eng4 2-2-1 bloc 1b (cba).rtf f1b.pdf
Стр. 1–2
Translation from Romanian and Russian into English
2026-403
Reconstruction of the terminal
building of “Eugen Doga”
International Airport - Chisinau
(cadastral no. 0100120.236.01),
including partial replanning of
internal spaces and building
extension
Form No. 1B
(name of the facility) WinEstimate
Cost Estimate-Offer No. 2-2-1
BLOCK 1B Phase 3
Reinforced Concrete Structures (RC section)
(name of works)
Coefficient for basic wages = 1,150
Coefficient for cost of machine operation = 1,150
No. Norm
symbol and
resource
code
Description of works
Unit of
measure
(U.M.)
Quantity
according to the
design data
1 2 3 4 5
1. Demolition Works / Removal of the
existing external staircase on the airside,
on the axes “R29–R30” × “X–EA”
1 RCsB28G
Demolition of old reinforced concrete by
mechanical means / dismantling of
reinforced-concrete foundations
m³ 9,90
7123010010200 Concrete worker man-
hours
45,54
9310060019920 Worker servicing ST man-
hours
23,339
4100116202818 Water for mortars and concrete m³ 0,495
2912340002509 Mobile low-pressure air compressor, capacity
4.0–5.9 m³/min
machine-
hours
3,985
2952270003380 Pneumatic hammer 8–15 kg machine-
hours
3,985
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
2,277
2 RCsB28G
Demolition of old reinforced concrete by
mechanical means / dismantling of
reinforced-concrete staircases (landings
and flights)
m³ 15,93
7123010010200 Concrete worker man- 73,278
1 2 3 4 5
hours
9310060019920 Worker servicing ST man-
hours
37,555
4100116202818 Water for mortars and concrete m³ 0,796
2912340002509 Mobile low-pressure air compressor, capacity
4.0–5.9 m³/min
machine-
hours
6,412
2952270003380 Pneumatic hammer 8–15 kg machine-
hours
6,412
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
3,664
3 RCsB28G
Demolition of old reinforced concrete by
mechanical means / dismantling of
reinforced-concrete floors
m³ 15,93
7123010010200 Concrete worker man-
hours
73,278
9310060019920 Worker servicing ST man-
hours
37,555
4100116202818 Water for mortars and concrete m³ 0,796
2912340002509 Mobile low-pressure air compressor, capacity
4.0–5.9 m³/min
machine-
hours
6,412
2952270003380 Pneumatic hammer 8–15 kg machine-
hours
6,412
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
3,664
4 TsC03G1
Mechanical excavation with excavator
0.40–0.70 m³, with internal combustion
engine and hydraulic control, in soil with
natural moisture, unloading into vehicles,
terrain category III / loading
100 m³ 0,42
2952260003501 Crawler excavator, single-bucket, with internal
combustion engine, 0.40–0.70 m³
machine-
hours
1,256
5 TsI51B5
Transportation of con
Стр. 2–3
rrain category III / loading
100 m³ 0,42
2952260003501 Crawler excavator, single-bucket, with internal
combustion engine, 0.40–0.70 m³
machine-
hours
1,256
5 TsI51B5
Transportation of construction debris by
10 tonne dump truck over a distance of
15 kilometres
tonne 100,30
3410540000007 Dump truck, 10 tonnes machine-
hours
8,766
Total Demolition Works /
Removal of the existing
external staircase on the
airside, on the axes “R29–
R30” × “X–EA”
2. Foundations
2.1. Pile Pm-1 (8 pieces)
6 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
m³ 25,60
1 2 3 4 5
12 m. Note: Concrete C20/25,
Reinforcement cage – 1,470.4 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
9310060019930 Worker man-
hours
336,499
2663102100002
0
Concrete C20/25 m³ 30,06
2873155901202 Electrodes E42A, diameter 6 mm kg 2,637
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 0,633
2710602000090 Reinforcement cages kg 1 470,40
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
94,208
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
6,771
2952270003100 Deep vibrator machine-
hours
20,902
Total Pile Pm-1 (8
pieces)
2.2. Pile Pm-2 (23 pieces)
7 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 3,873.2 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 64,86
9310060019930 Worker man-
hours
852,552
2663102100002
0
Concrete C20/25 m³ 76,159
2873155901202 Electrodes E42A, diameter 6 mm kg 6,681
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 1,603
2710602000090 Reinforcement cages kg 3 873,20
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
238,685
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
17,155
2952270003100 Deep vibrator machine-
hours
52,958
Total Pile Pm-2 (23
pieces)
2.3. Pile Pm-3 (10 pieces)
Стр. 3–5
nal welding
current 250–400 A
machine-
hours
17,155
2952270003100 Deep vibrator machine-
hours
52,958
Total Pile Pm-2 (23
pieces)
2.3. Pile Pm-3 (10 pieces)
1 2 3 4 5
8 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 1,330.0 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 22,00
9310060019930 Worker man-
hours
289,179
2663102100002
0
Concrete C20/25 m³ 25,832
2873155901202 Electrodes E42A, diameter 6 mm kg 2,266
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 0,544
2710602000090 Reinforcement cages kg 1 330,00
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
80,96
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
5,819
2952270003100 Deep vibrator machine-
hours
17,963
Total Pile Pm-3 (10
pieces)
2.4. Pile Pm-4 (20 pieces)
9 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 2,816.0 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 50,20
9310060019930 Worker man-
hours
659,854
2663102100002
0
Concrete C20/25 m³ 58,945
2873155901202 Electrodes E42A, diameter 6 mm kg 5,171
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 1,241
2710602000090 Reinforcement cages kg 2 816,00
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
184,736
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
13,278
2952270003100 Deep vibrator machine-
hours
40,988
1 2 3 4 5
Total Pile Pm-4 (20
pieces)
2.5. Pile Pm-5 (5 pieces)
10 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 381.0 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 6,70
9310060019930 Worker man-
hours
88,068
2663102100002
0
Concrete C20/25 m³ 7,867
2873155901202 Electrodes E42A, diameter 6 mm kg 0,69
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), out
Стр. 5–6
02100002
0
Concrete C20/25 m³ 7,867
2873155901202 Electrodes E42A, diameter 6 mm kg 0,69
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 0,166
2710602000090 Reinforcement cages kg 381,00
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
24,656
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
1,772
2952270003100 Deep vibrator machine-
hours
5,471
Total Pile Pm-5 (5 pieces)
2.6. Pile Pm-6 (1 piece)
11 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 88.0 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 1,55
9310060019930 Worker man-
hours
20,374
2663102100002
0
Concrete C20/25 m³ 1,82
2873155901202 Electrodes E42A, diameter 6 mm kg 0,16
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 0,038
2710602000090 Reinforcement cages kg 88,00
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
5,704
2940420002445 Welding unit with diesel engine, nominal welding machine- 0,41
1 2 3 4 5
current 250–400 A hours
2952270003100 Deep vibrator machine-
hours
1,266
Total Pile Pm-6 (1 piece)
2.7. Pile Pm-7 (1 piece)
12 CQ23A
Execution of bored reinforced concrete
piles in stable soils of Group II using an
SBU-type installation, with a diameter up
to 500–600 mm, concreting by the
Tremie Pipe Method, with a length up to
12 m. Note: Concrete C20/25,
Reinforcement cage – 120.2 kg
Small materials (drilling tool, metal inventory
device, water, etc.) = 1,030
m³ 2,22
9310060019930 Worker man-
hours
29,181
2663102100002
0
Concrete C20/25 m³ 2,607
2873155901202 Electrodes E42A, diameter 6 mm kg 0,229
2722103305015
Reusable steel tremie pipe set (loading hopper,
lifting section, connecting flange), outer diameter
250–325 mm
m 0,055
2710602000090 Reinforcement cages kg 120,20
2952270003629 Pile drilling and casting installation coupled to a
crawler crane, 25 ton-force (tf)
machine-
hours
8,17
2940420002445 Welding unit with diesel engine, nominal welding
current 250–400 A
machine-
hours
0,587
2952270003100 Deep vibrator machine-
hours
1,813
Total Pile Pm-7 (1 piece)
2.8. Monolithic raft slabs
13 CA02C
Plain concrete cast for leveling layers,
slopes and screeds at heights up to 35 m
inclusive, prepared by concrete batching
plant or ready-mix concrete, placed by
conventional
Стр. 6–7
bs 13 CA02C Plain concrete cast for leveling layers, slopes and screeds at heights up to 35 m inclusive, prepared by concrete batching plant or ready-mix concrete, placed by conventional means, class C8/10 Small materials (softwood planks) = 1,010 m³ 33,90 7123010010200 Concrete worker man- hours 150,092 9310060019920 Worker servicing ST man- hours 25,34 2663102100000 150 Concrete C8/10 m³ 35,095 4100116202818 Water for mortars and concrete m³ 3,424 2922140007000 Crane machine- hours 9,746 2952270003000 Surface vibrator machine- hours 15,594 14 CA03G Placing of concrete in reinforced m³ 130,60 1 2 3 4 5 structures of foundations, plinths, retaining walls and walls below zero level, concrete prepared at the ready-mix concrete plant or ready-mix concrete in accordance with CA01, placed by conventional means, reinforced concrete class C20/25 Small materials (softwood planks, nails, staples) = 1,015 7123010010200 Concrete worker man- hours 600,76 9310060019920 Worker servicing ST man- hours 60,076 2663102100000 20 Concrete C20/25 m³ 135,873 4100116202818 Water for mortars and concrete m³ 13,256 2952270003100 Deep vibrator machine- hours 90,114 3410520006752 Truck crane, 6–10 tf machine- hours 37,547 15 CB02A Formwork from reusable panels with sheathing of short and very short softwood boards for placing concrete in pads, cup foundations and equipment foundations, including fastenings m² 427,00 9310060019920 Worker servicing ST man- hours 73,657 7124010010700 1 Carpenter man- hours 515,602 2874125881241 Standard washers M10 kg 2,135 2874115841033 Standard square nuts M10 pieces 128,10 2874115825003 Standard square bolts M10 × 140 mm pieces 128,10 2875276311528 Steel construction staples kg 12,81 2734113803233 Soft black wire, diameter 2.5 mm kg 21,35 2873145887000 Conical head nails, type A kg 34,16 2020212928347 Formwork panel type P, beech plywood 15 mm m² 42,70 2010102903495 Softwood boards m³ 1,494 2010102900900 Softwood round timber m³ 0,213 2320187315789 Formwork release agent (Decofrol) kg 51,24 16 CC01E Rebar steel class OB 37, placed in strip foundations and raft beams, fabricated in centralized workshop, bar diameter up to 8 mm inclusive kg 780,20 7123020011140 Rebar worker man- hours 57,423 9310060019920 Worker servicing ST man- hours 2,692 2710602100000 Rebar steel OB 37 ≤ 8 mm kg 799,705 2010237318750 Spacers pieces 117,03 2734113803881 Soft black steel wire, diameter 1 mm kg 7,802 17 CC01F1 Rebar steel class PC 52, placed in strip kg 10 439,80
Стр. 7–9
ebar steel OB 37 ≤ 8 mm kg 799,705
2010237318750 Spacers pieces 117,03
2734113803881 Soft black steel wire, diameter 1 mm kg 7,802
17 CC01F1 Rebar steel class PC 52, placed in strip kg 10 439,80
1 2 3 4 5
foundations and raft beams, fabricated in
site workshop, bar diameter over 8 mm
7123020011140 Rebar worker man-
hours
648,312
9310060019920 Worker servicing ST man-
hours
36,017
2710602200000 Rebar steel PC 52 > 8 mm kg 10 700,795
2010237318750 Spacers pieces 1 565,97
2734113803881 Soft black steel wire, diameter 1 mm kg 104,398
18 CL57A
Installation and fixing of embedded parts
in monolithic reinforced concrete, weight
up to 4 kg / P-14, P-2
Small materials and installation materials (grease,
rags, kerosene, etc.) = 1,010
kg 189,70
7136080025001 Installer man-
hours
45,813
2811236309900 Metal fabrications kg 199,261
2412126100010 Red lead (minium) kg 3,832
2873155900311 Electrodes E-42A, diameter 4 mm kg 1,916
3110500002401 Welding machine, 28–35 kW machine-
hours
17,452
2922140006702 Window crane machine-
hours
2,182
Total Monolithic raft
slabs
2.9. Soil transportation
19 TsC03F1
Mechanical excavation with excavator
0.40–0.70 m³, unloading into vehicles,
soil with natural moisture, category II
(loading of soil from piles)
100 m³ 1,73
2952260003501 Crawler excavator, single-bucket, with internal
combustion engine, 0.40–0.70 m³
machine-
hours
4,476
20 TsI51B5
Transportation of soil by 10 tonne dump
truck over a distance of 15 kilometres
tonne 295,00
3410540000007 Dump truck, 10 tonnes machine-
hours
25,783
Total Soil transportation
Total Foundations
3. Columns
3.1. Monolithic columns Cm-1 (12 pieces)
21 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
m³ 18,00
1 2 3 4 5
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
7123010010200 Concrete worker man-
hours
90,666
9310060019920 Worker servicing ST man-
hours
49,887
2663102100000
20
Concrete C20/25 m³ 18,819
4100116202818 Water for mortars and concrete m³ 2,203
2952270003101 Poker vibrator machine-
hours
12,42
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
3,105
22 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 156,00
9310060019920 Worker servicing ST man-
hours
44,85
7124010010700 Carpenter man-
hours
179,40
2874125881241 Standard washers M10 kg 1,248
2874115841033 Standard square nuts M10 pieces 7,80
2874115825003 Standard square bolts M10 × 140 mm pieces 7,80
2875276311528 Steel con
Стр. 9–10
ours
179,40
2874125881241 Standard washers M10 kg 1,248
2874115841033 Standard square nuts M10 pieces 7,80
2874115825003 Standard square bolts M10 × 140 mm pieces 7,80
2875276311528 Steel construction staples kg 7,80
2873145887000 Conical head nails, type A kg 6,24
2030122928385 Formwork panel with 15 mm plywood m² 23,40
2010102904340 Softwood planks m³ 0,156
2010102903495 Softwood boards m³ 0,234
2320187315789 Formwork release agent (Decofrol) kg 18,72
3410520006752 Truck crane, 6–10 tf machine-
hours
3,588
23 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 2 113,70
7123020011140 Rebar worker man-
hours
209,045
9310060019920 Worker servicing ST man-
hours
72,923
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 2 166,542
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 21,137
2010237318750 Spacers pieces 317,055
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
85,076
24 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
kg 72,00
1 2 3 4 5
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
7214240021810 Construction locksmith (metal fitter) man-
hours
15,732
9310060019920 Worker servicing ST man-
hours
0,828
7212030022700 Welder man-
hours
0,828
2775276309886 Metal fabrications embedded in concrete kg 72,00
2734113803207 Soft black wire, diameter 2 mm kg 0,72
2873155901200 Welding electrodes kg 0,36
4011106202741 Electrical energy kw 0,576
1010126200341 Forge coal (hard coal) kg 1,08
25 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,072
7141020013400 Industrial painter man-
hours
0,533
2430116100000 Chlorinated rubber enamel kg 0,562
2430226100814 Red lead primer G 355-6 kg 0,281
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,04
2320166200676 White spirit kg 0,14
1711317306661 Cleaning cotton kg 0,07
26 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 144,00
7212030022700 Welder man-
hours
91,08
2873155900800 Welding electrodes kg 86,40
4011106202741 Electrical energy kw 158,40
Total Monolithic columns
Cm-1 (12 pieces)
3.2. Monolithic columns Cm-2 (3 pieces)
27 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slab
Стр. 10–11
x concrete delivered from the ready-mix concrete plant and placed by conventional means in columns, beams, ribs, slabs, landings, staircases, retaining walls, reinforced concrete pads, floor slabs, diaphragms, stair flights, etc., in existing buildings / C20/25 (M350) Small materials (boards, wire, nails, etc.) = 1,020 m³ 4,50 1 2 3 4 5 7123010010200 Concrete worker man- hours 22,666 9310060019920 Worker servicing ST man- hours 12,472 2663102100000 20 Concrete C20/25 m³ 4,705 4100116202818 Water for mortars and concrete m³ 0,551 2952270003101 Poker vibrator machine- hours 3,105 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 0,776 28 CB03F Formwork from reusable plywood panels, 15 mm thick, for concreting columns in structures up to 20 m in height inclusive, excluding fastenings m² 39,30 9310060019920 Worker servicing ST man- hours 11,299 7124010010700 Carpenter man- hours 45,195 2874125881241 Standard washers M10 kg 0,314 2874115841033 Standard square nuts M10 pieces 1,965 2874115825003 Standard square bolts M10 × 140 mm pieces 1,965 2875276311528 Steel construction staples kg 1,965 2873145887000 Conical head nails, type A kg 1,572 2030122928385 Formwork panel with 15 mm plywood m² 5,895 2010102904340 Softwood planks m³ 0,039 2010102903495 Softwood boards m³ 0,059 2320187315789 Formwork release agent (Decofrol) kg 4,716 3410520006752 Truck crane, 6–10 tf machine- hours 0,904 29 RCsD02D 1 Rebar steel PC 52, diameter over 8 mm, fabricated in a site workshop for foundations and raft beams, installed in existing structural elements. For flat slabs, columns, beams, etc. kg 613,56 7123020011140 Rebar worker man- hours 60,681 9310060019920 Worker servicing ST man- hours 21,168 2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 628,899 2746133803142 Ordinary soft wire, diameter 1.25 mm kg 6,136 2010237318750 Spacers pieces 92,034 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 24,696 30 CL18A Various metal products made of rolled profiles, sheet steel, checkered and reinforcing steel, and pipes for supports or coverings, fully or partially embedded in concrete / 100 × 100 × 20 State Standard (GOST) 103-76 kg 27,60 7214240021810 Construction locksmith (metal fitter) man- hours 6,031
Стр. 11–13
for supports
or coverings, fully or partially embedded
in concrete / 100 × 100 × 20 State
Standard (GOST) 103-76
kg 27,60
7214240021810 Construction locksmith (metal fitter) man-
hours
6,031
1 2 3 4 5
9310060019920 Worker servicing ST man-
hours
0,317
7212030022700 Welder man-
hours
0,317
2775276309886 Metal fabrications embedded in concrete kg 27,60
2734113803207 Soft black wire, diameter 2 mm kg 0,276
2873155901200 Welding electrodes kg 0,138
4011106202741 Electrical energy kw 0,221
1010126200341 Forge coal (hard coal) kg 0,414
31 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,028
7141020013400 Industrial painter man-
hours
0,207
2430116100000 Chlorinated rubber enamel kg 0,218
2430226100814 Red lead primer G 355-6 kg 0,109
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,015
2320166200676 White spirit kg 0,055
1711317306661 Cleaning cotton kg 0,027
32 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 36,00
7212030022700 Welder man-
hours
22,77
2873155900800 Welding electrodes kg 21,60
4011106202741 Electrical energy kw 39,60
Total Monolithic columns
Cm-2 (3 pieces)
3.3. Monolithic columns Cm-2a (2 pieces)
33 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 3,00
7123010010200 Concrete worker man-
hours
15,111
9310060019920 Worker servicing ST man-
hours
8,315
2663102100000
20
Concrete C20/25 m³ 3,136
4100116202818 Water for mortars and concrete m³ 0,367
1 2 3 4 5
2952270003101 Poker vibrator machine-
hours
2,07
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,517
34 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 26,20
9310060019920 Worker servicing ST man-
hours
7,532
7124010010700 Carpenter man-
hours
30,13
2874125881241 Standard washers M10 kg 0,21
2874115841033 Standard square nuts M10 pieces 1,31
2874115825003 Standard square bolts M10 × 140 mm pieces 1,31
2875276311528 Steel construction staples kg 1,31
2873145887000 Conical head nails, type A kg 1,048
2030122928385 Formwork panel with 15 mm plywood m² 3,93
2010102904340 Softwood planks m³ 0,026
2010102903495 Softwood boards m³ 0,039
2320187315789 Formwork release agent (Decofrol) kg 3,144
3410520006752 Truck crane, 6–10 tf machine
Стр. 13–14
wood m² 3,93
2010102904340 Softwood planks m³ 0,026
2010102903495 Softwood boards m³ 0,039
2320187315789 Formwork release agent (Decofrol) kg 3,144
3410520006752 Truck crane, 6–10 tf machine-
hours
0,603
35 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 420,00
7123020011140 Rebar worker man-
hours
41,538
9310060019920 Worker servicing ST man-
hours
14,49
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 430,50
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 4,20
2010237318750 Spacers pieces 63,00
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
16,905
36 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 18,40
7214240021810 Construction locksmith (metal fitter) man-
hours
4,02
9310060019920 Worker servicing ST man-
hours
0,212
7212030022700 Welder man-
hours
0,212
2775276309886 Metal fabrications embedded in concrete kg 18,40
2734113803207 Soft black wire, diameter 2 mm kg 0,184
2873155901200 Welding electrodes kg 0,092
1 2 3 4 5
4011106202741 Electrical energy kw 0,147
1010126200341 Forge coal (hard coal) kg 0,276
37 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,018
7141020013400 Industrial painter man-
hours
0,133
2430116100000 Chlorinated rubber enamel kg 0,14
2430226100814 Red lead primer G 355-6 kg 0,07
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,01
2320166200676 White spirit kg 0,035
1711317306661 Cleaning cotton kg 0,018
38 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 24,00
7212030022700 Welder man-
hours
15,18
2873155900800 Welding electrodes kg 14,40
4011106202741 Electrical energy kw 26,40
Total Monolithic columns
Cm-2a (2 pieces)
3.4. Monolithic columns Cm-3 (3 pieces)
39 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 4,38
7123010010200 Concrete worker man-
hours
22,062
9310060019920 Worker servicing ST man-
hours
12,139
2663102100000
20
Concrete C20/25 m³ 4,579
4100116202818 Water for mortars and concre
Стр. 14–15
4,38 7123010010200 Concrete worker man- hours 22,062 9310060019920 Worker servicing ST man- hours 12,139 2663102100000 20 Concrete C20/25 m³ 4,579 4100116202818 Water for mortars and concrete m³ 0,536 2952270003101 Poker vibrator machine- hours 3,022 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 0,756 40 CB03F Formwork from reusable plywood panels, 15 mm thick, for concreting columns in m² 39,30 1 2 3 4 5 structures up to 20 m in height inclusive, excluding fastenings 9310060019920 Worker servicing ST man- hours 11,299 7124010010700 Carpenter man- hours 45,195 2874125881241 Standard washers M10 kg 0,314 2874115841033 Standard square nuts M10 pieces 1,965 2874115825003 Standard square bolts M10 × 140 mm pieces 1,965 2875276311528 Steel construction staples kg 1,965 2873145887000 Conical head nails, type A kg 1,572 2030122928385 Formwork panel with 15 mm plywood m² 5,895 2010102904340 Softwood planks m³ 0,039 2010102903495 Softwood boards m³ 0,059 2320187315789 Formwork release agent (Decofrol) kg 4,716 3410520006752 Truck crane, 6–10 tf machine- hours 0,904 41 RCsD02D 1 Rebar steel PC 52, diameter over 8 mm, fabricated in a site workshop for foundations and raft beams, installed in existing structural elements. For flat slabs, columns, beams, etc. kg 756,00 7123020011140 Rebar worker man- hours 74,768 9310060019920 Worker servicing ST man- hours 26,082 2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 774,90 2746133803142 Ordinary soft wire, diameter 1.25 mm kg 7,56 2010237318750 Spacers pieces 113,40 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 30,429 42 CL18A Various metal products made of rolled profiles, sheet steel, checkered and reinforcing steel, and pipes for supports or coverings, fully or partially embedded in concrete / 80×80×15 State Standard (GOST) 103-76 kg 37,80 7214240021810 Construction locksmith (metal fitter) man- hours 8,259 9310060019920 Worker servicing ST man- hours 0,435 7212030022700 Welder man- hours 0,435 2775276309886 Metal fabrications embedded in concrete kg 37,80 2734113803207 Soft black wire, diameter 2 mm kg 0,378 2873155901200 Welding electrodes kg 0,189 4011106202741 Electrical energy kw 0,302 1010126200341 Forge coal (hard coal) kg 0,567 43 IzD10A Anticorrosion painting by brush of metal products and structures, one coat of anticorrosion primer based on red lead tonne 0,038
Стр. 15–17
0,302
1010126200341 Forge coal (hard coal) kg 0,567
43 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
tonne 0,038
1 2 3 4 5
and two coats of chlorinated rubber
enamel.
7141020013400 Industrial painter man-
hours
0,281
2430116100000 Chlorinated rubber enamel kg 0,296
2430226100814 Red lead primer G 355-6 kg 0,148
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,021
2320166200676 White spirit kg 0,074
1711317306661 Cleaning cotton kg 0,037
44 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 12,00
7212030022700 Welder man-
hours
7,59
2873155900800 Welding electrodes kg 7,20
4011106202741 Electrical energy kw 13,20
Total Monolithic columns
Cm-3 (3 pieces)
3.5. Monolithic columns Cm-4, Cm-4a (1
piece)
45 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 3,44
7123010010200 Concrete worker man-
hours
17,327
9310060019920 Worker servicing ST man-
hours
9,534
2663102100000
20
Concrete C20/25 m³ 3,597
4100116202818 Water for mortars and concrete m³ 0,421
2952270003101 Poker vibrator machine-
hours
2,374
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,593
46 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 30,40
9310060019920 Worker servicing ST man-
hours
8,74
1 2 3 4 5
7124010010700 Carpenter man-
hours
34,96
2874125881241 Standard washers M10 kg 0,243
2874115841033 Standard square nuts M10 pieces 1,52
2874115825003 Standard square bolts M10 × 140 mm pieces 1,52
2875276311528 Steel construction staples kg 1,52
2873145887000 Conical head nails, type A kg 1,216
2030122928385 Formwork panel with 15 mm plywood m² 4,56
2010102904340 Softwood planks m³ 0,03
2010102903495 Softwood boards m³ 0,046
2320187315789 Formwork release agent (Decofrol) kg 3,648
3410520006752 Truck crane, 6–10 tf machine-
hours
0,699
47 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 489,92
7123020011140 Rebar worker man-
hours
48,453
9310060019920 Worker servicing ST man-
hours
16,902
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 502,168
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 4,899
2010237318750 Spacers p
Стр. 17–18
0 Worker servicing ST man-
hours
16,902
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 502,168
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 4,899
2010237318750 Spacers pieces 73,488
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
19,719
48 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 18,60
7214240021810 Construction locksmith (metal fitter) man-
hours
4,064
9310060019920 Worker servicing ST man-
hours
0,214
7212030022700 Welder man-
hours
0,214
2775276309886 Metal fabrications embedded in concrete kg 18,60
2734113803207 Soft black wire, diameter 2 mm kg 0,186
2873155901200 Welding electrodes kg 0,093
4011106202741 Electrical energy kw 0,149
1010126200341 Forge coal (hard coal) kg 0,279
49 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,019
7141020013400 Industrial painter man-
hours
0,141
1 2 3 4 5
2430116100000 Chlorinated rubber enamel kg 0,148
2430226100814 Red lead primer G 355-6 kg 0,074
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,01
2320166200676 White spirit kg 0,037
1711317306661 Cleaning cotton kg 0,019
50 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 24,00
7212030022700 Welder man-
hours
15,18
2873155900800 Welding electrodes kg 14,40
4011106202741 Electrical energy kw 26,40
Total Monolithic columns
Cm-4, Cm-4a (1 piece)
3.6. Monolithic columns Cm-5, (1 piece)
51 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 1,72
7123010010200 Concrete worker man-
hours
8,664
9310060019920 Worker servicing ST man-
hours
4,767
2663102100000
20
Concrete C20/25 m³ 1,798
4100116202818 Water for mortars and concrete m³ 0,211
2952270003101 Poker vibrator machine-
hours
1,187
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,297
52 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 15,20
9310060019920 Worker servicing ST man-
hours
4,37
7124010010700 Carpenter man-
hours
17,48
2874125881241 Standard washers M10 kg 0,122
2874115841033 Standard square nu
Стр. 18–19
stenings m² 15,20 9310060019920 Worker servicing ST man- hours 4,37 7124010010700 Carpenter man- hours 17,48 2874125881241 Standard washers M10 kg 0,122 2874115841033 Standard square nuts M10 pieces 0,76 2874115825003 Standard square bolts M10 × 140 mm pieces 0,76 2875276311528 Steel construction staples kg 0,76 1 2 3 4 5 2873145887000 Conical head nails, type A kg 0,608 2030122928385 Formwork panel with 15 mm plywood m² 2,28 2010102904340 Softwood planks m³ 0,015 2010102903495 Softwood boards m³ 0,023 2320187315789 Formwork release agent (Decofrol) kg 1,824 3410520006752 Truck crane, 6–10 tf machine- hours 0,35 53 RCsD02D 1 Rebar steel PC 52, diameter over 8 mm, fabricated in a site workshop for foundations and raft beams, installed in existing structural elements. For flat slabs, columns, beams, etc. kg 234,00 7123020011140 Rebar worker man- hours 23,143 9310060019920 Worker servicing ST man- hours 8,073 2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 239,85 2746133803142 Ordinary soft wire, diameter 1.25 mm kg 2,34 2010237318750 Spacers pieces 35,10 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 9,418 54 CL18A Various metal products made of rolled profiles, sheet steel, checkered and reinforcing steel, and pipes for supports or coverings, fully or partially embedded in concrete / 80×80×15 State Standard (GOST) 103-76 kg 9,20 7214240021810 Construction locksmith (metal fitter) man- hours 2,01 9310060019920 Worker servicing ST man- hours 0,106 7212030022700 Welder man- hours 0,106 2775276309886 Metal fabrications embedded in concrete kg 9,20 2734113803207 Soft black wire, diameter 2 mm kg 0,092 2873155901200 Welding electrodes kg 0,046 4011106202741 Electrical energy kw 0,074 1010126200341 Forge coal (hard coal) kg 0,138 55 IzD10A Anticorrosion painting by brush of metal products and structures, one coat of anticorrosion primer based on red lead and two coats of chlorinated rubber enamel. tonne 0,009 7141020013400 Industrial painter man- hours 0,067 2430116100000 Chlorinated rubber enamel kg 0,07 2430226100814 Red lead primer G 355-6 kg 0,035 2430226109420 Thinner for anticorrosive varnishes D.006-1 NI 1708-61 A1 kg 0,005 2320166200676 White spirit kg 0,018 1711317306661 Cleaning cotton kg 0,009
Стр. 19–21
814 Red lead primer G 355-6 kg 0,035
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,005
2320166200676 White spirit kg 0,018
1711317306661 Cleaning cotton kg 0,009
1 2 3 4 5
56 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 12,00
7212030022700 Welder man-
hours
7,59
2873155900800 Welding electrodes kg 7,20
4011106202741 Electrical energy kw 13,20
Total Monolithic columns
Cm-5, (1 piece)
3.7. Monolithic columns Cm-6, Cm-6a (1
piece)
57 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 5,80
7123010010200 Concrete worker man-
hours
29,215
9310060019920 Worker servicing ST man-
hours
16,075
2663102100000
20
Concrete C20/25 m³ 6,064
4100116202818 Water for mortars and concrete m³ 0,71
2952270003101 Poker vibrator machine-
hours
4,002
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
1,00
58 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 26,20
9310060019920 Worker servicing ST man-
hours
7,532
7124010010700 Carpenter man-
hours
30,13
2874125881241 Standard washers M10 kg 0,21
2874115841033 Standard square nuts M10 pieces 1,31
2874115825003 Standard square bolts M10 × 140 mm pieces 1,31
2875276311528 Steel construction staples kg 1,31
2873145887000 Conical head nails, type A kg 1,048
2030122928385 Formwork panel with 15 mm plywood m² 3,93
2010102904340 Softwood planks m³ 0,026
2010102903495 Softwood boards m³ 0,039
2320187315789 Formwork release agent (Decofrol) kg 3,144
1 2 3 4 5
3410520006752 Truck crane, 6–10 tf machine-
hours
0,603
59 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 566,50
7123020011140 Rebar worker man-
hours
56,027
9310060019920 Worker servicing ST man-
hours
19,544
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 580,662
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 5,665
2010237318750 Spacers pieces 84,975
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
22,802
60 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76, M-2
kg 63,
Стр. 21–22
rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76, M-2
kg 63,00
7214240021810 Construction locksmith (metal fitter) man-
hours
13,765
9310060019920 Worker servicing ST man-
hours
0,724
7212030022700 Welder man-
hours
0,724
2775276309886 Metal fabrications embedded in concrete kg 63,00
2734113803207 Soft black wire, diameter 2 mm kg 0,63
2873155901200 Welding electrodes kg 0,315
4011106202741 Electrical energy kw 0,504
1010126200341 Forge coal (hard coal) kg 0,945
61 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,063
7141020013400 Industrial painter man-
hours
0,467
2430116100000 Chlorinated rubber enamel kg 0,491
2430226100814 Red lead primer G 355-6 kg 0,246
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,035
2320166200676 White spirit kg 0,123
1711317306661 Cleaning cotton kg 0,061
62 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 24,00
1 2 3 4 5
7212030022700 Welder man-
hours
15,18
2873155900800 Welding electrodes kg 14,40
4011106202741 Electrical energy kw 26,40
Total Monolithic columns
Cm-6, Cm-6a (1 piece)
3.8. Monolithic columns Cm-7 (1 piece)
63 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 2,35
7123010010200 Concrete worker man-
hours
11,837
9310060019920 Worker servicing ST man-
hours
6,513
2663102100000
20
Concrete C20/25 m³ 2,457
4100116202818 Water for mortars and concrete m³ 0,288
2952270003101 Poker vibrator machine-
hours
1,621
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,405
64 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 13,00
9310060019920 Worker servicing ST man-
hours
3,737
7124010010700 Carpenter man-
hours
14,95
2874125881241 Standard washers M10 kg 0,104
2874115841033 Standard square nuts M10 pieces 0,65
2874115825003 Standard square bolts M10 × 140 mm pieces 0,65
2875276311528 Steel construction staples kg 0,65
2873145887000 Conical head nails, type A kg 0,52
2030122928385 Formwork panel with 15 mm plywood m² 1,95
2010102904340 Softwood planks m³ 0,013
2010102903495 Softwood boards m³ 0,019
2320187315789 Formwork release a
Стр. 22–24
d nails, type A kg 0,52
2030122928385 Formwork panel with 15 mm plywood m² 1,95
2010102904340 Softwood planks m³ 0,013
2010102903495 Softwood boards m³ 0,019
2320187315789 Formwork release agent (Decofrol) kg 1,56
3410520006752 Truck crane, 6–10 tf machine-
hours
0,299
65 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
kg 260,40
1 2 3 4 5
slabs, columns, beams, etc.
7123020011140 Rebar worker man-
hours
25,754
9310060019920 Worker servicing ST man-
hours
8,984
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 266,91
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 2,604
2010237318750 Spacers pieces 39,06
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
10,481
66 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 6,00
7214240021810 Construction locksmith (metal fitter) man-
hours
1,311
9310060019920 Worker servicing ST man-
hours
0,069
7212030022700 Welder man-
hours
0,069
2775276309886 Metal fabrications embedded in concrete kg 6,00
2734113803207 Soft black wire, diameter 2 mm kg 0,06
2873155901200 Welding electrodes kg 0,03
4011106202741 Electrical energy kw 0,048
1010126200341 Forge coal (hard coal) kg 0,09
67 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,006
7141020013400 Industrial painter man-
hours
0,044
2430116100000 Chlorinated rubber enamel kg 0,047
2430226100814 Red lead primer G 355-6 kg 0,023
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,003
2320166200676 White spirit kg 0,012
1711317306661 Cleaning cotton kg 0,006
68 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 12,00
7212030022700 Welder man-
hours
7,59
2873155900800 Welding electrodes kg 7,20
4011106202741 Electrical energy kw 13,20
1 2 3 4 5
Total Monolithic columns
Cm-7 (1 piece)
3.9. Monolithic columns Cm-8 (1 piece)
69 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 1,50
7123010010200 Concrete worker man-
hours
7,555
9310060019920 Worker servicing ST man-
hours
4,157
2663102100000
20
Concrete C
Стр. 24–25
Small materials (boards, wire, nails, etc.) = 1,020 m³ 1,50 7123010010200 Concrete worker man- hours 7,555 9310060019920 Worker servicing ST man- hours 4,157 2663102100000 20 Concrete C20/25 m³ 1,568 4100116202818 Water for mortars and concrete m³ 0,184 2952270003101 Poker vibrator machine- hours 1,035 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 0,259 70 CB03F Formwork from reusable plywood panels, 15 mm thick, for concreting columns in structures up to 20 m in height inclusive, excluding fastenings m² 13,00 9310060019920 Worker servicing ST man- hours 3,737 7124010010700 Carpenter man- hours 14,95 2874125881241 Standard washers M10 kg 0,104 2874115841033 Standard square nuts M10 pieces 0,65 2874115825003 Standard square bolts M10 × 140 mm pieces 0,65 2875276311528 Steel construction staples kg 0,65 2873145887000 Conical head nails, type A kg 0,52 2030122928385 Formwork panel with 15 mm plywood m² 1,95 2010102904340 Softwood planks m³ 0,013 2010102903495 Softwood boards m³ 0,019 2320187315789 Formwork release agent (Decofrol) kg 1,56 3410520006752 Truck crane, 6–10 tf machine- hours 0,299 71 RCsD02D 1 Rebar steel PC 52, diameter over 8 mm, fabricated in a site workshop for foundations and raft beams, installed in existing structural elements. For flat slabs, columns, beams, etc. kg 183,14 7123020011140 Rebar worker man- hours 18,113 9310060019920 Worker servicing ST man- hours 6,318 2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 187,718 1 2 3 4 5 2746133803142 Ordinary soft wire, diameter 1.25 mm kg 1,831 2010237318750 Spacers pieces 27,471 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 7,371 72 CL18A Various metal products made of rolled profiles, sheet steel, checkered and reinforcing steel, and pipes for supports or coverings, fully or partially embedded in concrete / 80×80×15 State Standard (GOST) 103-76 kg 6,00 7214240021810 Construction locksmith (metal fitter) man- hours 1,311 9310060019920 Worker servicing ST man- hours 0,069 7212030022700 Welder man- hours 0,069 2775276309886 Metal fabrications embedded in concrete kg 6,00 2734113803207 Soft black wire, diameter 2 mm kg 0,06 2873155901200 Welding electrodes kg 0,03 4011106202741 Electrical energy kw 0,048 1010126200341 Forge coal (hard coal) kg 0,09 73 IzD10A Anticorrosion painting by brush of metal products and structures, one coat of anticorrosion primer based on red lead and two coats of chlorinated rubber enamel. tonne 0,006 7141020013400 Industrial painter man- hours 0,044 2430116100000 Chlorinated rubber enamel kg 0,047 2430226100814 Red lead primer G 355-6 kg 0,023 2430226109420 Thinner for anticorrosive varnishes D.006-1 NI 1708-61 A1 kg 0,003 2320166200676 White spirit kg 0,012 1711317306661 Cleaning cotton kg 0,006 74 CC13H Splicing of rebar s
Стр. 25–26
023
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,003
2320166200676 White spirit kg 0,012
1711317306661 Cleaning cotton kg 0,006
74 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 12,00
7212030022700 Welder man-
hours
7,59
2873155900800 Welding electrodes kg 7,20
4011106202741 Electrical energy kw 13,20
Total Monolithic columns
Cm-8 (1 piece)
3.10. Monolithic columns Cm-9 (1 piece)
75 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by m³ 0,65
1 2 3 4 5
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
7123010010200 Concrete worker man-
hours
3,274
9310060019920 Worker servicing ST man-
hours
1,801
2663102100000
20
Concrete C20/25 m³ 0,68
4100116202818 Water for mortars and concrete m³ 0,08
2952270003101 Poker vibrator machine-
hours
0,448
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,112
76 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 4,70
9310060019920 Worker servicing ST man-
hours
1,351
7124010010700 Carpenter man-
hours
5,405
2874125881241 Standard washers M10 kg 0,038
2874115841033 Standard square nuts M10 pieces 0,235
2874115825003 Standard square bolts M10 × 140 mm pieces 0,235
2875276311528 Steel construction staples kg 0,235
2873145887000 Conical head nails, type A kg 0,188
2030122928385 Formwork panel with 15 mm plywood m² 0,705
2010102904340 Softwood planks m³ 0,005
2010102903495 Softwood boards m³ 0,007
2320187315789 Formwork release agent (Decofrol) kg 0,564
3410520006752 Truck crane, 6–10 tf machine-
hours
0,108
77 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 89,92
7123020011140 Rebar worker man-
hours
8,893
9310060019920 Worker servicing ST man-
hours
3,102
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 92,168
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 0,899
2010237318750 Spacers pieces 13,488
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
3,619
78 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
kg 6,00
Стр. 26–28
ne-
hours
3,619
78 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
kg 6,00
1 2 3 4 5
in concrete / 80×80×15 State Standard
(GOST) 103-76
7214240021810 Construction locksmith (metal fitter) man-
hours
1,311
9310060019920 Worker servicing ST man-
hours
0,069
7212030022700 Welder man-
hours
0,069
2775276309886 Metal fabrications embedded in concrete kg 6,00
2734113803207 Soft black wire, diameter 2 mm kg 0,06
2873155901200 Welding electrodes kg 0,03
4011106202741 Electrical energy kw 0,048
1010126200341 Forge coal (hard coal) kg 0,09
79 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,006
7141020013400 Industrial painter man-
hours
0,044
2430116100000 Chlorinated rubber enamel kg 0,047
2430226100814 Red lead primer G 355-6 kg 0,023
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,003
2320166200676 White spirit kg 0,012
1711317306661 Cleaning cotton kg 0,006
80 CC13H
Splicing of rebar steel for reinforced
monolithic concrete by bench electric
welding, using one splice plate and butt
welding, for bars with diameter 18–28
mm
pieces 12,00
7212030022700 Welder man-
hours
7,59
2873155900800 Welding electrodes kg 7,20
4011106202741 Electrical energy kw 13,20
Total Monolithic columns
Cm-9 (1 piece)
3.11. Monolithic frame Rm-1, Rm-2 (1
piece)
81 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 2,04
7123010010200 Concrete worker man-
hours
10,275
9310060019920 Worker servicing ST man-
hours
5,654
1 2 3 4 5
2663102100000
20
Concrete C20/25 m³ 2,133
4100116202818 Water for mortars and concrete m³ 0,25
2952270003101 Poker vibrator machine-
hours
1,408
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,352
82 CB03F
Formwork from reusable plywood panels,
15 mm thick, for concreting columns in
structures up to 20 m in height inclusive,
excluding fastenings
m² 10,00
9310060019920 Worker servicing ST man-
hours
2,875
7124010010700 Carpenter man-
hours
11,50
2874125881241 Standard washers M10 kg 0,08
2874115841033 Standard square nuts M10 pieces 0,50
2874115825003 Standard square bolts M10 × 140 mm pieces 0,50
2875276311528 Steel construction staples kg 0,50
2873145887000 Conical head nails, type A kg 0,40
2030122928385 Formwork panel with 15 mm plywood m² 1,50
2010102904340 Softwood planks m³ 0,01
2010102903495 Softwood boa
Стр. 28–29
tion staples kg 0,50
2873145887000 Conical head nails, type A kg 0,40
2030122928385 Formwork panel with 15 mm plywood m² 1,50
2010102904340 Softwood planks m³ 0,01
2010102903495 Softwood boards m³ 0,015
2320187315789 Formwork release agent (Decofrol) kg 1,20
3410520006752 Truck crane, 6–10 tf machine-
hours
0,23
83 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 301,62
7123020011140 Rebar worker man-
hours
29,83
9310060019920 Worker servicing ST man-
hours
10,406
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 309,16
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 3,016
2010237318750 Spacers pieces 45,243
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
12,14
84 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 9,00
7214240021810 Construction locksmith (metal fitter) man-
hours
1,966
9310060019920 Worker servicing ST man-
hours
0,103
7212030022700 Welder man-
hours
0,103
2775276309886 Metal fabrications embedded in concrete kg 9,00
2734113803207 Soft black wire, diameter 2 mm kg 0,09
2873155901200 Welding electrodes kg 0,045
4011106202741 Electrical energy kw 0,072
1 2 3 4 5
1010126200341 Forge coal (hard coal) kg 0,135
85 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,009
7141020013400 Industrial painter man-
hours
0,067
2430116100000 Chlorinated rubber enamel kg 0,07
2430226100814 Red lead primer G 355-6 kg 0,035
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,005
2320166200676 White spirit kg 0,018
1711317306661 Cleaning cotton kg 0,009
Total Monolithic frame
Rm-1, Rm-2 (1 piece)
Total Columns
4. Beams
4.1. Stair beam Rg-1 (1 piece)
86 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 0,57
7123010010200 Concrete worker man-
hours
2,871
9310060019920 Worker servicing ST man-
hours
1,58
2663102100000
20
Concrete C20/25 m³ 0,596
4100116202818 Water for mortars and concrete m³ 0,07
2952270003101 Poker vibrator machine-
hours
0,393
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,098
87 CB03E
Formwork fr
Стр. 29–30
4100116202818 Water for mortars and concrete m³ 0,07
2952270003101 Poker vibrator machine-
hours
0,393
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,098
87 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 2,00
9310060019920 Worker servicing ST man-
hours
0,345
7124010010700 Carpenter man-
hours
1,955
2874125881241 Standard washers M10 kg 0,01
2874115841033 Standard square nuts M10 pieces 0,60
2874115825003 Standard square bolts M10 × 140 mm pieces 0,60
1 2 3 4 5
2875276311528 Steel construction staples kg 0,06
2873145887000 Conical head nails, type A kg 0,06
2030122928385 Formwork panel with 15 mm plywood m² 0,26
2010102904340 Softwood planks m³ 0,002
2010102903495 Softwood boards m³ 0,002
2320187315789 Formwork release agent (Decofrol) kg 0,24
3410520006752 Truck crane, 6–10 tf machine-
hours
0,046
88 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs,
with placement of partially or fully
monolithic slabs with beams or
monolithic beams with prefabricated
slabs type PE 3100 R
pieces 3,00
7124010010700
1
Carpenter man-
hours
1,035
9310060019920 Worker servicing ST man-
hours
0,517
2811236310185 Metal adjustable props PE 3100 R kg 1,20
2010102904340 Softwood planks m³ 0,002
2922140007000 Crane machine-
hours
0,034
89 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 82,31
7123020011140 Rebar worker man-
hours
8,14
9310060019920 Worker servicing ST man-
hours
2,84
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 84,368
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 0,823
2010237318750 Spacers pieces 12,347
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
3,313
Total Stair beam Rg-1 (1
piece)
4.2. Stair beam Rg-2 (1 piece)
90 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 0,51
7123010010200 Concrete worker man- 2,569
Стр. 30–32
pads, floor slabs, diaphragms, stair flights, etc., in existing buildings / C20/25 (M350) Small materials (boards, wire, nails, etc.) = 1,020 m³ 0,51 7123010010200 Concrete worker man- 2,569 1 2 3 4 5 hours 9310060019920 Worker servicing ST man- hours 1,413 2663102100000 20 Concrete C20/25 m³ 0,533 4100116202818 Water for mortars and concrete m³ 0,062 2952270003101 Poker vibrator machine- hours 0,352 3410520001373 Truck crane, 5 ton-force (tf) machine- hours 0,088 91 CB03E Formwork from reusable plywood panels, 15 mm thick, for concreting slabs and beams in structures up to 20 m in height inclusive, excluding fastenings m² 2,00 9310060019920 Worker servicing ST man- hours 0,345 7124010010700 Carpenter man- hours 1,955 2874125881241 Standard washers M10 kg 0,01 2874115841033 Standard square nuts M10 pieces 0,60 2874115825003 Standard square bolts M10 × 140 mm pieces 0,60 2875276311528 Steel construction staples kg 0,06 2873145887000 Conical head nails, type A kg 0,06 2030122928385 Formwork panel with 15 mm plywood m² 0,26 2010102904340 Softwood planks m³ 0,002 2010102903495 Softwood boards m³ 0,002 2320187315789 Formwork release agent (Decofrol) kg 0,24 3410520006752 Truck crane, 6–10 tf machine- hours 0,046 92 CB11A Supports with inventory adjustable props for installation of prefabricated slabs, with placement of partially or fully monolithic slabs with beams or monolithic beams with prefabricated slabs type PE 3100 R pieces 3,00 7124010010700 1 Carpenter man- hours 1,035 9310060019920 Worker servicing ST man- hours 0,517 2811236310185 Metal adjustable props PE 3100 R kg 1,20 2010102904340 Softwood planks m³ 0,002 2922140007000 Crane machine- hours 0,034 93 RCsD02D 1 Rebar steel PC 52, diameter over 8 mm, fabricated in a site workshop for foundations and raft beams, installed in existing structural elements. For flat slabs, columns, beams, etc. kg 82,07 7123020011140 Rebar worker man- hours 8,117 9310060019920 Worker servicing ST man- hours 2,831 1 2 3 4 5 2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 84,122 2746133803142 Ordinary soft wire, diameter 1.25 mm kg 0,821 2010237318750 Spacers pieces 12,31 2922140006703 Window crane, capacity 0.0015 meganewtons (MN) (0.15 ton-force (tf)) machine- hours 3,303 94 CL18A Various metal products made of rolled profiles, sheet steel, checkered and reinforcing steel, and pipes for supports or coverings, fully or partially embedded in concrete / 80×80×15 State Standard (GOST) 103-76 kg 2,25 7214240021810 Construction locksmith (metal fitter) man- hours 0,492 9310060019920 Worker servicing ST man- hours 0,026 7212030022700 Welder man- hours 0,026 2775276309886 Metal fabrications embedded in concrete kg 2,25 2734113803207 Soft black wire, diameter 2 mm kg 0,022 2873155901200 Welding electrodes kg 0,011 4011106202741 Electrical energy kw 0,018
Стр. 32–33
76309886 Metal fabrications embedded in concrete kg 2,25
2734113803207 Soft black wire, diameter 2 mm kg 0,022
2873155901200 Welding electrodes kg 0,011
4011106202741 Electrical energy kw 0,018
1010126200341 Forge coal (hard coal) kg 0,034
Total Stair beam Rg-2 (1
piece)
4.3. Beams at elevation 3.500
95 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 52,50
7123010010200 Concrete worker man-
hours
264,442
9310060019920 Worker servicing ST man-
hours
145,504
2663102100000
20
Concrete C20/25 m³ 54,889
4100116202818 Water for mortars and concrete m³ 6,426
2952270003101 Poker vibrator machine-
hours
36,225
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
9,056
96 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 420,00
9310060019920 Worker servicing ST man- 72,45
1 2 3 4 5
hours
7124010010700 Carpenter man-
hours
410,55
2874125881241 Standard washers M10 kg 2,10
2874115841033 Standard square nuts M10 pieces 126,00
2874115825003 Standard square bolts M10 × 140 mm pieces 126,00
2875276311528 Steel construction staples kg 12,60
2873145887000 Conical head nails, type A kg 12,60
2030122928385 Formwork panel with 15 mm plywood m² 54,60
2010102904340 Softwood planks m³ 0,42
2010102903495 Softwood boards m³ 0,42
2320187315789 Formwork release agent (Decofrol) kg 50,40
3410520006752 Truck crane, 6–10 tf machine-
hours
9,66
97 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs,
with placement of partially or fully
monolithic slabs with beams or
monolithic beams with prefabricated
slabs type PE 3100 R
pieces 840,00
7124010010700
1
Carpenter man-
hours
289,80
9310060019920 Worker servicing ST man-
hours
144,90
2811236310185 Metal adjustable props PE 3100 R kg 336,00
2010102904340 Softwood planks m³ 0,42
2922140007000 Crane machine-
hours
9,66
98 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 10 568,10
7123020011140 Rebar worker man-
hours
1 045,185
9310060019920 Worker servicing ST man-
hours
364,599
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 10 832,302
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 105,681
2010237318750 Spacers pieces 1 585,215
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
425,366
99 CL18A
Various metal
Стр. 33–34
r 1.25 mm kg 105,681
2010237318750 Spacers pieces 1 585,215
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
425,366
99 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 17,16
7214240021810 Construction locksmith (metal fitter) man-
hours
3,749
9310060019920 Worker servicing ST man- 0,197
1 2 3 4 5
hours
7212030022700 Welder man-
hours
0,197
2775276309886 Metal fabrications embedded in concrete kg 17,16
2734113803207 Soft black wire, diameter 2 mm kg 0,172
2873155901200 Welding electrodes kg 0,086
4011106202741 Electrical energy kw 0,137
1010126200341 Forge coal (hard coal) kg 0,257
Total Beams at elevation
3.500
4.4. Beams at elevation 7.100
100 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 58,50
7123010010200 Concrete worker man-
hours
294,664
9310060019920 Worker servicing ST man-
hours
162,133
2663102100000
20
Concrete C20/25 m³ 61,162
4100116202818 Water for mortars and concrete m³ 7,16
2952270003101 Poker vibrator machine-
hours
40,365
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
10,091
101 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 380,00
9310060019920 Worker servicing ST man-
hours
65,55
7124010010700 Carpenter man-
hours
371,45
2874125881241 Standard washers M10 kg 1,90
2874115841033 Standard square nuts M10 pieces 114,00
2874115825003 Standard square bolts M10 × 140 mm pieces 114,00
2875276311528 Steel construction staples kg 11,40
2873145887000 Conical head nails, type A kg 11,40
2030122928385 Formwork panel with 15 mm plywood m² 49,40
2010102904340 Softwood planks m³ 0,38
2010102903495 Softwood boards m³ 0,38
2320187315789 Formwork release agent (Decofrol) kg 45,60
3410520006752 Truck crane, 6–10 tf machine-
hours
8,74
102 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs, pieces 765,00
Стр. 34–36
lease agent (Decofrol) kg 45,60
3410520006752 Truck crane, 6–10 tf machine-
hours
8,74
102 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs, pieces 765,00
1 2 3 4 5
with placement of partially or fully
monolithic slabs with beams or
monolithic beams with prefabricated
slabs type PE 3100 R
7124010010700
1
Carpenter man-
hours
263,925
9310060019920 Worker servicing ST man-
hours
131,962
2811236310185 Metal adjustable props PE 3100 R kg 306,00
2010102904340 Softwood planks m³ 0,383
2922140007000 Crane machine-
hours
8,797
103 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 9 051,64
7123020011140 Rebar worker man-
hours
895,207
9310060019920 Worker servicing ST man-
hours
312,282
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 9 277,931
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 90,516
2010237318750 Spacers pieces 1 357,746
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
364,329
104 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / 80×80×15 State Standard
(GOST) 103-76
kg 65,53
7214240021810 Construction locksmith (metal fitter) man-
hours
14,318
9310060019920 Worker servicing ST man-
hours
0,754
7212030022700 Welder man-
hours
0,754
2775276309886 Metal fabrications embedded in concrete kg 65,53
2734113803207 Soft black wire, diameter 2 mm kg 0,655
2873155901200 Welding electrodes kg 0,328
4011106202741 Electrical energy kw 0,524
1010126200341 Forge coal (hard coal) kg 0,983
105 IzD10A
Anticorrosion painting by brush of metal
products and structures, one coat of
anticorrosion primer based on red lead
and two coats of chlorinated rubber
enamel.
tonne 0,066
7141020013400 Industrial painter man-
hours
0,489
1 2 3 4 5
2430116100000 Chlorinated rubber enamel kg 0,515
2430226100814 Red lead primer G 355-6 kg 0,257
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 0,036
2320166200676 White spirit kg 0,129
1711317306661 Cleaning cotton kg 0,064
Total Beams at elevation
7.100
Total Beams
5. Slab
5.1. Slab on axis Y–EA
106 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete /
kg 1 419,60
7214240021810 Construction locksmith (metal fitter) man-
hours
310,183
9310060019920 Worker servicing ST man-
hours
16,325
7212030022700 Welder man-
hours
16,325
2775276309886 Metal fabrications embedded in concrete kg 1 419
Стр. 36–37
ith (metal fitter) man-
hours
310,183
9310060019920 Worker servicing ST man-
hours
16,325
7212030022700 Welder man-
hours
16,325
2775276309886 Metal fabrications embedded in concrete kg 1 419,60
2734113803207 Soft black wire, diameter 2 mm kg 14,196
2873155901200 Welding electrodes kg 7,098
4011106202741 Electrical energy kw 11,357
1010126200341 Forge coal (hard coal) kg 21,294
Total Slab on axis Y–EA
5.2. Floors at elevation 0.000
107 TsC54B
Base layer of rubble stone
m³ 169,00
9310060019900 Unskilled worker man-
hours
192,406
1411122201752 Crushed stone m³ 194,35
4100126202818 Water m³ 16,90
2912340002506
Mobile compressor with internal combustion
engine, pressure up to 686 kilopascals (kPa) (7
atmospheres (atm)), capacity 2.2 m³/min
machine-
hours
40,813
2592270004021 Pneumatic or mechanical compactor, 150–200 kg machine-
hours
81,627
108 CA02C
Plain concrete cast for leveling layers,
slopes and screeds at heights up to 35 m
inclusive, prepared by concrete batching
plant or ready-mix concrete, placed by
conventional means, class C8/10
Small materials (softwood planks) = 1,010
m³ 4,30
1 2 3 4 5
7123010010200 Concrete worker man-
hours
19,038
9310060019920 Worker servicing ST man-
hours
3,214
2663102100000
150
Concrete C8/10 m³ 4,452
4100116202818 Water for mortars and concrete m³ 0,434
2922140007000 Crane machine-
hours
1,236
2952270003000 Surface vibrator machine-
hours
1,978
109 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 140,70
7123010010200 Concrete worker man-
hours
708,706
9310060019920 Worker servicing ST man-
hours
389,95
2663102100000
20
Concrete C20/25 m³ 147,102
4100116202818 Water for mortars and concrete m³ 17,222
2952270003101 Poker vibrator machine-
hours
97,083
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
24,271
110 RCsD02D
Rebar steel OB 37, with diameter over 8
mm, fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 677,50
7123020011140 Rebar worker man-
hours
60,772
9310060019920 Worker servicing ST man-
hours
23,374
2710602000035 Plain rebar steel OB 37, diameter over 8 mm kg 694,437
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 6,775
2010237318750 Spacers pieces 101,625
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
27,269
111 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
Стр. 37–38
))
machine-
hours
27,269
111 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 5 720,10
7123020011140 Rebar worker man-
hours
565,718
9310060019920 Worker servicing ST man- 197,343
1 2 3 4 5
hours
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 5 863,102
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 57,201
2010237318750 Spacers pieces 858,015
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
230,234
Total Floors at elevation
0.000
5.3. Slab at elevation 3.500
112 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 116,00
7123010010200 Concrete worker man-
hours
584,292
9310060019920 Worker servicing ST man-
hours
321,494
2663102100000
20
Concrete C20/25 m³ 121,278
4100116202818 Water for mortars and concrete m³ 14,198
2952270003101 Poker vibrator machine-
hours
80,04
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
20,01
113 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 660,00
9310060019920 Worker servicing ST man-
hours
113,85
7124010010700 Carpenter man-
hours
645,15
2874125881241 Standard washers M10 kg 3,30
2874115841033 Standard square nuts M10 pieces 198,00
2874115825003 Standard square bolts M10 × 140 mm pieces 198,00
2875276311528 Steel construction staples kg 19,80
2873145887000 Conical head nails, type A kg 19,80
2030122928385 Formwork panel with 15 mm plywood m² 85,80
2010102904340 Softwood planks m³ 0,66
2010102903495 Softwood boards m³ 0,66
2320187315789 Formwork release agent (Decofrol) kg 79,20
3410520006752 Truck crane, 6–10 tf machine-
hours
15,18
114 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs,
with placement of partially or fully
monolithic slabs with beams or
pieces 1 320,00
Стр. 38–40
ne-
hours
15,18
114 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs,
with placement of partially or fully
monolithic slabs with beams or
pieces 1 320,00
1 2 3 4 5
monolithic beams with prefabricated
slabs type PE 3100 R
7124010010700
1
Carpenter man-
hours
455,40
9310060019920 Worker servicing ST man-
hours
227,70
2811236310185 Metal adjustable props PE 3100 R kg 528,00
2010102904340 Softwood planks m³ 0,66
2922140007000 Crane machine-
hours
15,18
115 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 16 834,18
7123020011140 Rebar worker man-
hours
1 664,90
9310060019920 Worker servicing ST man-
hours
580,779
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 17 255,034
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 168,342
2010237318750 Spacers pieces 2 525,127
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
677,576
116 CL18A
Various metal products made of rolled
profiles, sheet steel, checkered and
reinforcing steel, and pipes for supports
or coverings, fully or partially embedded
in concrete / Embedded parts M1
kg 21,84
7214240021810 Construction locksmith (metal fitter) man-
hours
4,772
9310060019920 Worker servicing ST man-
hours
0,251
7212030022700 Welder man-
hours
0,251
2775276309886 Metal fabrications embedded in concrete kg 21,84
2734113803207 Soft black wire, diameter 2 mm kg 0,218
2873155901200 Welding electrodes kg 0,109
4011106202741 Electrical energy kw 0,175
1010126200341 Forge coal (hard coal) kg 0,328
Total Slab at elevation
3.500
5.4. Slab at elevation 7.100
117 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
m³ 98,00
1 2 3 4 5
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
7123010010200 Concrete worker man-
hours
493,626
9310060019920 Worker servicing ST man-
hours
271,607
2663102100000
20
Concrete C20/25 m³ 102,459
4100116202818 Water for mortars and concrete m³ 11,995
2952270003101 Poker vibrator machine-
hours
67,62
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
16,905
118 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 550,00
9310060019920 Worker servicing ST man-
hours
94,875
7124010010700 Carpenter man-
hours
537,625
2874125881241 Standard washers M10 kg 2,75
2874115841033 Standard square nuts M10 pieces 165,00
2874115825003 Standa
Стр. 40–41
servicing ST man-
hours
94,875
7124010010700 Carpenter man-
hours
537,625
2874125881241 Standard washers M10 kg 2,75
2874115841033 Standard square nuts M10 pieces 165,00
2874115825003 Standard square bolts M10 × 140 mm pieces 165,00
2875276311528 Steel construction staples kg 16,50
2873145887000 Conical head nails, type A kg 16,50
2030122928385 Formwork panel with 15 mm plywood m² 71,50
2010102904340 Softwood planks m³ 0,55
2010102903495 Softwood boards m³ 0,55
2320187315789 Formwork release agent (Decofrol) kg 66,00
3410520006752 Truck crane, 6–10 tf machine-
hours
12,65
119 CB11A
Supports with inventory adjustable props
for installation of prefabricated slabs,
with placement of partially or fully
monolithic slabs with beams or
monolithic beams with prefabricated
slabs type PE 3100 R
pieces 1 100,00
7124010010700
1
Carpenter man-
hours
379,50
9310060019920 Worker servicing ST man-
hours
189,75
2811236310185 Metal adjustable props PE 3100 R kg 440,00
2010102904340 Softwood planks m³ 0,55
2922140007000 Crane machine-
hours
12,65
120 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 6 579,55
1 2 3 4 5
7123020011140 Rebar worker man-
hours
650,717
9310060019920 Worker servicing ST man-
hours
226,994
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 6 744,039
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 65,796
2010237318750 Spacers pieces 986,933
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
264,827
Total Slab at elevation
7.100
5.5. Interior staircase SC-1
121 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 3,60
7123010010200 Concrete worker man-
hours
18,133
9310060019920 Worker servicing ST man-
hours
9,977
2663102100000
20
Concrete C20/25 m³ 3,764
4100116202818 Water for mortars and concrete m³ 0,441
2952270003101 Poker vibrator machine-
hours
2,484
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,621
122 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 12,00
9310060019920 Worker servicing ST man-
hours
2,07
7124010010700 Carpenter man-
hours
11,73
2874125881241 Standard washers M10 kg 0,06
2874115841033 Standard square nuts M10 pieces 3,60
2874115825003 Standard square bolts M10 × 140 mm pieces 3,60
2875276311528 Steel construction staples kg
Стр. 41–42
25881241 Standard washers M10 kg 0,06
2874115841033 Standard square nuts M10 pieces 3,60
2874115825003 Standard square bolts M10 × 140 mm pieces 3,60
2875276311528 Steel construction staples kg 0,36
2873145887000 Conical head nails, type A kg 0,36
2030122928385 Formwork panel with 15 mm plywood m² 1,56
2010102904340 Softwood planks m³ 0,012
2010102903495 Softwood boards m³ 0,012
2320187315789 Formwork release agent (Decofrol) kg 1,44
3410520006752 Truck crane, 6–10 tf machine-
hours
0,276
1 2 3 4 5
123 RCsD02D
Rebar steel OB 37, with diameter over 8
mm, fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 122,90
7123020011140 Rebar worker man-
hours
11,024
9310060019920 Worker servicing ST man-
hours
4,24
2710602000035 Plain rebar steel OB 37, diameter over 8 mm kg 125,972
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 1,229
2010237318750 Spacers pieces 18,435
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
4,947
124 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 1 175,60
7123020011140 Rebar worker man-
hours
116,267
9310060019920 Worker servicing ST man-
hours
40,558
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 1 204,99
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 11,756
2010237318750 Spacers pieces 176,34
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
47,318
Total Interior staircase
SC-1
5.6. Interior staircase SC-2
125 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 3,50
7123010010200 Concrete worker man-
hours
17,629
9310060019920 Worker servicing ST man-
hours
9,70
2663102100000
20
Concrete C20/25 m³ 3,659
4100116202818 Water for mortars and concrete m³ 0,428
2952270003101 Poker vibrator machine-
hours
2,415
3410520001373 Truck crane, 5 ton-force (tf) machine- 0,604
Стр. 42–44
20
Concrete C20/25 m³ 3,659
4100116202818 Water for mortars and concrete m³ 0,428
2952270003101 Poker vibrator machine-
hours
2,415
3410520001373 Truck crane, 5 ton-force (tf) machine- 0,604
1 2 3 4 5
hours
126 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 12,00
9310060019920 Worker servicing ST man-
hours
2,07
7124010010700 Carpenter man-
hours
11,73
2874125881241 Standard washers M10 kg 0,06
2874115841033 Standard square nuts M10 pieces 3,60
2874115825003 Standard square bolts M10 × 140 mm pieces 3,60
2875276311528 Steel construction staples kg 0,36
2873145887000 Conical head nails, type A kg 0,36
2030122928385 Formwork panel with 15 mm plywood m² 1,56
2010102904340 Softwood planks m³ 0,012
2010102903495 Softwood boards m³ 0,012
2320187315789 Formwork release agent (Decofrol) kg 1,44
3410520006752 Truck crane, 6–10 tf machine-
hours
0,276
127 RCsD02D
Rebar steel OB 37, with diameter over 8
mm, fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 105,78
7123020011140 Rebar worker man-
hours
9,488
9310060019920 Worker servicing ST man-
hours
3,649
2710602000035 Plain rebar steel OB 37, diameter over 8 mm kg 108,424
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 1,058
2010237318750 Spacers pieces 15,867
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
4,258
128 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 439,56
7123020011140 Rebar worker man-
hours
43,472
9310060019920 Worker servicing ST man-
hours
15,165
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 450,549
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 4,396
2010237318750 Spacers pieces 65,934
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
17,692
Total Interior staircase
SC-2
1 2 3 4 5
5.7. Interior staircase SC-3
129 RCsB04D
Ready-mix concrete delivered from the
ready-mix concrete plant and placed by
conventional means in columns, beams,
ribs, slabs, landings, staircases, retaining
walls, reinforced concrete pads, floor
slabs, diaphragms, stair flights, etc., in
existing buildings / C20/25 (M350)
Small materials (boards, wire, nails, etc.) = 1,020
m³ 3,50
7123010010200 Concrete worker man-
hours
17,629
9310060019920 Worker servicing ST man-
hours
9,70
2663102100000
20
Concrete C20/25 m³ 3,659
4100116202818 Water for mortars and concrete m³ 0,428
2952270003101 Poker vibrator machine-
hours
2,415
3410520001373 Truck crane, 5 ton-force (tf) machine-
hour
Стр. 44–45
0
20
Concrete C20/25 m³ 3,659
4100116202818 Water for mortars and concrete m³ 0,428
2952270003101 Poker vibrator machine-
hours
2,415
3410520001373 Truck crane, 5 ton-force (tf) machine-
hours
0,604
130 CB03E
Formwork from reusable plywood panels,
15 mm thick, for concreting slabs and
beams in structures up to 20 m in height
inclusive, excluding fastenings
m² 9,00
9310060019920 Worker servicing ST man-
hours
1,552
7124010010700 Carpenter man-
hours
8,797
2874125881241 Standard washers M10 kg 0,045
2874115841033 Standard square nuts M10 pieces 2,70
2874115825003 Standard square bolts M10 × 140 mm pieces 2,70
2875276311528 Steel construction staples kg 0,27
2873145887000 Conical head nails, type A kg 0,27
2030122928385 Formwork panel with 15 mm plywood m² 1,17
2010102904340 Softwood planks m³ 0,009
2010102903495 Softwood boards m³ 0,009
2320187315789 Formwork release agent (Decofrol) kg 1,08
3410520006752 Truck crane, 6–10 tf machine-
hours
0,207
131 RCsD02D
Rebar steel OB 37, with diameter over 8
mm, fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 105,78
7123020011140 Rebar worker man-
hours
9,488
9310060019920 Worker servicing ST man-
hours
3,649
2710602000035 Plain rebar steel OB 37, diameter over 8 mm kg 108,424
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 1,058
2010237318750 Spacers pieces 15,867
1 2 3 4 5
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
4,258
132 RCsD02D
1
Rebar steel PC 52, diameter over 8 mm,
fabricated in a site workshop for
foundations and raft beams, installed in
existing structural elements. For flat
slabs, columns, beams, etc.
kg 377,40
7123020011140 Rebar worker man-
hours
37,325
9310060019920 Worker servicing ST man-
hours
13,02
2710602000038 Plain rebar steel PC 52, diameter over 8 mm kg 386,835
2746133803142 Ordinary soft wire, diameter 1.25 mm kg 3,774
2010237318750 Spacers pieces 56,61
2922140006703 Window crane, capacity 0.0015 meganewtons
(MN) (0.15 ton-force (tf))
machine-
hours
15,19
Total Interior staircase
SC-3
Total Slab
6. Elevator shaft (A1, A2)
133 CA03G
Placing of concrete in reinforced
structures of foundations, plinths,
retaining walls and walls below zero
level, concrete prepared at the ready-mix
concrete plant or ready-mix concrete in
accordance with CA01, placed by
conventional means, reinforced concrete
class C20/25
Small materials (softwood planks, nails, staples) =
1,015
m³ 3,80
7123010010200 Concrete worker man-
hours
17,48
9310060019920 Worker servicing ST man-
hours
1,748
2663102100000
20
Concrete C20/25 m³ 3,953
4100116202818 Water for mortars and concrete m³ 0,386
2952270003100 Deep vibrator machine-
hours
2,622
341052000
Стр. 45–46
ker servicing ST man- hours 1,748 2663102100000 20 Concrete C20/25 m³ 3,953 4100116202818 Water for mortars and concrete m³ 0,386 2952270003100 Deep vibrator machine- hours 2,622 3410520006752 Truck crane, 6–10 tf machine- hours 1,092 134 CB02A Formwork from reusable panels with sheathing of short and very short softwood boards for placing concrete in pads, cup foundations and equipment foundations, including fastenings m² 30,00 9310060019920 Worker servicing ST man- hours 5,175 1 2 3 4 5 7124010010700 1 Carpenter man- hours 36,225 2874125881241 Standard washers M10 kg 0,15 2874115841033 Standard square nuts M10 pieces 9,00 2874115825003 Standard square bolts M10 × 140 mm pieces 9,00 2875276311528 Steel construction staples kg 0,90 2734113803233 Soft black wire, diameter 2.5 mm kg 1,50 2873145887000 Conical head nails, type A kg 2,40 2020212928347 Formwork panel type P, beech plywood 15 mm m² 3,00 2010102903495 Softwood boards m³ 0,105 2010102900900 Softwood round timber m³ 0,015 2320187315789 Formwork release agent (Decofrol) kg 3,60 135 CC01E Rebar steel class OB 37, placed in strip foundations and raft beams, fabricated in centralized workshop, bar diameter up to 8 mm inclusive kg 51,92 7123020011140 Rebar worker man- hours 3,821 9310060019920 Worker servicing ST man- hours 0,179 2710602100000 Rebar steel OB 37 ≤ 8 mm kg 53,218 2010237318750 Spacers pieces 7,788 2734113803881 Soft black steel wire, diameter 1 mm kg 0,519 136 CC01F1 Rebar steel class PC 52, placed in strip foundations and raft beams, fabricated in site workshop, bar diameter over 8 mm kg 1 226,80 7123020011140 Rebar worker man- hours 76,184 9310060019920 Worker servicing ST man- hours 4,232 2710602200000 Rebar steel PC 52 > 8 mm kg 1 257,47 2010237318750 Spacers pieces 184,02 2734113803881 Soft black steel wire, diameter 1 mm kg 12,268 137 CL57A Installation and fixing of embedded parts in monolithic reinforced concrete, weight up to 4 kg / Embedded part M-1, M-2 Small materials and installation materials (grease, rags, kerosene, etc.) = 1,010 kg 50,70 7136080025001 Installer man- hours 12,244 2811236309900 Metal fabrications kg 53,255 2412126100010 Red lead (minium) kg 1,024 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,512 3110500002401 Welding machine, 28–35 kW machine- hours 4,664 2922140006702 Window crane machine- hours 0,583 138 CL08A Factory-fabricated metal elements (columns, beams, trusses), delivered fully assembled, mounted on site, in lightweight structural framework tonne 6,06
Стр. 46–48
rane machine- hours 0,583 138 CL08A Factory-fabricated metal elements (columns, beams, trusses), delivered fully assembled, mounted on site, in lightweight structural framework tonne 6,06 1 2 3 4 5 7214210026800 Metal structure installer man- hours 243,915 9310060019920 Worker servicing ST man- hours 34,845 2811106301200 Metal elements kg 6 181,20 2775276309886 Metal fabrications embedded in concrete kg 12,12 2873155901340 Welding electrode for low-alloy steel S 1125/2 E 50B 4 kg 2,727 2874115842700 Hexagonal nut M20 pieces 39,39 2874115802500 Hexagonal head bolt M20 pieces 39,39 2874115883700 Washer M20 pieces 39,39 2413547308164 Technical calcium carbide (carbide) S102 kg 0,394 2411115904512 Technical gaseous oxygen S2031 m³ 0,606 4011106202741 Electrical energy kw 2,727 3410520006728 Pneumatic crane up to 9.9 ton-force (TF) with lattice boom machine- hours 1,045 139 CL57A Installation and fixing of embedded parts in monolithic reinforced concrete, weight up to 4 kg / Embedded part M-3 Small materials and installation materials (grease, rags, kerosene, etc.) = 1,010 kg 25,30 7136080025001 Installer man- hours 6,11 2811236309900 Metal fabrications kg 26,575 2412126100010 Red lead (minium) kg 0,511 2873155900311 Electrodes E-42A, diameter 4 mm kg 0,256 3110500002401 Welding machine, 28–35 kW machine- hours 2,328 2922140006702 Window crane machine- hours 0,291 140 CL57B Installation and fixing of embedded parts in monolithic reinforced concrete: with weight under 10 kg / Embedded part M-4 Small materials and installation materials (grease, rags, kerosene, etc.) = 1,010 kg 129,32 7136080025001 Installer man- hours 15,615 2811236309900 Metal fabrications kg 135,838 2412126100010 Red lead (minium) kg 2,612 2873155900311 Electrodes E-42A, diameter 4 mm kg 1,306 3110500002401 Welding machine, 28–35 kW machine- hours 11,897 2922140006702 Window crane machine- hours 1,933 141 IzD10A Anticorrosion painting by brush of metal products and structures with one coat of anticorrosive primer based on red lead and two coats of chlorinated rubber enamel. tonne 6,17 7141020013400 Industrial painter man- hours 45,695 2430116100000 Chlorinated rubber enamel kg 48,126 1 2 3 4 5 2430226100814 Red lead primer G 355-6 kg 24,063 2430226109420 Thinner for anticorrosive varnishes D.006-1 NI 1708-61 A1 kg 3,394 2320166200676 White spirit kg 12,031 1711317306661 Cleaning cotton kg 6,016 142 CL31A Protection of metal structures with intumescent fire-retardant coating “Pirex- Metal Plus” m² 162,54 7134050013250 Insulator man- hours 271,035 9310060019920 Worker servicing ST man- hours 37,384 2430126104976 Fire-retardant paint “Pirex-Metal Plus” R90* kg 308,826 2430226101026 Anticorrosive primer GF 021 kg 21,943 1711317306661 Cleaning cotton kg 8,29 2320166200676 White spirit kg 24,381 2681126001472 Dry sandpaper 23 × 30 cm,
Стр. 48
al Plus” R90* kg 308,826
2430226101026 Anticorrosive primer GF 021 kg 21,943
1711317306661 Cleaning cotton kg 8,29
2320166200676 White spirit kg 24,381
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 81,27
Total Elevator shaft (A1,
A2)
Total
Social fund
Total
Transportation of materials
Storage expenses
Direct expenses
Overhead expenses
Total
Estimated profit
Total estimate:
Including wages
Subsemnata, Poleacova Ana, tradu cător
autorizat, (limba Englez ă), certific
exactitatea traducerii cu textul
înscrisului, care a fost vizată de mine şi
port răspundere personală pentru
corectitudinea traducerii actului.
Undersigned, Poleacova Ana, sworn translator,
(English language), certify the authenticity of
the translation which corresponds to the text
of the authentic document, which was
confirmed by me and I do take personal
responsibility for the truthfulness of the
translation.
26.02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,