessories m² 99,90
2873155900800 Welding electrodes kg 1,998
4011106202741 Electrical energy kw 4,995
2430226100034 Anticorrosive red lead primer G.351-4 S 3097-80 kg 7,992
2651122100402 Metallurgical cement with additives M 30, bags
S1500
kg 119,88
1421102200496 Sorted unwashed river and lake sand 0.0–1.0 mm m³ 0,40
4100116202818 Water for mortars and concrete m³ 0,10
1 2 3 4 5
2410520006700 Truck crane machine-
hours
2,298
Total Skylight
Total Glazing
5. Floor finishes
5.1. Level 1
32 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (50 mm)
m² 768,61
7132030012600 Mosaic worker man-
hours
530,341
9310060019920 Worker servicing ST man-
hours
88,39
2664102102010
150
Cement mortar M150 m³ 25,364
4100116202818 Water for mortars and concrete m³ 7,686
2952160007200 Lifting equipment for finishing works machine-
hours
26,517
2952270003817 Electric mortar mixer, 200 L machine-
hours
10,607
33 CG01A1
k=4
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 4,000
Coefficient for materials = 4,000
Coefficient for machines = 4,000
m² 768,61
7132030012600 Mosaic worker man-
hours
353,561
9310060019920 Worker servicing ST man-
hours
70,712
2664102102010
150
Cement mortar M150 m³ 16,909
4100116202818 Water for mortars and concrete m³ 6,149
2952160007200 Lifting equipment for finishing works machine-
hours
10,607
2952270003817 Electric mortar mixer, 200 L machine-
hours
5,303
34 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 768,61
9310060019930 Worker man-
hours
2 116,06
2670112202052 Ceramic granite tiles m² 780,139
2462106110554 Adhesive based on acrylic resins or latex kg 3 305,023
2430226100000 Grout kg 153,722
Стр. 12–14
,61
9310060019930 Worker man-
hours
2 116,06
2670112202052 Ceramic granite tiles m² 780,139
2462106110554 Adhesive based on acrylic resins or latex kg 3 305,023
2430226100000 Grout kg 153,722
1 2 3 4 5
1
2881116002700 Abrasive disc pieces 15,372
4100126202818 Water m³ 3,074
2952270003205 Universal stone cutting machine machine-
hours
64,525
2922140006702 Window crane machine-
hours
10,253
2952270007607 Electric drilling machine with auger attachment machine-
hours
4,685
Total Level 1
5.2. Level 2
35 IzF53A
Manual execution of floor substrate with
thermal insulation layer made of extruded
polystyrene boards Tehnonicol Carbon
XPS – 20 mm (ρ = 35 kg/m³, λ = 0.032
W/mK)
Small materials (metal bars D = 6–8 mm, length
400 mm) = 1,015
m² 770,94
7134050013250 Insulator man-
hours
62,061
9310060019922 Service worker man-
hours
44,329
2670112204002
20
Extruded polystyrene boards XPS – 20 mm (ρ =
35 kg/m³, λ = 0.032 W/mK)
m² 798,154
2922140006702 Window crane machine-
hours
3,546
36 CG01A
Substrate layer for floors executed from
cement mortar M150, 3 cm thick, with
finely trowelled surface (60 mm)
m² 770,94
7132030012600 Mosaic worker man-
hours
531,949
9310060019920 Worker servicing ST man-
hours
88,658
2664102102010
150
Cement mortar M150 m³ 25,441
4100116202818 Water for mortars and concrete m³ 7,709
2952160007200 Lifting equipment for finishing works machine-
hours
26,597
2952270003817 Electric mortar mixer, 200 L machine-
hours
10,639
37 CG01A1
k=6
Substrate layer for floors made of cement
mortar M150, 3 cm thick, with finely
trowelled surface. Difference in addition
or deduction for each 0.5 cm of substrate
layer made of cement mortar M150 shall
be added
Coefficient for labour input = 6,000
Coefficient for materials = 6,000
Coefficient for machines = 6,000
m² 770,94
7132030012600 Mosaic worker man- 531,949
1 2 3 4 5
hours
9310060019920 Worker servicing ST man-
hours
106,39
2664102102010
150
Cement mortar M150 m³ 25,441
4100116202818 Water for mortars and concrete m³ 9,251
2952160007200 Lifting equipment for finishing works machine-
hours
15,958
2952270003817 Electric mortar mixer, 200 L machine-
hours
7,979
38 CG50A
Execution of ceramic granite floor
finishes fixed with adhesive: tile
dimensions under 40 × 40 cm
m² 650,56
9310060019930 Worker man-
hours
1 791,057
2670112202052 Ceramic granite tiles m² 660,318
2462106110554 Adhesive based on acrylic resins or latex kg 2 797,408
2430226100000
1
Grout kg 130,112
2881116002700 Abrasive disc pieces 13,011
4100126202818 Water m³ 2,602
2952270003205 Universal stone cutting machine machine-
hours
54,615
2922140006702 Window crane machine-
hours
8,678
2952270007607 Electric drilling machine with auger attachment machine-
hours
3,965
Total Level 2
Total Floor finishes
Стр. 14–15
machine-
hours
8,678
2952270007607 Electric drilling machine with auger attachment machine-
hours
3,965
Total Level 2
Total Floor finishes
6. Interior finishing (Ceiling)
6.1. Level 1
39 CN53A
Priming of interior ceiling surfaces
m² 803,60
7141020013300 Painter (plasterer-painter) man-
hours
27,724
2416586105303
2
Primer kg 120,54
810741 Dry sanding paper pieces 40,18
40 CF52B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar (2
mm)
m² 803,60
7122050013442 Plasterer man-
hours
1 413,934
2653102100831 Dry mix kg 5 737,704
4100116202818 Water for mortars and concrete m³ 3,214
2952160007200 Lifting equipment for finishing works machine-
hours
73,007
2952240004021 Electric mixer machine-
hours
18,021
1 2 3 4 5
41 CF53B
k=3
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar.
Difference in addition or deduction for
each 1.0 mm (to be added to or deducted
from item CF52)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² -803,60
7122050013442 Plasterer man-
hours
-859,45
2653102100831 Dry mix kg -3 447,444
4100116202818 Water for mortars and concrete m³ -2,411
2952160007200 Lifting equipment for finishing works machine-
hours
-11,09
2952240004021 Electric mixer machine-
hours
-44,359
42 CN53A
Priming of interior wall surfaces
m² 803,60
7141020013300 Painter (plasterer-painter) man-
hours
27,724
2416586105303
2
Primer kg 120,54
810741 Dry sanding paper pieces 40,18
43 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 803,60
7141020013300 Painter (plasterer-painter) man-
hours
508,277
2430116103800 Vinyl copolymer-based paint kg 321,44
2653102100830 Construction gypsum type A kg 48,216
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 401,80
1711317306661 Cleaning cotton kg 40,18
4100116202818 Water for mortars and concrete m³ 1,607
44 CK52B
Suspended ceilings from “Griliato” strip
panels on metal frame with suspension
using strap and rod, in rooms with height
up to 4 m / suspended metal cassette
ceiling Griliato
Small materials (profile selector, rags) = 1,003
m² 803,60
9310060019930 Worker man-
hours
822,485
2662102701010 “Griliato” ceiling panels m² 822,131
2812106305912 Suspension with clamp and rod pieces 644,809
2812106305914 White 24 mm corner profiles m 902,732
2812106305915 Trapezoidal lamella profiles 35/30 m 677,049
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 174,098
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pieces 652,869
2952160007200 Lifting equipment for finishing works machine-
hour
Стр. 15–17
fixing metal profiles 6.0 × 40 mm pieces 174,098
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pieces 652,869
2952160007200 Lifting equipment for finishing works machine-
hours
3,327
1 2 3 4 5
2952270007609 Electric drilling machine machine-
hours
22,364
Total Level 1
6.2. Level 2
45 CN53A
Priming of interior ceiling surfaces
m² 693,00
7141020013300 Painter (plasterer-painter) man-
hours
23,908
2416586105303
2
Primer kg 103,95
810741 Dry sanding paper pieces 34,65
46 CF52B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar (2
mm)
m² 693,00
7122050013442 Plasterer man-
hours
1 219,333
2653102100831 Dry mix kg 4 948,02
4100116202818 Water for mortars and concrete m³ 2,772
2952160007200 Lifting equipment for finishing works machine-
hours
62,959
2952240004021 Electric mixer machine-
hours
15,541
47 CF53B
k=3
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
ceilings, manual preparation of mortar.
Difference in addition or deduction for
each 1.0 mm (to be added to or deducted
from item CF52)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² -693,00
7122050013442 Plasterer man-
hours
-741,163
2653102100831 Dry mix kg -2 972,97
4100116202818 Water for mortars and concrete m³ -2,079
2952160007200 Lifting equipment for finishing works machine-
hours
-9,563
2952240004021 Electric mixer machine-
hours
-38,254
48 CN53A
Priming of interior wall surfaces
m² 693,00
7141020013300 Painter (plasterer-painter) man-
hours
23,908
2416586105303
2
Primer kg 103,95
810741 Dry sanding paper pieces 34,65
49 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 693,00
1 2 3 4 5
7141020013300 Painter (plasterer-painter) man-
hours
438,322
2430116103800 Vinyl copolymer-based paint kg 277,20
2653102100830 Construction gypsum type A kg 41,58
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 346,50
1711317306661 Cleaning cotton kg 34,65
4100116202818 Water for mortars and concrete m³ 1,386
50 CK52B
Suspended ceilings from “Griliato” strip
panels on metal frame with suspension
using strap and rod, in rooms with height
up to 4 m / suspended metal cassette
ceiling Griliato
Small materials (profile selector, rags) = 1,003
m² 693,00
9310060019930 Worker man-
hours
709,285
2662102701010 “Griliato” ceiling panels m² 708,981
2812106305912 Suspension with clamp and rod pieces 556,063
2812106305914 White 24 mm corner profiles m 778,488
2812106305915 Trapezoidal lamella profiles 35/30 m 583,866
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 150,137
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pie
Стр. 17–18
6305915 Trapezoidal lamella profiles 35/30 m 583,866
2051142950713 Dowels for fixing metal profiles 6.0 × 40 mm pieces 150,137
2051142950712 Dowels for fixing ceiling suspensions 6.0 × 40
mm
pieces 563,014
2952160007200 Lifting equipment for finishing works machine-
hours
2,869
2952270007609 Electric drilling machine machine-
hours
19,286
Total Level 2
Total Interior finishing
(Ceiling)
7. Interior finishing (Walls)
7.1. Type 1 (external walls)
51 CF02B
Interior plastering 2 cm thick, trowelled,
manually executed, on walls or columns,
on plane surfaces with cement-lime
mortar grade M100-T for splash coat,
base coat and finishing coat, on brick
masonry or small concrete blocks / 25
mm
m² 77,80
7122050013400 Bricklayer man-
hours
89,47
9310060019920 Worker servicing ST man-
hours
17,894
2664102103001 Cement-lime mortar m³ 1,634
4100116202818 Water for mortars and concrete m³ 0,506
2952270003817 Electric mortar mixer, 200 L machine-
hours
0,447
2952160007200 Lifting equipment for finishing works machine- 0,179
1 2 3 4 5
hours
52 CF17B
Various works – thickness difference, ±5
mm to base coat layer applied on walls,
executed with mortar
m² 77,80
7122050013400 Bricklayer man-
hours
8,947
9310060019920 Worker servicing ST man-
hours
2,684
2664102100000 Mortar m³ 0,467
2952160007200 Lifting equipment for finishing works machine-
hours
0,089
53 CN53A
Priming of interior wall surfaces
m² 77,80
7141020013300 Painter (plasterer-painter) man-
hours
2,684
2416586105303
2
Primer kg 11,67
810741 Dry sanding paper pieces 3,89
54 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar / 2 mm
m² 77,80
7122050013442 Plasterer man-
hours
109,153
2653102100831 Dry mix kg 555,492
4100116202818 Water for mortars and concrete m³ 0,311
2952160007200 Lifting equipment for finishing works machine-
hours
7,068
2952240004021 Electric mixer machine-
hours
1,432
55 CF51B
k=3
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar. Difference in
addition or deduction for each 1.0 mm (to
be added to or deducted from item CF50)
Coefficient for labour input = 3,000
Coefficient for materials = 3,000
Coefficient for machines = 3,000
m² -77,80
7122050013442 Plasterer man-
hours
-64,418
2653102100831 Dry mix kg -333,762
4100116202818 Water for mortars and concrete m³ -0,233
2952160007200 Lifting equipment for finishing works machine-
hours
-4,295
2952240004021 Electric mixer machine-
hours
-0,805
56 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 77,60
Стр. 18–20
,295
2952240004021 Electric mixer machine-
hours
-0,805
56 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 77,60
1 2 3 4 5
7122050013401 Mason, grade 4 man-
hours
40,158
9310060019920 Worker servicing ST man-
hours
8,924
2653102100833 Gypsum-based putty “Eurofin” kg 81,86
4100126202818 Water m³ 0,078
2952160007200 Lifting equipment for finishing works machine-
hours
0,089
57 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 77,80
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
12,526
2430226101010 Quartz primer “Gleta” kg 32,287
810741 Dry sanding paper pieces 3,89
58 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 77,80
7141020013300 Painter (plasterer-painter) man-
hours
49,209
2430116103800 Vinyl copolymer-based paint kg 31,12
2653102100830 Construction gypsum type A kg 4,668
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 38,90
1711317306661 Cleaning cotton kg 3,89
4100116202818 Water for mortars and concrete m³ 0,156
Total Type 1 (external
walls)
7.2. Type 2 (gypsum plasterboard
partition walls, columns)
59 CN53A
Priming of interior wall surfaces
m² 182,50
7141020013300 Painter (plasterer-painter) man-
hours
6,296
2416586105303
2
Primer kg 27,375
810741 Dry sanding paper pieces 9,125
60 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar
m² 182,50
7122050013442 Plasterer man-
hours
256,047
2653102100831 Dry mix kg 1 303,05
4100116202818 Water for mortars and concrete m³ 0,73
2952160007200 Lifting equipment for finishing works machine-
hours
16,58
2952240004021 Electric mixer machine-
hours
3,358
1 2 3 4 5
61 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 182,50
7122050013401 Mason, grade 4 man-
hours
94,444
9310060019920 Worker servicing ST man-
hours
20,988
2653102100833 Gypsum-based putty “Eurofin” kg 192,519
4100126202818 Water m³ 0,182
2952160007200 Lifting equipment for finishing works machine-
hours
0,21
62 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 182,50
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
29,383
2430226101010 Quartz primer “Gleta” kg 75,737
810741 Dry sanding paper pieces 9,125
63 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 182,50
7141020013300 Painter (plasterer-painter) man-
hours
115,431
2430116103800 Vinyl copolymer-based paint kg 73,00
2653102100830 Co
Стр. 20–21
coats on existing putty layer, manually
executed
m² 182,50
7141020013300 Painter (plasterer-painter) man-
hours
115,431
2430116103800 Vinyl copolymer-based paint kg 73,00
2653102100830 Construction gypsum type A kg 10,95
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 91,25
1711317306661 Cleaning cotton kg 9,125
4100116202818 Water for mortars and concrete m³ 0,365
Total Type 2 (gypsum
plasterboard partition
walls, columns)
7.3. Type 3 (partition walls made of
gypsum plasterboard)
64 CN53A
Priming of interior wall surfaces
m² 133,20
7141020013300 Painter (plasterer-painter) man-
hours
4,595
2416586105303
2
Primer kg 19,98
810741 Dry sanding paper pieces 6,66
65 CF50B
Interior plastering 5 mm thick, manually
executed, with dry gypsum-based mix, on
walls and partition walls, manual
preparation of mortar
m² 133,20
7122050013442 Plasterer man-
hours
186,88
2653102100831 Dry mix kg 951,048
1 2 3 4 5
4100116202818 Water for mortars and concrete m³ 0,533
2952160007200 Lifting equipment for finishing works machine-
hours
12,101
2952240004021 Electric mixer machine-
hours
2,451
66 CF57A
Manual application of gypsum-based
putty “Eurofin”, thickness 1.0 mm, on
surfaces of walls, columns and ceilings
m² 133,20
7122050013401 Mason, grade 4 man-
hours
68,931
9310060019920 Worker servicing ST man-
hours
15,318
2653102100833 Gypsum-based putty “Eurofin” kg 140,513
4100126202818 Water m³ 0,133
2952160007200 Lifting equipment for finishing works machine-
hours
0,153
67 CN54A
Manual application of quartz primer
“Gleta” in one layer, on interior walls and
ceilings
m² 133,20
7141020013301 Painter (plasterer-painter), grade 3 man-
hours
21,445
2430226101010 Quartz primer “Gleta” kg 55,278
810741 Dry sanding paper pieces 6,66
68 CN06A
Interior painting with water-based vinyl
copolymer emulsion paint, applied in 2
coats on existing putty layer, manually
executed
m² 133,20
7141020013300 Painter (plasterer-painter) man-
hours
84,249
2430116103800 Vinyl copolymer-based paint kg 53,28
2653102100830 Construction gypsum type A kg 7,992
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 66,60
1711317306661 Cleaning cotton kg 6,66
4100116202818 Water for mortars and concrete m³ 0,266
Total Type 3 (partition
walls made of gypsum
plasterboard)
7.4. Finishing of the wall and partition
walls in the lower part
69 CD07B
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height up to 6 m
inclusive (cladding with HPL panels –
High Pressure Laminate)
m² 81,00
7214240021810 Construction locksmith (metal fitter) man-
hours
93,15
2732103646070
2
HPL panels (High Pressure Laminate) m² 89,91
Стр. 21–23
cladding with HPL panels –
High Pressure Laminate)
m² 81,00
7214240021810 Construction locksmith (metal fitter) man-
hours
93,15
2732103646070
2
HPL panels (High Pressure Laminate) m² 89,91
1 2 3 4 5
2874125886734 POP (blind) rivets pieces 283,50
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 226,80
2922140007000 Crane machine-
hours
3,726
70 CD07B
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height up to 6 m
inclusive / stainless steel
m² 12,10
7214240021810 Construction locksmith (metal fitter) man-
hours
13,915
2732103646070
21
Stainless steel m² 13,431
2874125886734 POP (blind) rivets pieces 42,35
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 33,88
2922140007000 Crane machine-
hours
0,557
71 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m / aluminium panel (AKL-FR)
m² 290,90
7214240021810 Construction locksmith (metal fitter) man-
hours
317,808
2732103646070
11
Tempered glass m² 322,899
2874125886734 POP (blind) rivets pieces 1 018,15
2874115893397 Tornado bolt K 6/20 OL50 pieces 814,52
2461117308504 Cartridges for TORNADO bolt gun pieces 814,52
2922140007000 Crane machine-
hours
16,727
72 RCsP38F
Aluminium frame
tonne 0,46
7214210026800 Metal structure installer man-
hours
21,424
9310060019922 Service worker man-
hours
2,116
2811106301200
1
Aluminium frame kg 460,00
2735725901235 Covered electrode E 51 2R 2 × 350 mm S 1125/2 kg 0,23
2874115802501 Bolt M20 pieces 4,60
2874115840601 Hexagonal nut M20 pieces 4,60
2874115883700 Washer M20 pieces 4,60
2413547308164 Technical calcium carbide (carbide) S102 kg 0,055
2411115904512 Technical gaseous oxygen S2031 m³ 0,083
2811236309900 Metal fabrications kg 0,46
2410520006751 Truck crane, 4.5–9.9 ton-force (TF); machine-
hours
0,529
3110500003004 Welding inverter, 14 kW machine-
hours
0,265
Total Finishing of the
wall and partition walls in
the lower part
Total Interior finishing
1 2 3 4 5
(Walls)
8. Exterior finishing
8.1. Ventilated façade
73 CL53A
Installation of ventilated façade system
with cladding of building walls and
structures with linear metal panels
arranged horizontally with concealed
fixing, with architectural details surface
up to 30% of the total wall surface. Note:
the resource with norm 0.00 (zero) shall
be taken according to the design
(aluminium composite panel made of
AK-AR)
Small materials (self-tapping screws) = 1,005
m² 361,10
9310060019930 Worker man-
hours
696,399
2811236304899
1
Linear metal façade panels with complete set of
substructure elements and fixing components for
ventilated façade cladding (brackets, bearing
profiles, anchors, clamps, etc.) (Aluminium
composite panel made of AK-AR)
m² 399,196
252130260
Стр. 23–24
of
substructure elements and fixing components for
ventilated façade cladding (brackets, bearing
profiles, anchors, clamps, etc.) (Aluminium
composite panel made of AK-AR)
m² 399,196
2521302602900 Thermal insulation boards m² 373,793
2614122601913 Glass fiber mat type 160 g/m² m² 399,196
2523156719204 Plastic dowels with screws 8 × 100 reinforced
with glass fibers
pieces 2 721,791
3410520001102 Truck crane 10 ton-force (tf) machine-
hours
8,305
2952160007200 Lifting equipment for finishing works machine-
hours
95,096
2940520007609 Electric drill with carbide (widia) bit machine-
hours
16,611
2952270007609 Electric drilling machine machine-
hours
114,198
2940520004058 Disc cutting machine machine-
hours
1,827
Total Ventilated façade
8.2. Node 1
74 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m / aluminium composite panel
(ACP) exterior
m² 51,60
7214240021810 Construction locksmith (metal fitter) man-
hours
56,373
2732103646070
1
Corrugated sheet aluminium composite panel
(ACP)
m² 57,276
2874125886734 POP (blind) rivets pieces 180,60
2874115893397 Tornado bolt K 6/20 OL50 pieces 144,48
1 2 3 4 5
2461117308504 Cartridges for TORNADO bolt gun pieces 144,48
2922140007000 Crane machine-
hours
2,967
75 CE17A
Additional polymer layer type Ondutiss
installed under the roofing layer of tiles,
corrugated or embossed sheets (Hydro-
windproof membrane)
Small materials = 1,030
m² 49,10
7134030012200 Waterproofing installer man-
hours
11,293
9310060019920 Worker servicing ST man-
hours
2,823
2682132600465
1
Additional polymer foil Hydro-windproof
membrane
m² 58,159
2875276312000
1
Studs (pins) pieces 606,876
2952160007200 Lifting equipment for finishing works machine-
hours
0,565
76 IzF14B
Sound insulation layer executed with
mineral wool boards Tehnoruf H35
thickness 100 mm
m² 47,60
7134050013240 Thermal insulator man-
hours
8,758
2682162611371
00
Mineral wool boards Tehnoruf H35 thickness 100
mm
m² 48,552
77 CK18C
Installation of aluminium frame
(Aluminium frame)
m 92,40
7422010060100 Carpenter (joiner) man-
hours
27,628
2743123549025 Aluminium frame m 97,02
2651122100402 Metallurgical cement with additives M 30, bags
S1500
kg 2,31
1421102200496 Sorted unwashed river and lake sand 0.0–1.0 mm m³ 0,092
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 554,40
78 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m / aluminium composite panel
(ACP) interior
m² 42,00
7214240021810 Construction locksmith (metal fitter) man-
hours
45,885
2732103646070
1
Corrugated sheet aluminium composite panel
(ACP)
m² 46,62
2874125886734 POP (blind) rivets pieces 147,00
2874115893397 Tornado bolt K 6/20 OL50 piece
Стр. 24–26
itter) man-
hours
45,885
2732103646070
1
Corrugated sheet aluminium composite panel
(ACP)
m² 46,62
2874125886734 POP (blind) rivets pieces 147,00
2874115893397 Tornado bolt K 6/20 OL50 pieces 117,60
2461117308504 Cartridges for TORNADO bolt gun pieces 117,60
2922140007000 Crane machine-
hours
2,415
Total Node 1
8.3. Node 2
1 2 3 4 5
79 IzF53A
Manual execution of floor substrate with
thermal insulation layer made of extruded
polystyrene boards XPS – 50 mm
Small materials (metal bars D = 6–8 mm, length
400 mm) = 1,015
m² 155,90
7134050013250 Insulator man-
hours
12,55
9310060019922 Service worker man-
hours
8,964
2670112204002
50
Extruded polystyrene boards XPS – 50 mm m² 161,403
2922140006702 Window crane machine-
hours
0,717
80 IzF01B
Priming of surfaces for the application of
diffusion layer, vapor barrier, thermal
insulation or waterproofing on horizontal,
inclined or vertical surfaces, with
fillerized bitumen suspension (Subif) in
one layer (BITUMEN-POLYMER
PRIMER TECHNONICOL NO. 01)
m² 107,80
7134030012200 Waterproofing installer man-
hours
4,959
2413317346011 BITUMEN-POLYMER PRIMER
TECHNONICOL NO. 01
kg 32,34
4100116202818 Water for mortars and concrete m³ 0,108
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
0,037
81 RpCE09A
Additional separation layers, forming part
of the waterproofing system, executed
with bituminous felt type CA 300, single
laid over waterproofing or capillary break
layers on horizontal or inclined surfaces
with slope up to 7% (Profiled membrane
PLANTER Standard)
Small materials = 1,010
m² 155,90
7134030012200 Waterproofing installer man-
hours
12,55
2682122600746
2
Profiled membrane PLANTER Standard m² 176,354
2922140006702 Window crane machine-
hours
2,689
82 CI21B
Cladding of walls with ceramic granite
tiles: dimensions up to 600 × 600 mm
Small materials (rags, disc) = 1,010
m² 15,40
9310060019930 Worker man-
hours
38,962
2670112202051 Ceramic granite tiles m² 15,865
2462106110557 Acrylic or latex adhesive kg 93,324
2430226100000
1
Grout kg 6,066
1 2 3 4 5
4100126202818 Water m³ 0,047
2952160007200 Lifting equipment for finishing works machine-
hours
0,556
2952270003820 Mobile electric mixer machine-
hours
0,269
2952270003205 Universal stone cutting machine machine-
hours
0,808
83 CE25B
Additional sealing along the perimeter, at
penetrations or joints with expanded
polymer profiles (Waterproofing tape
Sika SealTape-S 120 mm)
Small materials (adhesive, thinner) = 1,050
m 108,00
7134030012200 Waterproofing installer man-
hours
18,63
9310060019920 Worker servicing ST man-
hours
6,21
2812106306022 Waterproofing tape Sika Seal Tape-S 120 mm m 124,74
84 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m
Стр. 26–27
22 Waterproofing tape Sika Seal Tape-S 120 mm m 124,74
84 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m / aluminium composite panel
(ACP) exterior
m² 29,20
7214240021810 Construction locksmith (metal fitter) man-
hours
31,901
2732103646070
1
Corrugated sheet aluminium composite panel
(ACP)
m² 32,412
2874125886734 POP (blind) rivets pieces 102,20
2874115893397 Tornado bolt K 6/20 OL50 pieces 81,76
2461117308504 Cartridges for TORNADO bolt gun pieces 81,76
2922140007000 Crane machine-
hours
1,679
Total Node 2
8.4. Parapet at staircase B-2,3
85 CH08A
apl
Metal railings at interior staircase
parapets
m 156,10
7129200011200 Finisher MP man-
hours
98,733
2812106305700 Frame made of U-type profiles for staircase
railings
m 163,905
86 CM04D
Laminated glass (Triplex), delivered to
custom dimensions, installed on metal
joinery or on staircase parapets, etc., with
metal glazing beads
m² 140,70
7135010011440 Glazier man-
hours
121,354
9310060019900 Unskilled worker man-
hours
24,271
2611112500400 Tempered laminated glass (Triplex) m² 154,77
1 2 3 4 5
2952160007200 Lifting equipment for finishing works machine-
hours
3,236
87 CD07A1
Walls made of corrugated galvanized
sheet panels fixed by shooting onto metal
framework, installed at a height greater
than 6 m / aluminium composite panel
(ACP) interior
m² 117,30
7214240021810 Construction locksmith (metal fitter) man-
hours
128,15
2732103646070
1
Corrugated sheet aluminium composite panel
(ACP)
m² 130,203
2874125886734 POP (blind) rivets pieces 410,55
2874115893397 Tornado bolt K 6/20 OL50 pieces 328,44
2461117308504 Cartridges for TORNADO bolt gun pieces 328,44
2922140007000 Crane machine-
hours
6,745
Total Parapet at staircase
B-2,3
Total Exterior finishing
9. Cladding of the elevator shaft (2 pieces)
88 CD07B1
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height greater than 6
m (AKL-FR panel)
m² 16,10
7214240021810 Construction locksmith (metal fitter) man-
hours
19,441
2732103646070
16
Corrugated sheet aluminium composite panel
(ACP)
m² 17,871
2874125886734 POP (blind) rivets pieces 56,35
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 45,08
2922140007000 Crane machine-
hours
0,926
89 CD07B1
Walls made of corrugated galvanized
sheet panels fixed with self-tapping
screws, installed at a height greater than 6
m (Enclosure of the elevator shaft with
tempered glass “Spider Glass System”)
m² 30,24
7214240021810 Construction locksmith (metal fitter) man-
hours
36,515
2732104560701 Enclosure with tempered glass “Spider Glass
System”
m² 33,566
2874125886734 POP (blind) rivets pieces 105,84
2874115833878 Self-tap
Стр. 27–29
on locksmith (metal fitter) man-
hours
36,515
2732104560701 Enclosure with tempered glass “Spider Glass
System”
m² 33,566
2874125886734 POP (blind) rivets pieces 105,84
2874115833878 Self-tapping screws 6.3 × 22 mm pieces 84,672
2922140007000 Crane machine-
hours
1,739
90 CK33C
Spider fittings for glass fastening
pieces 24,00
1 2 3 4 5
9310060019920 Worker servicing ST man-
hours
2,208
7422010060100 Carpenter (joiner) man-
hours
66,792
2863146310237
1
Spider fittings pieces 24,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 144,00
Total Cladding of the
elevator shaft (2 pieces)
10. Canopies
10.1. Canopy C 2-1
91 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete
kg 4 274,50
7214240021810 Construction locksmith (metal fitter) man-
hours
933,978
9310060019920 Worker servicing ST man-
hours
49,157
7212030022700 Welder man-
hours
49,157
2775276309886 Metal fabrications embedded in concrete kg 4 274,50
2734113803207 Soft black wire, diameter 2 mm kg 42,745
2873155901200 Welding electrodes kg 21,372
4011106202741 Electrical energy kw 34,196
92 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 4,28
7141020013400 Industrial painter man-
hours
31,698
2430116100000 Chlorinated rubber enamel kg 33,384
2430226100814 Red lead primer G 355-6 kg 16,692
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 2,354
2320166200676 White spirit kg 8,346
1711317306661 Cleaning cotton kg 4,173
93 CL18A
Crossbeam, stainless steel pipe D20 × 4,
kg 235,30
7214240021810 Construction locksmith (metal fitter) man-
hours
51,413
9310060019920 Worker servicing ST man-
hours
2,706
7212030022700 Welder man-
hours
2,706
2775276309886
1
crossbeam, stainless steel pipe D20 × 4, L = 2.5 m kg 235,30
2734113803207 Soft black wire, diameter 2 mm kg 2,353
2873155901200 Welding electrodes kg 1,177
1 2 3 4 5
4011106202741 Electrical energy kw 1,882
94 CK35B
Connector wall – crossbeam
pieces 49,00
7422010060100 Carpenter (joiner) man-
hours
11,27
2874136313300
1
(chemical anchor pieces 49,00
95 CK35B
Connector crossbeam – pipe
pieces 49,00
7422010060100 Carpenter (joiner) man-
hours
11,27
2874136313300
21
Connector crossbeam – pipe pieces 49,00
96 CK33C
Double spider fitting
pieces 135,00
9310060019920 Worker servicing ST man-
hours
12,42
7422010060100 Carpenter (joiner) man-
hours
375,705
2863146310237
11
Double spider fitting pieces 135,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 810,00
97 CK33C
Single spider fitting
pieces 12,00
9310060019920 Worker servicing ST man-
hours
1
Стр. 29–30
ble spider fitting pieces 135,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 810,00
97 CK33C
Single spider fitting
pieces 12,00
9310060019920 Worker servicing ST man-
hours
1,104
7422010060100 Carpenter (joiner) man-
hours
33,396
2863146310237
12
Single spider fitting pieces 12,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 72,00
98 CM03E
Glass – laminated tempered glass (10 +
10)
m² 175,00
7135010011440 Glazier man-
hours
201,25
9310060019920 Worker servicing ST man-
hours
40,25
2611112500300
1
Glass – laminated tempered glass (10 + 10) m² 192,50
99 CE20A
Gutter systems type brass made of sheet
metal protected against corrosion
Small materials = 1,030
m 58,30
7213050013100 Tinsmith man-
hours
20,113
2710406311800 Prefabricated semi-round gutters type brass m 63,051
2875274000501 Gutter elbow pieces 12,01
2875276311231 Zinc-coated steel hooks for gutters pieces 84,069
2666122800555 End cap element pieces 12,01
2875274000050
1
Gutter connection elements pieces 6,005
2875274110101 Gutter-to-downpipe connection piece pieces 12,01
2874115837745 Screws pieces 600,49
2952160007200 Lifting equipment for finishing works machine-
hours
1,341
100 CE22A Downpipe systems type brass made of m 27,00
1 2 3 4 5
sheet metal protected against corrosion
Small materials = 1,020
7213050013100 Tinsmith man-
hours
10,867
2710406311726 Prefabricated round downpipe type brass m 28,917
2875274000502 Downpipe elbow pieces 13,77
2875274000503 End elbow pieces 6,885
2874115830000 Cleaning outlets pieces 6,885
2413217300010 Clamps pieces 13,77
2875274110001 Connection piece pieces 6,885
2875274000050
2
Downpipe connection elements pieces 6,885
2952160007200 Lifting equipment for finishing works machine-
hours
0,466
Total Canopy C 2-1
10.2. Canopy C 2-2
101 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete
kg 1 480,10
7214240021810 Construction locksmith (metal fitter) man-
hours
323,402
9310060019920 Worker servicing ST man-
hours
17,021
7212030022700 Welder man-
hours
17,021
2775276309886 Metal fabrications embedded in concrete kg 1 480,10
2734113803207 Soft black wire, diameter 2 mm kg 14,801
2873155901200 Welding electrodes kg 7,401
4011106202741 Electrical energy kw 11,841
102 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 1,48
7141020013400 Industrial painter man-
hours
10,961
2430116100000 Chlorinated rubber enamel kg 11,544
2430226100814 Red lead primer G 355-6 kg 5,772
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,814
2320166200676 White spirit kg 2,886
17113173
Стр. 30–32
enamel kg 11,544 2430226100814 Red lead primer G 355-6 kg 5,772 2430226109420 Thinner for anticorrosive varnishes D.006-1 NI 1708-61 A1 kg 0,814 2320166200676 White spirit kg 2,886 1711317306661 Cleaning cotton kg 1,443 103 CL18A Crossbeam, stainless steel pipe D20 × 4, kg 83,00 7214240021810 Construction locksmith (metal fitter) man- hours 18,136 9310060019920 Worker servicing ST man- hours 0,954 1 2 3 4 5 7212030022700 Welder man- hours 0,954 2775276309886 1 crossbeam, stainless steel pipe D20 × 4, L = 2.5 m kg 83,00 2734113803207 Soft black wire, diameter 2 mm kg 0,83 2873155901200 Welding electrodes kg 0,415 4011106202741 Electrical energy kw 0,664 104 CK35B Connector wall – crossbeam pieces 17,00 7422010060100 Carpenter (joiner) man- hours 3,91 2874136313300 1 (chemical anchor pieces 17,00 105 CK35B Connector crossbeam – pipe pieces 17,00 7422010060100 Carpenter (joiner) man- hours 3,91 2874136313300 21 Connector crossbeam – pipe pieces 17,00 106 CK33C Double spider fitting pieces 45,00 9310060019920 Worker servicing ST man- hours 4,14 7422010060100 Carpenter (joiner) man- hours 125,235 2863146310237 11 Double spider fitting pieces 45,00 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 270,00 107 CK33C Single spider fitting pieces 6,00 9310060019920 Worker servicing ST man- hours 0,552 7422010060100 Carpenter (joiner) man- hours 16,698 2863146310237 12 Single spider fitting pieces 6,00 2874115829126 Countersunk slotted screws 6 × 30 mm pieces 36,00 108 CM03E Glass – laminated tempered glass (10 + 10) m² 60,00 7135010011440 Glazier man- hours 69,00 9310060019920 Worker servicing ST man- hours 13,80 2611112500300 1 Glass – laminated tempered glass (10 + 10) m² 66,00 109 CE20A Gutter systems type brass made of sheet metal protected against corrosion Small materials = 1,030 m 20,00 7213050013100 Tinsmith man- hours 6,90 2710406311800 Prefabricated semi-round gutters type brass m 21,63 2875274000501 Gutter elbow pieces 4,12 2875276311231 Zinc-coated steel hooks for gutters pieces 28,84 2666122800555 End cap element pieces 4,12 2875274000050 1 Gutter connection elements pieces 2,06 1 2 3 4 5 2875274110101 Gutter-to-downpipe connection piece pieces 4,12 2874115837745 Screws pieces 206,00 2952160007200 Lifting equipment for finishing works machine- hours 0,46 110 CE22A Downpipe systems type brass made of sheet metal protected against corrosion Small materials = 1,020 m 10,80 7213050013100 Tinsmith man- hours 4,347 2710406311726 Prefabricated round downpipe type brass m 11,567 2875274000502 Downpipe elbow pieces 5,508 2875274000503 End elbow pieces 2,754 2874115830000 Cleaning outlets pieces 2,754 2413217300010 Clamps pieces 5,508 2875274110001 Connection piece pieces 2,754 2875274000050 2 Downpipe connection elements pieces 2,754 2952160007200 Lifting equip
Стр. 32–33
aning outlets pieces 2,754
2413217300010 Clamps pieces 5,508
2875274110001 Connection piece pieces 2,754
2875274000050
2
Downpipe connection elements pieces 2,754
2952160007200 Lifting equipment for finishing works machine-
hours
0,186
Total Canopy C 2-2
10.3. Canopy C 2-3
111 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete
kg 137,40
7214240021810 Construction locksmith (metal fitter) man-
hours
30,022
9310060019920 Worker servicing ST man-
hours
1,58
7212030022700 Welder man-
hours
1,58
2775276309886 Metal fabrications embedded in concrete kg 137,40
2734113803207 Soft black wire, diameter 2 mm kg 1,374
2873155901200 Welding electrodes kg 0,687
4011106202741 Electrical energy kw 1,099
112 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,14
7141020013400 Industrial painter man-
hours
1,037
2430116100000 Chlorinated rubber enamel kg 1,092
2430226100814 Red lead primer G 355-6 kg 0,546
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,077
2320166200676 White spirit kg 0,273
1711317306661 Cleaning cotton kg 0,137
113 CL18A Crossbeam, stainless steel pipe D20 × 4, kg 6,60
1 2 3 4 5
7214240021810 Construction locksmith (metal fitter) man-
hours
1,442
9310060019920 Worker servicing ST man-
hours
0,076
7212030022700 Welder man-
hours
0,076
2775276309886
1
crossbeam, stainless steel pipe D20 × 4, L = 2.5 m kg 6,60
2734113803207 Soft black wire, diameter 2 mm kg 0,066
2873155901200 Welding electrodes kg 0,033
4011106202741 Electrical energy kw 0,053
114 CK35B
Connector wall – crossbeam
pieces 2,00
7422010060100 Carpenter (joiner) man-
hours
0,46
2874136313300
1
(chemical anchor pieces 2,00
115 CK35B
Connector crossbeam – pipe
pieces 2,00
7422010060100 Carpenter (joiner) man-
hours
0,46
2874136313300
21
Connector crossbeam – pipe pieces 2,00
116 CK33C
Double spider fitting
pieces 2,00
9310060019920 Worker servicing ST man-
hours
0,184
7422010060100 Carpenter (joiner) man-
hours
5,566
2863146310237
11
Double spider fitting pieces 2,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 12,00
117 CK33C
Single spider fitting
pieces 4,00
9310060019920 Worker servicing ST man-
hours
0,368
7422010060100 Carpenter (joiner) man-
hours
11,132
2863146310237
12
Single spider fitting pieces 4,00
2874115829126 Countersunk slotted screws 6 × 30 mm pieces 24,00
118 CM03E
Glass – laminated tempered glass (10 +
10)
m² 5,00
7135010011440 Glazier man-
hours
5,75
9310060019920 Worker servicing ST man-
hours
1,15
2611112500300
1
Glass – laminated tempered glass (10 + 10) m² 5,50
119
Стр. 33–34
d glass (10 +
10)
m² 5,00
7135010011440 Glazier man-
hours
5,75
9310060019920 Worker servicing ST man-
hours
1,15
2611112500300
1
Glass – laminated tempered glass (10 + 10) m² 5,50
119 CE20A
Gutter systems type brass made of sheet
metal protected against corrosion
Small materials = 1,030
m 2,50
7213050013100 Tinsmith man-
hours
0,862
1 2 3 4 5
2710406311800 Prefabricated semi-round gutters type brass m 2,704
2875274000501 Gutter elbow pieces 0,515
2875276311231 Zinc-coated steel hooks for gutters pieces 3,605
2666122800555 End cap element pieces 0,515
2875274000050
1
Gutter connection elements pieces 0,258
2875274110101 Gutter-to-downpipe connection piece pieces 0,515
2874115837745 Screws pieces 25,75
2952160007200 Lifting equipment for finishing works machine-
hours
0,057
120 CE22A
Downpipe systems type brass made of
sheet metal protected against corrosion
Small materials = 1,020
m 5,40
7213050013100 Tinsmith man-
hours
2,173
2710406311726 Prefabricated round downpipe type brass m 5,783
2875274000502 Downpipe elbow pieces 2,754
2875274000503 End elbow pieces 1,377
2874115830000 Cleaning outlets pieces 1,377
2413217300010 Clamps pieces 2,754
2875274110001 Connection piece pieces 1,377
2875274000050
2
Downpipe connection elements pieces 1,377
2952160007200 Lifting equipment for finishing works machine-
hours
0,093
Total Canopy C 2-3
Total Canopies
Total
Social fund
Total
Transportation of materials
Storage expenses
Direct expenses
Overhead expenses
Total
Estimated profit
Total estimate:
Including wages
Subsemnata, Poleacova Ana, tradu cător
autorizat, (limba Englez ă), certific
exactitatea traducerii cu textul
înscrisului, care a fost vizată de mine şi
port răspundere personală pentru
corectitudinea traducerii actului.
Undersigned, Poleacova Ana, sworn translator,
(English language), certify the authenticity of
the translation which corresponds to the text
of the authentic document, which was
confirmed by me and I do take personal
responsibility for the truthfulness of the
translation.
26.02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,
Authorization AT No. 461 of 10.02.2014, AT No. 500 of 21.07.2014,
English, French, Romanian, Russian, Translator
Стр. 34
02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,
Authorization AT No. 461 of 10.02.2014, AT No. 500 of 21.07.2014,
English, French, Romanian, Russian, Translator
Предпросмотр носит справочный характер. Юридически значим только официальный оригинал в источнике.