eng3 2-1-3 bloc 1a (cm).rtf f1b.pdf
Стр. 1–2
Translation from Romanian and Russian into English
2026-405
Reconstruction of the terminal
building of “Eugen Doga”
International Airport - Chisinau
(cadastral no. 0100120.236.01),
including partial replanning of
internal spaces and building
extension
Form No. 1B
(name of the facility) WinEstimate
Cost Estimate-Offer No. 2-1-3
BLOCK 1A Phase 2
Structural Steelwork Structures (ST section)
(name of works)
Coefficient for basic wages = 1,150
Coefficient for cost of machine operation = 1,150
No. Norm symbol
and resource
code
Description of works
Unit of
measure
(U.M.)
Quantity
according to the
design data
1 2 3 4 5
1. Structural Steelwork Structures
1 CL08A
Factory-fabricated metal elements
(columns, beams, trusses), delivered fully
assembled, mounted on site, in
lightweight structural framework
tonne 15,47
7214210026800 Metal structure installer man-
hours
622,668
9310060019920 Worker servicing ST man-
hours
88,953
2811106301200 Metal elements kg 15 779,40
2775276309886 Metal fabrications embedded in concrete kg 30,94
2873155901340 Welding electrode for low-alloy steel S 1125/2 E
50B 4
kg 6,962
2874115842700 Hexagonal nut M20 pieces 100,555
2874115802500 Hexagonal head bolt M20 pieces 100,555
2874115883700 Washer M20 pieces 100,555
2413547308164 Technical calcium carbide (carbide) S102 kg 1,006
2411115904512 Technical gaseous oxygen S2031 m³ 1,547
4011106202741 Electrical energy kw 6,962
3410520006728 Pneumatic crane up to 9.9 ton-force (TF) with
lattice boom
machine-
hours
2,669
2 IzD10A
Anticorrosion painting by brush of metal
products and structures with one coat of
anticorrosive primer based on red lead
and two coats of chlorinated rubber
tonne 15,47
1 2 3 4 5
enamel.
7141020013400 Industrial painter man-
hours
114,571
2430116100000 Chlorinated rubber enamel kg 120,666
2430226100814 Red lead primer G 355-6 kg 60,333
2430226109420 Thinner for anticorrosive varnishes D.006-1 NI
1708-61 A1
kg 8,509
2320166200676 White spirit kg 30,166
1711317306661 Cleaning cotton kg 15,083
3 CL31A
Protection of metal structures with
intumescent fire-retardant coating “Pirex-
Metal Plus”
m² 418,00
7134050013250 Insulator man-
hours
697,015
9310060019920 Worker servicing ST man-
hours
96,14
2430126104976 Fire-retardant paint “Pirex-Metal Plus” R90* kg 794,20
2430226101026 Anticorrosive primer GF 021 kg 56,43
1711317306661 Cleaning cotton kg 21,318
2320166200676 White spirit kg 62,70
2681126001472 Dry sandpaper 23 × 30 cm, grit 6 pieces 209,00
Total Structural
Steelwork Structures
Total
Social fund
Total
Transportation of materials
Storage expenses
Direct expenses
Overhead expenses
Total
Estimated profit
Total estimate:
Including wages
Subsemnata
Стр. 2
ial fund
Total
Transportation of materials
Storage expenses
Direct expenses
Overhead expenses
Total
Estimated profit
Total estimate:
Including wages
Subsemnata, Poleacova Ana, tradu cător
autorizat, (limba Englez ă), certific
exactitatea traducerii cu textul
înscrisului, care a fost vizată de mine şi
port răspundere personală pentru
corectitudinea traducerii actului.
Undersigned, Poleacova Ana, sworn translator,
(English language), c ertify the authenticity of
the translation which corresponds to the text
of the authentic document, which was
confirmed by me and I do take personal
responsibility for the truthfulness of the
translation.
26.02.2026
Semnătura
Signature
Translator’s stamp: /Republic of Moldova,
Authorization AT No. 461 of 10.02.2014, AT No. 500 of 21.07.2014,
English, French, Romanian, Russian, Translator
Предпросмотр носит справочный характер. Юридически значим только официальный оригинал в источнике.